Ordinance 29-10RECORD OF ORDINANCES 29 -10 Ordinance No. Passed 20 AN ORDINANCE ADOPTING THE 2011 -2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM WHEREAS, Section 8.03 (a) of the Dublin City Charter requires the City Manager to prepare and submit to City Council a five -year capital improvements program in accordance with the annual budget calendar as authorized by City Council; and WHEREAS, City Council has received and reviewed the Five -Year Capital Improvements Program (CIP) for the years 2011 -2015; and WHEREAS, the CIP represents a long -term financial plan, which establishes priorities, identifies project costs and phasing, identifies funding sources, and serves as aplanning document for capital improvements; and WHEREAS, the Administration has incorporated in the attached CIP all modifications as requested by City Council as a result of the CIP budget workshops. NOW, THEREFORE, BE IT ORDAINED by the Council ofthe City of Dublin, State of Ohio, _(,# elected members concurring that: Section 1 . The 2011 -2015 Five -Year Capital Improvements Program, attached hereto as an Exhibit be, and hereby is, approved. Section 2 . This Ordinance shall take effect and be in force on the earliest date permitted by law. Passed this t day of .1 /��� , 2010 Mayor - Presi ) Officer ATTEST: 01_ �� Clerk of Council CITY OF DUBLIN- Office of the City Manager 5200 Emerald Parkway • Dublin, OH 43017 -1090 Phone: 614-410-4400 • Fax: 614- 410 -4490 To: Members of Dublin City Council From: Tent' Foegler, City Manager Date: September 9, 2010 Initiated By: Marsha Grigsby,, Deputy City Manager /Director of Finance Bryan Thurman, Deputy Director of Finance K 1_� 0 Re: Ordinance No. 29 -10 - Adopting the 2011 — 2015 Five Year Capital Improvements Program (CIP) Summary The following is a recap of the Council workshop meetings for the 2011 — 2015 Capital Improvements Tax Program (CIP) on August 16, 2010 and August 30, 2010, including any requested follow -up information. The recap is broken down by category. A copy of the CIP project worksheets, reflecting programming by category is attached with changes highlighted. Any changes as a result of the workshop meetings have been incorporated into the final CIP document. Administration Adjustments Bridge Street Corridor - A significant focus area for 2011 and beyond will continue to be the Bridge Street Corridor. The intent is to develop a community -based vision for Bridge Street /State Route 161 from Interstate 270 to Sawmill Road, including the Historic District. Evaluation continues on the development and redevelopment opportunities of key sites within the corridor to create a more sustainable, walkable urban environment and to seek ways to better capitalize on one of the City's most treasured assets, the Scioto River. A separate line item has been added to the CIP with and 2015 programmed for potential improvements 5500,000 has been reserved for debt in 2012 — 2015. debt. Service an annual allocation of 5250,000 in years 2013, 2014 in this area. Additionally, an annual allocation of This funding could support S5 million to S6 million in Adiustrnents — No adjustments were made to the 2011 — 2015 Service CIP. Parks and Recreation - non -major Adjustments Ballantrae Park - Due to the popularity and increased utilization of the spray park, 530,000 has been programmed in 2010 for redesign of the filtration system with improvements programmed to be completed in 2011 at an estimated cost of 5250,000. The original filtration system was not designed to handle the volume of those who are currently utilizing the amenities of the park. Memo re. Ordinance 29 -10 2011 -2015 CIP follow -up September 9, 2010 Page 2 of 4 Follow -up information Riverside Drive Park — Information was requested concerning the possibility of partnering with Washington Township on the completion of this park. Parks and Open Space will contact Washington Township to discuss the possibilities and report their findings to Council. Campden Lakes/Wedgewood Glen Park Llewellyn Farms South Park Council requested the Administration meet with the residents in these developments to discuss future development of the parks. Parks and Open Space will contact the respective homeowners associations with the goal of being added to their agenda at their next homeowners meeting. As of the submission of this memo, no dates have been confirmed. Parks and Recreation — maior Adjustments — No adjustments were made to the 2011 — 2015 Parks and Recreation - major CIP Follow -up information Darree Fields - Discussions centered around the possible expansion of the dog park area. Currently, there are potential issues with obtaining easements due to both overhead electric transmission wires and underground gas transmission lines. Past attempts to contact the owners of the easements have been unsuccessful. The Administration will attempt to make contact with the owners to discuss the possibility of obtaining easements for the potential expansion of the dog park and report their findings to Council for future discussions. Police Adjustments — No adjustments were made to the 2011 — 2015 Police CIP Sanitary Sewer Adjustments — No adjustments were made to the 2011 — 2015 Sanitary Sewer CIP Additional requested information Unserved areas — The Administration is currently working on a report relating to cost estimates for the unserved areas of the City for water and sewer. This report should be completed within the next two months. Transportation — non -maior Adjustments - No adjustments were made to the 2011 — 2015 Transportation non -major CIP. Additional requested information Annual roadside improvement program — The City allocates $85,000 per year to improve the conditions along City roadways. The program is completed in conjunction with the Annual Street Maintenance program. Council requested information concerning locations where improvements are needed. Engineering staff will establish and provide a prioritized list of roadside improvement locations and criteria used in establishing the list. Annual sidewalk program — An annual allocation is provided to replace deficient sidewalks throughout the City. A condition assessment has been completed by Engineering, and sidewalk replacement is based on this Memo re. Ordinance 29 -10 2011 -2015 CIP follow -up September 9, 2010 Page 3 of 4 assessment. Timing of completion can also be based on the location of needed repairs. Engineering attempts to cluster repairs to allow for economies of scale and to provide a more efficient completion of necessary repairs by the contractor. Per Chapter 97.21 of the Dublin Codified Ordinances, it is the property owner's responsibility to "keep the sidewalks, curbs or gutters in repair." Although the City repairs sidewalks as a benefit to its residents, it is ultimately the responsibility of the property owner to maintain the sidewalks abutting their property. Paying for the cost of sidewalk repairs is unique to the City of Dublin. The more common practice is for the property owner to bear the cost of the sidewalk repairs. The property owner has the option of completing their own sidewalk repairs as another option. Engineering will provide information regarding the City's sidewalk program and the property owners' responsibilities and options at the upcoming Homeowners Association meeting. Transportation — maior Adiustments Railroad quiet zones — This project will add Supplemental Safety Measures (medians or extra gates) at each public road/rail crossing. Once installed, locomotive homs would not routinely sound along the CSX line for seven consecutive crossings. The crossings include three in Franklin County, two in Hilliard, one in Columbus and one crossing in Dublin. The City has applied for State Capital Budget funding for the project. The cost to install the crossing in the City has been programmed in 2011; however, to achieve the desired results, all crossings would need to be upgraded and it is unlikely all jurisdictions will move forward without state funding. We have programmed the project based on the recent funding request submitted for the State Capital Budget. To better understand the scope of this project, an additional allocation in the amount of $20,000 has been added in 2010 for a preliminary design of the crossings. Franklin County has committed up to $25,000 towards these costs. Bikeway connections /additions — As a result of the Bicycle Advisory Task Force (BATF) recommendations, the City has programmed additional funds in the CIP for both multi -use paths, bike lanes and sharrows. The $400,000 programmed in 2010 for Brand Road will be used for design of both the multi -use path and bike lanes. An additional $1,565,000 has been programmed in 2011 to complete a multi -use path and bike lanes on Brand Road between Muirfield Drive and Dublin Road. An additional $1,035,000 has been programmed in 2012 to complete bike lanes between Hyland Croy Road and Muirfield Drive. An additional allocation of $50,000 has been programmed in 2011 for the preliminary design and alignment of bike lanes on Muirfield Drive between Brand Road and Glick Road. Funds have been programmed in 2010 ($60,000) and 2011 ($120,000) to add sharrows to Emerald Parkway. In 2010, plans are to add sharrows to a portion of the roadway for evaluation, with the remaining roadway being completed in 2011 based on the results of the evaluation. Water Adjustments - No adjustments were made to the 2011 — 2015 Water CIP_ Memo re. Ordinance 29 -10 2011 -2015 CIP follow -up September 9, 2010 Page 4 of 4 Additional requested information Unserved areas — The Administration is currently working on a report relating to cost estimates for the unserved areas of the City for water and sewer. This report should be completed within the next two months. Stormwater Adjustments - No adjustments were made to the 2011 — 2015 Stormwater CIP. Recommendation It is recommended that Ordinance No. 29 -10 be adopted at the September 13, 2010 City Council meeting. CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 PROJECT PROJECT PRIOR 125 0 0 0 0 0 0 0 TOTAL NO. DESCRIPTION I YEARS 0 60 450 400 400 400 TOTAL BEYOND TO BE AB1101 Building maintenance /renovations $000 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED ADMINIS TRATION / NONMAJOR PROJECTS AL1101 Land acquisition 0 125 0 0 0 0 0 0 0 0 AU1101 Utility service improvements 0 0 60 450 400 400 400 1,710 0 1,710 AB1101 Building maintenance /renovations 0 620 930 355 260 325 305 2,175 0 2,175 AB0802 Technology improvements 254 205 280 130 0 0 0 410 0 410 AA1101 Contingencies 0 225 225 225 225 225 225 1,125 0 1,125 9113/2010 TOTAL 254 1,175 1,495 1,160 885 950 930 5,420 0 5,420 ADMINISTRATION / MAJOR PROJECTS AL1102 Parkland acquisition 0 650 650 1,725 1,725 1,725 1,725 7,550 01 7,550 A11101 Computer hardware /software 0 750 900 1,125 955 930 905 4,815 0 4,815 AB0601 Municipal facilities 1,112 150 115 0 0 0 0 115 1,260 1,375 AV1101 Fleet management program-replacements 0 1,110 1,065 780 1,020 565 240 3,670 370 4,040 AV1103 Fleet management program-equipment 0 365 295 345 360 525 415 1,940 0 1,940 AB0602 Historic Dublin 2,643 500 250 250 0 0 0 500 0 500 AB1301 Bridge Street Corridor 0 0 0 0 250 250 250 750 0 750 9/13/2010 TOTAL 3,755 3,525 3,275 4,225 4,310 3,995 3,535 19,340 1,630 20,970 Changes SACIP - Administratlon @011- 2015%ADMINCIP summary.xls CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 PROJECT PROJECT PRIOR 01 01 01 ol ol 0 0 0 TOTAL NO. DESCRIPTION I YEARS ol ol 1 ol ol 1 TOTAL BEYOND TO BE $000 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED AB1002 9/13/2010 SERVICE \ MAJOR PROJECTS Upgrade fuel facility for Compressed Natural G 01 2,1751 01 01 01 ol ol 0 0 0 TOTAL I ol 2,1751 ol ol ol ol ol ol 0 0 Changes SKIP - Seni0e12011 - 201 SSERVICECIP summary.As CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 - 2015 PROJECT PROJECT PRIOR 20 0 25 0 0 0 25 0 TOTAL NO. DESCRIPTION I YEARS 35 0 40 0 0 0 TOTAL BEYOND TO BE PP0805 O ticom ($000) 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED POLICE / NONMAJOR PROJECTS PP0803 Replacement lasers 17 20 0 25 0 0 0 25 0 25 PP0804 Replacement radars 28 35 0 40 0 0 0 40 0 40 PP0805 O ticom 15 0 25 25 0 0 0 50 0 50 PP1002 Covert surveillance & investigative a ui ment 0 40 0 0 0 0 0 0 0 0 PP1003 Uninterrupted power supply replacement 0 35 0 0 0 0 0 0 0 0 PP1102 Dublin Emergency Warning System Upgrade 0 0 280 0 0 0 0 280 0 280 PP1103 Portable Sign Board S stem 0 0 0 0 35 0 0 35 0 35 PP1104 Digital Video Recorders for Motors 0 0 351 0 0 0 0 i 35 0 i 35 9/13/2010 TOTAL 1 601 1301 3401 901 01 01 4651 01 465 POLICE / MAJOR PROJECTS PP0004 Justice Center renovations 1071 01 01 01 01 01 01 01 1,3201 1,320 PP1501 Radio communications tower 0 0 0 0 0 0 0 0 500 500 P1 PSAP equipment re lacement 0 0 420 0 0 0 0 420 0 420 PP1601 Radios stem upgrade 01 0 01 P 0 0 0 0 750 750 9/13/2010 TOTAL 107 0 420 0 0 0 0 420 2,5701 2,990 " FOJ funds Changes SBCIP - Police�2011 - 2015TOLCIP summary As CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 PROJECT PROJECT PRIOR 01 01 01 0 0 0 4001 400 TOTAL NO. DESCRIPTION YEARS 01 01 01 01 01 4001 TOTAL BEYOND TO BE 1,1301 3601 ($000) 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED ES1110 9/13/2010 SANITARY SEWER SYSTEM \ NONMAJOR North Fork sewer - capacity improvement 0 0 01 01 01 0 0 0 4001 400 TOTAL 0 01 01 01 01 01 01 01 4001 400 SANITARY SEWER SYSTEM \ MAJOR PROJECTS ES0701 I Sewer lining and repair 1 2,2231 8501 01 2,0001 01 01 01 2,0001 01 2,000 ES0601 I South Fork sanitary sewer extension 1 71 3301 3601 01 01 01 01 3601 01 360 9/13/2010 ITOTA 1 2,2301 1,1301 3601 2,0001 01 01 01 2,3601 01 2,360 Changes SKIP - Sanitary Sawem\2011 - 20151SNSEWCIP summary.xls CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 PARKS & RECREATION / NONMAJOR PROJECTS AR1101 Park renovations/improvements PRIOR 395 300 450 450 450 450 2,100 0 TOTAL PROJECT DESCRIPTION YEARS 30 250 0 1 0 1 TOTAL BEYOND TO BE NO. Avery Park $000 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED PARKS & RECREATION / NONMAJOR PROJECTS AR1101 Park renovations/improvements 0 395 300 450 450 450 450 2,100 0 2,100 GRO108 Ballantrae Park 5,079 30 250 0 370 0 0 620 0 620 GRO502 Avery Park 1,404 445 0 0 0 0 0 0 0 0 GR0505 Skate Park redesign 0 0 0 40 90 0 0 130 0 130 GR0710 Kiwanis Boardwalk extension 0 0 85 0 0 0 0 85 0 85 GRO910 Belvedere Park 0 150 0 0 0 0 0 0 0 0 GRO911 Riverside Drive Park 0 50 505 0 0 0 0 505 275 780 GRO913 Post Preserve Park 62 135 0 0 0 0 0 0 0 0 GRO914 Dublin Sprinq Park 0 20 150 0 0 0 0 150 0 150 GR1010 Cam den Lakes Med ewood Glen Park 0 0 0 150 0 0 0 150 0 150 GR1011 Llewellyn Farms South Park 0 0 0 0 0 0 0 0 210 210 GR1012 Emerald Parkway Bridge Park 0 0 45 435 0 0 0 480 0 480 GR1110 Riverwalk Emerald Parkway to SR161 0 0 0 0 40 0 995 1,035 0 1,035 GR1111 Sycamore Ride Park 0 0 0 0 0 490 0 490 0 490 GR0008 Martin Commons Park 2 250 0 0 0 0 0 0 0 0 GR1112 Hutchins Property 0 0 275 0 0 0 0 275 0 275 GR1113 IGS Park TIF 0 0 0 280 0 0 0 280 0 280 GR1114 Holder Tract 0 0 80 0 1 0 0 0 i 80 1,000 i 1,080 GR1115 I Dublin Community Pool North Renov 0 1 0 1 525 1 320 1 3201 01 01 1,165 01 1,165 9/13/2010 ITOTAL 6,547 1 1,475 1 2,2151 1,6751 1,270 1 940 1 1,445 1 7,545 1,4851 9,030 Changes SACIP - Parks 8 RecreaUon\2011- 20151PARKSCIP summary.As CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 PARKS & RECREATION /MAJOR PROJECTS GR9901 Darree Fields development PRIOR 260 1 380 30 200 0 0 610 1,215 TOTAL PROJECT DESCRIPTION YEARS 85 9 0 0 100 565 75 TOTAL BEYOND TO BE NO. Emerald Fields N.E. Quad Park ($000 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED PARKS & RECREATION /MAJOR PROJECTS GR9901 Darree Fields development 5,346 260 1 380 30 200 0 0 610 1,215 1,825 GR9903 Amberlei h Community Park 826 85 9 0 0 100 565 75 740 715 1,455 GR9904 Emerald Fields N.E. Quad Park 4,983 0 0 520 0 0 0 520 0 520 GR9902 Coffman Park expansion 0 50 0 0 0 0 0 0 1,505 1,505 9/13/2010 TOT AL 11,155 1,295 380 550 300 565 75 1,870 3,435 5,305 Changes SACIP - Parks & Recreakon= 1.20151PARKSCIP summary.xls CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 TRANSPORTATION /NONMAJOR PROJECTS AT1101 jAnnual street maintenance program PRIOR 2,725 3,000 3,150 3,300 3,465 3,640 16,555 0 TOTAL REF. PROJECT YEARS 85 85 85 85 85 85 TOTAL BEYOND TO BE NO. DESCRIPTION $000 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED TRANSPORTATION /NONMAJOR PROJECTS AT1101 jAnnual street maintenance program 0 2,725 3,000 3,150 3,300 3,465 3,640 16,555 0 16,555 AT1102 Annual roadside improvement program 0 85 85 85 85 85 85 425 0 425 AT1103 Annual bike path maintenance 0 40 350 350 100 100 100 1,000 0 1,000 AT1104 Annual bike path connections /additons* 0 0 45 230 20 0 0 295 0 295 AT1106 Annual sidewalk program 0 125 125 125 125 125 125 625 0 625 AT1107 Annual parking lot maintenance 0 355 100 100 100 100 100 500 0 500 AT1108 Annual pedestrian tunnel maintenance 0 100 250 200 50 50 50 600 0 600 AT1109 Annual infrastructure repairs(previously programmed in Service 0 75 75 75 75 75 75 375 0 375 AT1110 Annual guardrail replacement 01 65 651 65 651 65 0 260 0 260 AT1111 Annual bike rack installation 0 0 25 25 25 25 25 125 0 125 AT1105 Traffic calming program 0 0 0 0 0 0 0 0 0 0 ET0403 Pedestrian tunnels 746 0 0 0 0 0 0 0 650 650 ET0504 Metro Center street lighting/pedestrian improvements (TIF) 184 750 0 0 0 0 0 0 0 0 ET0711 Riverside Drive overlay-SR 161 to north limits 0 265 0 0 0 0 0 0 0 0 ET1118 Riverside Drive /Hard Road turn lane 76 0 0 250 0 0 0 250 0 250 ET1201 Shannon Glen Park bikepath bridge 0 0 0 0 0 0 0 0 180 180 9/13/2010 TOTAL 1,006 4,585 4,120 4,655 3,945 4,090 4,200 21,010 830 21,840 * Large connections(Brand, Glick, Dublin Rd.) moved to major. Changes SACIP- Transpo0ation @011- 2015 \TR NSCIPsummary.xls CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 TRANSPORTATION / MAJOR PROJECTS ET0609 1COIC #1 -West area improvements PRIOR 0 0 0 0 0 0 0 2 TOTAL REF. PROJECT I YEARS 1 0 40 0 0 0 1 TOTAL BEYOND 1 TO BE N0. DESCRIPTION ($000 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED TRANSPORTATION / MAJOR PROJECTS ET0609 1COIC #1 -West area improvements 0 0 0 0 0 0 0 0 2 2,235 ET0607 COIC #2-industrial parkway relocation TIF 9,789 0 40 0 0 0 0 40 0 40 ET0606 COIC #3- Eiterman Rd relocation 545 0 0 0 0 0 0 0 3,725 3,725 ET0611 COIC #5- SR 161 improvements 1,285 0 40 0 0 0 0 40 0 40 ET0003 COIC #6- US33 /SR 161 /Post Road interchange 14 088 0 0 0 0 0 0 0 24,750 24,750 ET0902 COIC #7 -Post Preserve access modification 191 0 0 0 0 0 0 0 1,565 1,565 ET0103 Tuttle Crossing Blvd. Ext.-Wilcox Road to Ave Road TIF 15 0 0 150 500 1,800 0 2,450 7,000 9,450 ET0104 Emerald Parkway-Riverside Drive to Billingsley Creek TIF 1,625 1,775 9,500 210 0 0 0 9,710 0 9,710 ET0205 Emerald Parkway-Rings Road to Tuttle Crossing Blvd. TIF 464 2,500 0 1 0 0 0 0 1 0 0 0 ET1119 Relocated Rings Road 0 0 0 90 350 725 0 1,165 0 1,165 ET1202 1 Frantz Road utility burial (TIF) 0 0 75 0 750 0 0 825 0 825 ET0810 ET1101 ET1103 Frantz Road - Dublin Road connector Potential TIF Railroad Quiet Zone - Houchard to Leap LED Street Light Replacement 229 0 0 0 20 0 2,650 470 300 0 0 2,000 0 0 0 0 0 0 0 0 0 2,650 470 2 0 0 0 2,650 470 2,300 Intersection Improvements; ET0405 Hyland-Croy Road /Brand Road (TIF) 273 0 2,700 0 0 0 0 2,700 0 2,700 ET0410 Ave - Muirfield /Perimeter Loo /Perimeter Drive (TIF) 0 101 500 3301 0 3,500 0 4,330 1,800 6,130 ET0508 Riverside Drive/SR161 (TIF) 232 L? , 500 400 0 0 0 0 1 400 3,500 3,900 ET0511 Ave - Muirfield/Tull more/Valle Stream/Avery Road 51 0 100 0 725 0 0 8251 0 825 ET0605 I Sawmill Road /Hard Road (TIF) 235 200 550 0 1,700 0 0 2,250 0 2,250 ET1001 Cos ra Road/ Shier Rings 136 0 1,850 50 0 0 0 1,900 0 1 ET0809 Hyland Cro - McKitrick Road 0 0 0 180 50 0 1,230 1,460 0 1,460 ET0904 Perimeter Drive/Commerce Parkway TIF) 117 0 1 0 0 0 0 1,500 0 1,500 ET1401 1- 270 /US 33 interchange phase 1 improvements Potential TIF 0 500 0 0 0 2,400 0 2,400 0 2,400 ET1003 Dublin Road and Glick Road* 01 250 01 0 01 0 0 0 2,650 2,650 ET1102 US 33 /SR 161 /Post Road eastbound rams 0 0 150 0 0 0 0 150 0 150 Blkepath connections/additions: ET1004 Brand Road 82 400 2,005 1,035 0 0 0 3,040 0 3,040 ET1203 Dublin Road South 92 0 0 740 430 0 0 1,170 0 1,170 ET1204 Glick Road 0 0 0 340 60 290 0 690 760 1,450 ET1104 Muirfield Drive bike lanes 0 0 50 0 0 0 0 50 0 50 ET1204 Memerald Parkway sharrows 0 60 120 0 0 0 0 120 0 120 9/13/2010 TOTAL 29,449 8,215 23,000 5,125 4,565 8,715 1,230 42,635 47,985 90,620 * Does not include ROW acquisition and utility relocation Changes SACIP- Tmnspona0oM2011- 2015 \TRANSCIP summary.xls CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 20.1.1.2015 TDAK1QPnRTAT!01 1! AAA OR PROJECTS ET0901 IUS 33 widenin from 1 -270 to Post Road PRIOR 0 0 0 0 0 0 0 2,2401 TOTAL REF. PROJECT YEARS 0 0 0 0 0 0 TOTAL BEYOND TO BE NO. DESCRIPTION $000) 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED TDAK1QPnRTAT!01 1! AAA OR PROJECTS ET0901 IUS 33 widenin from 1 -270 to Post Road 781 0 0 0 0 0 0 0 2,2401 2,240 Blazer Parkway/Frantz Road TIF 0 0 0 0 0 0 0 0 675 675 Ave Road /Brand Road TIF 0 0 0 0 0 0 0 0 1,150 1,150 Riverside Drive /Summitview Drive 46 0 0 0 0 0 0 0 575 575 Shier Rings Road -Ave Road to Emerald Parkway 0 0 0 0 0 0 0 0 5,350 5,350 V Rings Road -west of Ave Road 0 0 0 0 0 0 0 0 6,125 6,125 Cos ra Road improvements-proposed street intersection 0 0 0 0 0 0 0 0 850 850 Shier Rings Road-Cos gray Road to Houchard Road 0 0 0 0 0 0 0 0 1,680 1,680 Old Ave Road relocation 0 0 0 0 0 0 0 0 3,350 3,350 Shier Rings Road - Eiterman Road to Cos gray Road 0 0 0 0 0 0 0 0 1,760 1,760 ET1517 Shier Rings Road -Ave Road to Eiterman Road 0 0 0 0 0 0 0 0 1,740 1,740 ET1518 Hyland Croy & Post Preserve roundabout 0 0 0 0 0 0 0 0 1,300 1,300 ET1520 Emerald Parkway/Shier Rings Road improvements 0 0 0 0 0 0 0 0 900 900 ET1521 Muirfield Drive and Memorial Drive 0 0 0 0 0 0 0 0 1,930 1,930 ET1522 Relocated Tuller Road 0 0 0 0 0 0 0 0 4,370 4,370 ET1523 Perimeter widening - Holt Road to Commerce Parkway 0 0 0 0 0 0 0 0 4,800 4,800 ET1624 US33 /SR 161 /Frantz Road intersection 0 0 0 0 0 0 0 0 0 0 9/13/2010 TOTAL 29,573 8,215 21,965 5,125 4,565 8,715 1,230 41,600 86,780 128,380 Changes SACIP - TransporlalionU011- 20151TRANSCIP summary.xls CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS � PROJECT PRIOR 0 0 0 0 0 0 0 0 TOTAL NO. DESCRIPTION I YEARS 1 0 500 0 1 1 TOTAL BEYOND 1 TO BE AW0604 Booster station upgrades ($000) 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED \NATFR nIRTRIRI ITION SYSTF_M \ NONMAJOR PROJECTS AW1102 Water line oversizing 0 0 0 0 0 0 0 0 0 0 AW1001 Water line replacement 0 0 0 500 0 470 0 970 0 970 AW0604 Booster station upgrades 0 195 580 85 0 0 0 665 50 715 EW0102 Water tower maintenance 472 495 500 0 0 305 305 1,110 680 1,790 EW1102 Post Road water tower decommissioning 0 0 85 0 0 0 0 85 0 85 EW1501 12" waterline - Ballantrae Section 9 to Cosgray 0 0 0 0 0 0 0 0 170 170 9/13/2010 TOTAL 472 690 1,165 585 0 775 305 2,830 900 3,730 WATER nISTRIRI ITInN SYSTFM \ MAJOR PROJECTS EW1201 Dublin Road water tower 01 2501 150 2,7001 0 01 01 2,850 0 2,850 EW1101 Rings Road Waterline 0 0 0 0 0 730 0 730 0 730 9/13/2010 ITOTAL 1 01 2501 1501 2,7001 01 7301 01 3,58 0 3,580 Changes SACIP- Water\2011- 2016WATERCIP summary.xls CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011_2015 PROJECT PROJECT PRIOR 3001 300 300 300 300 300 1,500 0 TOTAL NO. DESCRIPTION YEARS TOTAL BEYOND TO BE 9/13/2010 TOTAL ($000) 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED STORMWATFR SYSTEM \NONMAJOR PROJECTS AF1101 Annual stormwater maintenance 0 3001 300 300 300 300 300 1,500 0 1,500 0 0 9/13/2010 TOTAL 2,653 0 50 0 465 205 0 0 0 0 9/13/2010 TOTAL ol 3001 3001 3001 3001 3001 3001 1,5001 0 1,500 RTnRMWATFR SYSTEM \ MAJOR PROJECTS EF0201 I Stormwaterimprovements 2,6531 01 501 01 4651 2051 ol 720 011111 20 9/13/2010 TOTAL 2,653 0 50 0 465 205 0 720 0 720 Changes SKIP - Sto"watef2011- 2015 \STRMCIP summaryAs 2011-2015 Capital Improvements Program Adopted by: Ordinance No. 29 -10 2011-2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM ANNUAL BUDGET PROCESS The City of Dublin has implemented an annual schedule for the preparation and adoption of the Five -Year Capital Improvements Program (CIP) and the Operating Budget, which includes the annual CIP budget. The following time frames are key elements in the annual budget calendar: First quarter City Council goal setting session(s) End of March Adoption of goals by City Council End of June Completion of the Administration's recommended Five -Year CIP July /August City Council review of recommended CIP End of October Completion of the Administration's recommended Operating Budget November City Council review of recommended Operating Budget By December 31 Adoption of Operating Budget and Appropriations Ordinances by City Council The Five -Year CIP and the Operating Budget are two critical documents prepared annually. The relationship between these two documents is summarized by the following points: Five -Year CIP • Represents a long -term financial plan, including funding sources. • Establishes priorities and serves as a planning document or blueprint for the City's investment in capital infrastructure. • Provides a breakdown of major project costs and phasing. • Does not appropriate money. • As indicated by the above points, the Operating Budget is the document which authorizes the actual funding for the major and non -major capital projects. Operating Budget - Annual CIP Budget • Appropriates money to implement the first year of the Five -Year CIP. • Appropriates money to implement a "phase of a major, multi -year project." • Appropriates money for non -major capital expenditures, including those of a continuing nature (i.e. fleet and equipment management, computers). 1 -1 9/13/2010 MAMCapital Budgets\2011CIP \Final Document \1 -1 Capital Budget Process.doc 2011-2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM FINANCIAL GUIDELINES The Five -Year CIP establishes the City's blueprint for investment in its capital infrastructure. This document is used as a tool to help ensure that the City's long and short-term capital investments are made in the context of careful consideration of the City's needs as well as the resources available to fund all projects. The financial guidelines used in the preparation of the CIP will provide assurance that the City can meet, in a full and timely manner, both our debt service obligations and all other obligations competing for the available resources. It is our objective to complete as many needed capital improvement projects as financially possible while maintaining flexibility and the ability to adapt to changes as they occur. There are several key guidelines that the Administration utilized in determining the City's fiscal capacity to complete capital projects over the next five years. These are summarized as follows: • The five -year plan will be updated annually. • 25 percent of the City's two percent income tax revenue shall be made available to fund capital improvements. This allocation is in accordance with Ordinance No. 17 -87 and the ballot language approved by the voters in November 1987. • Of the 25 percent of the total income tax revenues which are utilized for capital improvements, 60 percent of that amount will be allocated to fund long -term debt, and 40 percent to fund projects and capital expenses on a cash basis. The reasons for this guideline are: a) It is important to stress that funding projects with long -term debt obligates the use of public funds for the next 20 years in most cases. The more long -term debt which is incurred now significantly reduces the options available to future City Councils to fund needed projects. b) The City has determined that paying cash for projects where financially possible (pay -as- you -go financing) will increase our flexibility in the future. In utilizing pay -as- you -go financing, revenue projections and estimated fund balances will be reviewed and evaluated to assure that sufficient reserves are maintained. C) It is not economical to issue debt for some projects. d) The estimated life of some projects does not meet the criteria to issue long -term debt. 2 -1 9/13/2010 MAMCapital Budgets12011CIP \Final Documenfl2 -1 to 2 -3 Financial Guidelines.doc • Our philosophy for projecting income tax revenues is to be conservative. Income tax revenues through July 2010 were up 2.6% compared to the same period of time in 2009. Based on the July year -to -date income tax collections and an analysis of the remaining months of the year, we are projecting income tax revenues to be "flat" in 2010. Due to the uncertainty of the economic recovery, revenues are projected to remain "flat" in 2011. Beyond 2011 we are projecting moderate rates of growth in income tax revenues as follows: 2012 - 0.5% 2014 - 2.00% 2013 - 1.5% 2015 - 2.00% In addition to funding projects on a cash basis over the next five years, the purpose of these projections is to determine the amount of long -term debt that can be retired using income tax revenues. To incur substantial long -term debt based upon a less than conservative rate of growth could result in a serious financial strain on the City if those growth projections are not achieved. Issuing long -term debt, in most cases, will result in debt service payments over a 20 year period. Issuing long -term debt based on less than conservative growth estimates would not be a financially sound approach. • To the degree that the income tax revenue rate of growth exceeds our projections in any given year, the excess revenue should be utilized to fund projects on a cash basis the following year or to reduce the amount of debt on projects identified to be financed with debt proceeds. • The availability of adequate financial reserves or balances that can be used to address unforeseen contingencies or take advantage of opportunities is a critical element in evaluating financial strength. The City's practice is to maintain a General Fund balance of at least 50% of the General Fund expenditures, including operating transfers. The 2009 General Fund year -end balance equaled 64.9% of expenditures and operating transfers. The percentage as of the year -end 2010 is projected to remain above 60 %. • Since a significant portion of the debt outstanding and future capital improvements are utility (water and sewer) related, the systems' user fees and capacity charges (tap permits) will continue to be evaluated. Water related improvements will be programmed based on the Water Fund's available cash reserves and estimated annual revenues. The repayment of the Ohio Water Development Authority loan for the Upper Scioto West Branch Interceptor will be retired utilizing the Sewer Fund's available cash reserves and estimated annual revenues. Every effort will be made to structure the debt service obligations for utility infrastructure improvements in such a manner as to utilize the Sewer Fund and Water Fund available cash reserves and estimated annual revenues to the fullest and thereby reducing or eliminating the dependency on income tax revenues. The goal in the Water and Sewer funds has been to maintain fund balances equal to approximately 25% of the total historical value of each system. The 2009 combined Water and Sewer Fund balances, including advances, equal 24.35% of the total historical value of both systems. 2 -2 9/13/2010 MAFA \Capital Budgets\2011CIP \Final Document\2 -1 to 2 -3 Financial Guidelines.doc In 2011, approximately 80% of the property tax revenue from the City's "inside millage" will be allocated to the Capital Improvements Tax Fund. A portion of the funding will be utilized to reimburse the General Fund for advances made to acquire right -of -way for the US33 /SR161/Post Road project and the remaining funding will be utilized to fund capital projects. The property tax revenue from the City's inside millage (1.75 mills) was allocated 100 percent to the Parkland Acquisition Fund from 2001 -2006. From 2007 - 2009, the City began allocating .95 mills of the total 1.75 mills to the Parkland Acquisition Fund and the remaining .80 mills allocated to the Capital Improvements Tax Fund, we will return to this allocation for 2012 - 2015. The maximum amount of income tax supported debt to be issued is 10 percent less than the estimated maximum amount of debt that can be supported by the income tax revenue allocated as available for annual debt service obligations, see page 3 -2. This guideline provides an additional buffer in the event that income tax revenues fall short of projections or that an unexpected increase in interest rates occurs. As a matter of general policy, the City will do the following in order to be able to fund additional projects needed to serve the citizens of Dublin: a) Pursue federal, state and local assistance in the form of grants, low interest loans, cost - sharing, etc. b) Utilize assessment procedures for projects which have a reasonably well defined group of beneficiaries and which legally lend themselves to this type of financing. c) Look increasingly at ways to obtain revenue through user fees as a means to fund capital projects or as a way to free -up other income tax dollars so that they can be used to fund capital projects. d) Utilize, where appropriate, economic development incentives such as tax increment financing. As projects are proposed for funding, the statutory debt limitations will be reviewed to ensure compliance. The five -year program provides for significant capital programming, especially given the current economic times. The programming of projects needs to be distributed over the five -year period so that as we update our capital program each year, we can evaluate current conditions, including the capital needs, revenue growth, and respond to new priorities. 2 -3 9/13/2010 MAMCapital Budgets\2011CIP \Final Document\2 -1 to 2 -3 Financial Guidelines.doc 2011-2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM REVENUE PROJECTIONS The most significant funding source for the Five -Year Capital Improvements Program (CIP) is the City's income tax revenue. Projecting income tax revenues for the five year period is a significant element in determining resources available for capital programming. Section 2 Financial Guidelines, outlines the financial guidelines used in determining our fiscal capacity to complete capital projects. In addition to the income tax revenues, the projects associated with the water and sewer systems will be funded in whole or in part by revenues from those systems (i.e. user charges and tap permit fees). The following pages provide projections for income tax revenues and projections for the water and sewer system operations. The assumptions used for the projected water and sewer system operations are included. Section 6 reflects the debt financed projects that are also supported by service payments from tax increment financing districts and property tax revenue from "inside millage." The current five -year CIP assumes 100% of the OEPA /OWDA low- interest loan for the Upper Scioto West Branch Interceptor will be repaid from Sewer Fund revenues. Based on annual reviews, user charges for the sewer system were increased effective January 1, 2008, 2009 and 2010 with an additional adjustment authorized for January 1, 2011 and the capacity charge for a 3/4" tap was increased to $2,100 effective 1/1/2009. We will continue to closely monitor the revenues and the available resources in the Sewer Fund. Based on maintenance needs of the sanitary sewer system, it is anticipated that additional user charges will be needed in the future. 3 -1 9/13/2010 MAWCapital Budgets\2011CIP \Final Document \3 Revenue Projections section 3\3 -1 to 3 -9 Revenue projections.doc 2011 -2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM INCOME TAX REVENUE PROJECTIONS 2009 2010 2011 2012 2013 2014 2015 Income Tax Revenue* $65,907,592 $65,907,600 $65,907,600 $66,237,138 $67,230,695 $68,575,309 $69,946,815 Revenue for capital projects ( 25% of income tax revenue 16,476,898 16,476,900 16,476,900 16,559,285 16,807,674 17,143,827 17,486,704 (1)Revenue available for cash capital projects 6,590 759 6,590,760 6,590,760 6,623,714 6,723,070 6,857,531 6,994,682 (2)Revenue available for debt financed projects 9,886,139 9,886,140 9,886,140 9,935,571 10,084,604 10,286,296 10,492,022 Recommended maximum amount of ou�bt 3 75,918,559 71,802,148 81,621,0961 73,080,185 71,737,270 69,826,745 69,527,696 * Income tax revenues for 2008 and 2009 reflect actual collections. The remaining years reflect an estimated increase over the previous year as follows: 2009 - decrease of 6.14% from 2008 2010 - "Flat" 2011 "Flat" 2012 -0.5% 2013 -1.5% 2014 -2.0% 2015 -2.0% (1) 40% of the 25% designated for capital improvements is further designated for cash capital projects. (2) 60% of the 25% designated for capital improvements is further designated to retire debt issued for capital projects. (3) Forwarded from page 5 -3. Amount is based on existing income tax supported debt and projections for additional debt that can be supported by income tax allocated for debt service. 09/13/2010 M :TA%Ca0a1 autlgeWD11C"Flnal nocumxnt 9 Revenue Pr Wions section 312 income Tax Revenues.xismcome Taxes 3-2 2011-2015 Five -Year Capital Improvements Program Income Tax Revenue Actuals /Projections 80,000,000 70,000,000 60,000,000 50,000,000 40,000,000 30,000,000 20,000,000 3 -3 �?o �0 �O �O `�O 2 0 �O �O �O �O 1 0 - O o * 0 0 oo lO fl 1 2 l ly fs 2011.2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM STATEMENT OF PROJECTED REVENUE, EXPENSES AND CHANGES IN SEWER FUND CASH BALANCE 2010 2011 2012 2013 2014 2015 Revenues: User charges Tap fees Interest Other Income tax subsidy Expenses: Salaries /wages Benefits /uniforms Utilities Contract services Repairs /maintenance Other Capital expenditures Debt service: Existing -prior to 1992 USWBI 2009 issue 2013 issue Net cash (required) provided Advances -out Advances -in Beginning balance Ending balance 09/13/2010 $1,810,000 $1,752,646 $1,762,636 $1,772,626 $1,782,616 $1,792,606 175,000 150,000 150,000 150,000 150,000 150,000 215,250 232,395 214,045 245,275 232,400 218,465 165,000 0 0 0 0 0 124,719 0 0 0 0 0 2,489,969 2,135 2,126,681 2,167,901 2,165,016 2,161,071 463,500 486,675 506,142 526,388 547,443 569,341 170,900 177,736 184,845 192 199,929 207,926 575 610 646 685 726 769 125,000 50,000 50,000 50,000 50,000 50,000 82,950 150,000 150,000 150,000 150,000 150,000 10,000 15,000 15,000 15,000 15,000 15,000 852,925 880,021 906,634 934,312 963,098 993,036 457,242 360,000 124,719 0 0 0 0 0 1,350,721 1,350,721 1,350,721 1,350 1,350,721 1,350,721 154,952 155,815 154,015 152,215 155,415 153,562 0 0 160,000 160,000 160,000 160,000 1,630,392 1,506,536 1,664,736 1,662,936 1,666,136 1,664,283 (450,590) (611,516) (444,689) (429,346) (464,218) (496,248) 0 1,485,700 8,196,973 7,746,384 7,134,868 8,175,879 7,746,533 7,282,315 $7,746,384 $7,134,868 $8,175,879 $7,746,533 $7,282,315 $6,786,067 K`FA \Capital 3ud9etsV0110IPTmei Document \3 Revenue Projections section 3\ 3 -4 2011-2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM SEWER FUND ASSUMPTIONS Projected User Charges and Capacity Charges (Tap Fees) Assumptions: • Revenues based on estimated ERUs and fees as authorized by Ordinance 64 -09. • Effective 1/1/2010 and 1/1/2011, an increase of .25 MCF in user charges for sewer was approved. • Effective 1/1/2010, a reallocation of .25 per MCF in user charges from water to sewer was approved. • Average number of ERUs for 2010 reflects a growth of 83. This is based on the number of residential building permits issued in 2009 for new units. • Average number of ERUs for 2010 and forward are the total of the estimated previous year's average number of ERUs at the beginning of the year and the previous year's estimated ERU growth. • Estimated ERU growth for 2011 through 2015: 2011 -75 2012-75 2013 -75 2014-75 2015 -75 • Beyond 2015 estimated ERU growth: 2016 - 2021 - 100 Statement of Projected Revenue, Expenses and Charges in Sewer Fund Cash Balance Assumptions: • Revenues for user charges and tap fees are based on the schedule of Projected User Charges and Capacity Charges. • Interest income is based on the previous year's ending fund balance and an interest rate of 3 percent during the five year period. 3 -5 9/13/2010 M AWCapital Budgets\2011CIP \Final Document \3 Revenue Projections section 3 \3 -1 to 3 -9 Revenue projections.doc Sewer Fund Assumptions (Continued) • Subsidy for debt service is the debt service obligation for the 1990 bond issue for lift station improvements. The debt matures in 2010. • Debt service obligations for the USWBI (Upper Scioto West Branch Interceptor) assume the debt will be retired 100% from Sewer Fund resources. • The 2012 debt service issue is based on the current plan to issue $2.0 million in long -term debt for relining sanitary sewer lines. On February 11, 2009, the Ohio Environmental Protection Agency (OPEA) issued a binding "Director's Final Findings and Orders" (the Findings) to the City. The Findings indicate that the City operates its sanitary sewer system in connection with the City of Columbus sanitary sewer system, and that Columbus cannot comply with its OEPA consent order unless it obtains accurate information about sanitary flow and clear water infiltration and inflow (I and I) that contribute to their sanitary sewer overflows, from all connected suburban systems. Pursuant to the Findings, the OEPA ordered the City to 1) complete a Sewer System Evaluation Study (SSES) within either five years (for the entire system) or fifteen years (for an phased -in area -by -area approach), to identify sources and quantities of I and I /SSO, describe all feasible cost - effective actions needed to correct any such identified system deficiencies and establish a task prioritization and timetable for implementing them; 2) issue a Capacity, Management, Operation and Maintenance Program report within three years and update it biannually thereafter, to help best manage the City's sewer system; 3) submit an "SSO Emergency Response Plan" to the OEPA within 180 days to establish a process to identify and report any SSO that endangers the public health; and 4) implement a Public Notification Program within 90 days to inform the public of the location of, and possible health or environmental impacts associated with, any SSO occurrence. In an effort to reduce I and I in the system, the debt service obligations programmed in 2012 are for debt issues that will be used to finance the relining of existing sanitary sewer lines. The Statement of Projected Revenue, Expenses and Changes in Sewer Fund Cash Balance were prepared through the year 2020. Using the above assumptions, sufficient revenue to maintain a "positive" cash balance will be available through the year 2020, and the projected balance will not meet the goal of 25% of the historical value of the system assets. However, the 2009 combined Water and Sewer Fund balances, including advances, equal 24.35% of the total historical value of both systems. The rate of growth, the user fees and capacity charges will continue to be evaluated to determine the need to adjust rates in the future. 3 -6 9/1312010 MAWCapital Budgets\2011 CIP \Final Document \3 Revenue Projections section 3 \3 -1 to 3 -9 Revenue projections.doc 2011 -2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM STATEMENT OF PROJECTED REVENUE, EXPENSES AND CHANGES IN WATER FUND CASH BALANCE 2010 2011 2012 2013 2014 2015 Revenues: User charges Tap fees Interest Fire hydrant permits /Other Subsidy for debt service Expenses: Salaries /wages Benefits /uniforms Utilities Equipment maintenance Contract services Hydrant maintenance Other Capital expenditures Debt service: Existing 1994 issue 2009 issue 2012 issue Net cash (required) provided Advances -out Advances -in Transfer -out Beginning balance Ending balance $870,000 $819,063 $822,825 $826,587 $830,349 $834,111 160,000 135,000 135,000 135,000 135,000 135,000 252,300 378,201 351,580 345,926 367,721 344,780 2,500 1,000 1,000 1,000 1,000 1,000 279,660 0 0 0 0 0 1,564,460 1,333,264 1,310,404 1,308,512 1,334,070 1,314,891 83,000 87,150 90,636 94,261 98,032 101,953 30,700 32,235 33,524 34,865 36,260 37,710 140,600 147,630 153,535 159,677 166,064 172,706 2,000 2,120 2,247 2,382 2,525 2,676 155,000 75,000 75,000 75,000 75,000 50,000 46,200 48,510 50,450 52,468 54,567 56,750 8,400 15,000 15,000 15,000 15,000 15,000 465,900 407,645 420,393 433,654 447,448 436,796 940,000 1,315,000 585,000 0 1,505,000 305,000 279,660 0 0 0 0 0 360,360 358,400 355,480 356,600 356,440 0 138,486 139,773 138,173 141,573 139,873 138,215 0 0 216,000 216,000 216,000 216,000 778,506 498,173 493,653 498,173 496,313 138,215 (619,946) (887,554) (188,642) 376,685 (1,114,691) 434,880 0 0 0 0 0 0 0 0 0 350,000 350,000 350,000 13,226,860 12,606,914 11,719,360 11,530,718 12,257,404 11,492,713 $12,606,914 $11,719,360 $11,530,718 $12,257,404 $11,492,713 $12,277,593 9/1312010 M:\FA\Capital audgetst2011CIP \Final Document \3 Revenue Projections section 3\ 3 -7 2011-2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM WATER FUND ASSUMPTIONS The following information provides the assumptions used in the analysis. Projected User Changes and Capacity Charges (Tan Fees) Assumptions: • Revenues based on ERUs and authorized fees established by Ordinance 64 -09. • Effective 1/1/2010, a reallocation of .25 per MCF in user charges from water to sewer has been approved. • Average number of ERUs for 2010 reflects a growth of 83. This is based on the number of residential building permits issued in 2009 for new units. • Average number of ERUs for 2010 and forward are the total of the estimated previous year's average number of ERUs at the beginning of the year and the previous year's estimated ERU growth. • Estimated ERU growth for 2011 through 2015 2011 -75 2012-75 2013 -75 2014-75 2015-75 • Beyond 2015 estimated ERU growth: 2016 — 2021 - 100 Statement of Projected Revenue Expenses and Changes in Water Fund Cash Balance Assumptions: • Revenues for user charges and tap fees based on schedule of Projected User Fees and Projected Capacity Charges. • Salaries /wages and Benefits /uniforms included for water hydrant program. • Subsidy for debt service is the debt service obligation for the debt issued in 1990. The debt matures in 2010. • The 1994 debt service obligation provides funding to retire the debt on the $4,100,000 in long -term bonds issued for the Rings /Blazer water tower. 3 -8 9/13/2010 MAMCapital Budgets\2011 CIP \Final Document \3 Revenue Projections section 3 \3 -1 to 3 -9 Revenue projeclions.doc Water Fund Assumptions (Continued) • The 2009 debt service obligation provides funding to retire the debt on the $2,015,000 in long -term debt issued for the Darree Fields water tower. • The 2012 debt service issue is based on the current plan to issue $2.7 million in long -term debt for the construction of the Dublin Road water tower. • Funding has been programmed during the five year period to paint existing water towers and to replace pumps at the City's booster stations. • Funding has been programmed to replace water lines in 2012 and 2014. A comprehensive list of areas to review for water line replacement will be prepared and an analysis of the lines completed to determine the future replacement programming needs. The Statement of Projected Revenue, Expenses and Changes in Water Fund Cash Balance were prepared through the year 2020. Using the above assumptions, sufficient revenue will be available, as well as maintaining a considerable reserve, throughout the life of existing and proposed debt obligations. The projected balance and outstanding advances will meet the goal of 25% of the historical value of the system assets. The rate of growth and the user fees and capacity charges will continue to be evaluated annually. 3 -9 9/13/2010 MAMCapital Budgets\2011 CIP \Final Document \3 Revenue Projections section 3\3 -1 to 3 -9 Revenue projections.doc 2011-2015 FIVE-YEAR CAPITAL IMPROVEMENTS PROGRAM MAJOR PROJECTS Project Prioritization In developing the Five -Year CIP several elements are taken into consideration: City Council goals, both past and present; findings included in the Economic Development Strategy; commitments made by the City in agreements such as tax increment financing /economic development agreements; bi- annual community surveys, input from citizen committees, and economic development opportunities. Utilizing these criteria resulted in projects to be funded that are biased towards needed infrastructure improvements such as roads and utility needs. The following pages reflect the projects to be funded, project descriptions, and a recap of the funding sources. 4 -1 9/13/2010 WFA \Capital Budgets\2011CIP \Final Document \Major section 4 \4 -1 Major projects.doc 2011 -2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM FUNDED PROJECTS TOTAL PRIOR TOTAL PROJECT COST YEARS 2010 2011 2012 2013 2014 2015 2011-2015 ET0607 Central Ohio Innovation Center (COIC) roadway improvements42- Industrial Parkway relocation A¢hi(eclu2l\Engineenng fees 450,000 450,000 0 Acquisition 4,128,000 4,128,000 0 Construction 5.211,000 5.211000 0 Other ez nses 40,000 40,000 40,000 Total 9,829,000 9,789,000 0 40,000 0 0 0 0 40,000 ET0606 Central Ohio Innovation Center (COIL ) roadway improvements43- Eitennan Road relocation Archcectuml \Engineenng fees 545000 545,000 0 Acquisition 0 0 Construction 0 0 Otherex e 0 0 Total 545,000 545.0001 0 01 0 0 0 0 0 ET0611 Central Ohio Innovation Center (COIC ) roadway improvements-#5- SR 161 improvements ArohitectumAlicgineenng fees 1,029,000 1029,000 0 ArquisXion 2.000 2,000 0 construction 254.000 254.000 0 Otherez .nses 40,000 40,000 40000 Total 1,325,000 1,285,000 0 40,000 0 0 0 0 40,000 ET0003 Central Ohio Innovation Center (COIC ) roadway improvements- 4GUS33 /SR161 /Post Road interchange Architectural \Engineering fees 3,130,000 3.130,000 0 Acquisition 10,024 000 10.024,000 0 Construction 886,000 886,000 0 Other expenses 48,040 48.000 0 Total 14.088,0001 14.088000 01 0 0 0 0 0 0 ET0902 Central Ohio Innovation Center (COIC ) roadway improvements47 -Post Preserve access modification ArchitecturanEngineenng fees 191,000 191,000 0 Acquisition 0 0 0 Construction 0 0 0 Other ex nses 0 0 0 Total 191,000 19 0 0 0 0 0 0 0 ET0103 Tuttle Crossing Boulevard extension -Wilcox Road to Avery Road (TIF) Arehitecturat\Engineering fees 652,000 2.000 150,000 500.000 650.000 Acquisition 1.613000 13.000 1,800,000 1,800.000 OonsWdion 0 0 Other Expenses 0 0 Total 2.465,000 15,000 01 0 150,000 500,000 1,800,000 0 2,450,000 ET0104 Emerald Parkway- Riverside Drive to Billingsley Creek (TIF) ArehitecturahEngineerng fees 794,000 794000 0 Acquisition 2.541000 766,000 1,775.000 0 Construction 9,565000 65.000 9,500,000 9,500000 Other Ex penses 210.000 210,000 210,000 Total 13,110,000 1,625,000 1,775,000 9,500,000 210,000 0 0 0 9,710,000 ET0205 Emerald Parkway -Rings Road to Tuttle Crossing Boulevard (TIF) Architectural\Engineenng fees 684,000 464,000 220,000 0 Acquisition 0 0 Construction 2,280.000 2280,000 0 Other Expenses 0 0 Total 2,964,0017 464,000 2.500,000 0 0 0 0 0 0 snscs 4 -2 2011 -2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM FUNDED PROJECTS TOTAL PRIOR TOTAL PROJECT COST YEARS 2010 2011 2012 2013 2014 2015 2011 -2015 ET1119 Relocated Rings Re ad AmhltedumhEngineenng fees 90,000 90,000 90.000 Acquisition 350.000 350.000 350000 Construetion 725,000 7zs.000 725.000 omere e o 0 Total 1,165000 0 0 0 90,000 350.000 725,000 0 1,165.000 ET1202 Frantz Road atility burial Arcbiteduml\Engineenng fees 75.000 75.000 75,000 Acquisition 0 0 Const Vct.on 750,000 750.000 750.000 Otherex enses 0 0 Total 825,000 0 0 75,000 0 750,000 0 0 825.000 ET0810 Frantz Road - Dublin Road connector (Potential TIF) Architeduml\Engineering fees 229,000 229.000 0 Acquisition 0 0 ConsUUdion 2,650,000 2,650,000 2.650.000 Other expenses o 0 Total 2,879,000 229,000 0 2,650,000 0 0 0 0 2.650.000 ET1101 Railroad Ouiet Zones Architedv21\En9ineering fees 20.000 20.000 0 Acquisition 0 0 Construef. 470.000 470.000 470,000 Other expenses 0 0 n 470,000 Total 490 0 20,000 470,000 0 0 0 ET1103 LED street light replacement Am fteetumhEngheehng fees 0 0 Acquisition 0 0 Const,vdion 2.300000 300,000 2.000.000 2,300000 Other expenses o 0 300,000 2,000.000 0 0 0 0 2.300,000 Total 2,300,000 0 Intersection Improvements: ET0405 Hyland -Croy Road/Brand Road (TIF) Arehltect.reREngineerng fees 273000 273.000 0 A,visition 200.000 200.000 200.000 Consvudion 2.500,000 2.500.000 2.500.000 Otherex enses o 0 0 0 0 0 2.700,000 Total 2,973,000 273,000 0 2,700,000 ET0410 Avery- Muirfield Drive/Perimeter Loop /Perimeter Drive (TIF) intersection (TIF) Architedu2l\Engineenng lees stoner 10.000 500.000 500,000 330.000 330,000 330,000 Agquisilign 3$00000 3.500.000 ConsWdioq 3.500,000 0 Otherex enses 0 10.000 500,000 330,000 0 3.500,000 0 4,330,000 Total 4,340.000 0 ET0508 Riverside Drive /SR161(TIF) Architetuml\Engineenng fees 594.000 194,000 400,000 400.000 Acquisition 2536,000 36.000 2,500.000 0 CoWnuction n e 0 Otheresperses 0 232,000 2,500,000 400,000 0 0 0 0 400,000 Total 3,132,000 ET0511 Avery- Muirfeld/iullymoreNalley Stream /Avery Road Archifeduml \Engineering fees 151,000 51.000 100,000 100,000 25,000 25.000 25.000 Acquisition 70 0pop 700.000 Construction 700,000 0 Otherex enses 0 51,000 0 100,000 0 725,000 0 0 825.000 Total 876,000 N10 4 -3 rx�rnnwu� a+x.'.w� �cinr..m oa:.nwu v.v ..•.m. eer aeasx.an 2011-2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM FUNDED PROJECTS TOTAL PRIOR TOTAL PROJECT COST YEARS 2010 2011 2012 2013 2014 2015 2011 -2015 ET0605 Sawmill Road /Hard Road (TIF) AnehMstumhEnginesnng fees 222,000 222,000 0 Acquisition 213,000 13,000 200.000 0 Constmdion 2.250.000 550.000 1,7M,000 2250,000 Other ex enses o 0 Total 2.685,000 235.000 200,000 550,000 0 1,700,000 0 0 2,250,00D ET1001 Cosgray Road /Shier Rings Road Architectual\Engineering fees 136,000 136,000 0 Acquisition 250.000 250.000 250.000 Conshudion 1,600.000 1,600,000 1 600,000 Other expenses 50.0001 5D.000 50.000 Total 136.000 0 1,850.000 50.000 0 0 0 1,900.000 ET0809 Hyland Croy Road /McKitrick Road ArchiteduallEngineenng fees 180.000 180.000 Acquisition 50.000 50.000 Constmdion 1.200.000 1,200.000 Olherex enses ;1.460,000 30.000 30.000 Total 0 0 0 180,000 50,000 0 1,230.000 1460,000 ET09N Perimeter Drive /Commerce Parkway (TIF) Architeduxl\Engineenng fees 11],000 0 Acquisition 0 Construction 1,500,000 1,500,000 Other ex nses D 0 Total 1,617,000 117,000 0 1500.000 0 0 0 0 1,500,000 ET1401 1- 270 /US 33 Interchange phase i improvements (Potential TIF) ArchiteduraREnginesdng fees 500,000 500,000 0 AcquiAw 0 0 COnsiNdion 2.400,000 2400,000 2400.000 Otherex enses 0 0 Total 2.900,000 0 500,000 0 0 0 2,400,000 0 2,400,000 ET1003 Dublin Road and Glick Road intersection improvements ArchiteduahEngineenng fees 250000 250.000 0 Acquisition 0 0 Constmdion 0 0 Other ex nses 0 0 Total 250.000 0 250,000 0 0 0 0 0 0 ET1102 US33 /SR 161/Post Road eastbound ramps PrchitedurahEngineering fees 0 0 Acquisition 0 0 Conswction 0 0 Other expenses 150000 150 150.000 Total 150,000 0 0 150,000 0 0 0 0 150,000 Multi -use pathsthike lanes: ETION Brand Road multi -use path /bike lanes Ar dedualTngineedng fees 240.000 2 0 A,uisitien 160000 160.000 0 Construction 3,122,000 82,000 2.005,000 1,035,000 3,04,000 Other expenses 0 0 Total 3,522,000 82,000 400,000 2.005,000 1,035,000 0 0 0 3,040,000 ET1203 Dublin Road South multi -use path Architedu2REngineering fees 0 0 A,uisition 0 0 Consmdion 1,222,000 92.000 70,000 430,000 1,130.000 Omer expenses 40000 40 40.000 Total 1,262,000 92,0D0 0 0 740,000 430,000 0 0 1,170.000 9!t]R010 4 -4 u. ssae.rn wwwewr+ci ra.n u uw x.uxa. e+z civa -.Mw.n 2011 -2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM FUNDED PROJECTS TOTAL PRIOR TOTAL PROJECT COST YEARS 2010 2011 2012 2013 2014 2015 2011 -2015 ET1204 Glick Road multi -use path AmhRedu26Englneed, fees 340.000 340.000 340,000 Acquisition 60,000 60,000 6,000 Constmdion 250.000 250,000 250.000 Otherex enses 40 40 40 Total 690,000 0 0 0 340,000 60 000 290,0001 0 690,000 ET1104 MuiMeld Drive bike lanes ArchiteduallEngmeedng fees 50,000 50.000 50,000 Ac3ui0ion 0 0 Conswdion 0 0 Otherex enses 0 0 Total 50,000 0 0 50,000 0 0 0 0 50,000 ET1005 Emearld Parkway shanows Architectuml\Engineedng fees 0 0 Acquisition 0 0 Cgnsfn r., 180,000 60,000 120,000 120,000 Other ex enses 0 0 Total 180,000 0 60.000 120,000 0 0 0 0 120,000 Total Transportation 80299,000 29449000 8,215000 23,000,000 5125,000 4565,000 8,715000 1,230,000 42,635000 GR9901 Darree Fields development ArchitedumpEngineehng fees 616.000 586.000 30,000 30.000 Acgvisifron 552.000 552.000 0 Constmdion 4974,000 4,130.000 260,000 300.000 200,000 580,000 E Moment 74000 74 0 Total 6,216,000 5,346,000 260,000 380,000 30.000 200,000 0 0 610,000 GR9902 Coffman Park expansion AmHtectuml\Engineering fees 50.000 50.000 0 Acquisition 0 0 Constmdion 0 0 Equipment Total 0 50,0001 0 50,000 0 0 0 0 0 0 0 GR9903 Amberleigh Community Park development ArohitedumhEngineering fees 269,000 94,000 100.000 75.000 175.000 Acquisition 732.000 732.000 0 Constmdion 1550,000 905000 565000 565,000 Equipment Total 0 2,551.000 626,000 965,000 0 0 100,000 565.000 75,000 0 740.000 GR9904 Emerald Fields (N.E. Quad Park) development Amhhedur \Engineering fees 217.000 21 ?000 0 Acquisition 1.220.000 1.220,000 0 Conswdion 4,066.000 3.546.000 520000 520.000 E ui went Total 0 5,503,000 4,963,000 0 0 520,000 0 0 0 0 520.000 AL1102 Parkland acquisition 8,200.000 sso.000 650.000 1.725.000 +725,000 1,725,000 +7x5,000 7550.000 Acquisition 8.200,000 0 650,000 650,000 1,725,000 1,725,000 1,725,000 1725,000 7,550,000 Total Total Parks 22,520,000 11,155 1,945 000 1,030 2 275 000 2,025 000 2 1,800,000 9,420,000 ES0701 Sewer lining and repair 0 Archdeduml\Engineedng fees 0 0 Acquisition Conswdion 0 5,073,000 2,223,000 850.000 2.000,000 2,000,000 Other expenses 0 850,000 0 2,000.000 0 0 0 0 2,000,000 Total 5.073,000 2.223,000 ES0601 South Fork sanitary sewer extension 0 Amhhedural Orgineering fees 0 0 Acquisition 7.000 7,000 96,000 Construction 690.000 330,000 360.000 Other ex enses 0 330000 360,000 0 0 0 0 0 360,000 Total 697.000 ],000 9r ,- 4 -5 u�[>rCa[yxaexu :wr,nrrrrprzwmw wi.sse..�.vv.xcrvJ.rv.vm 2011-2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM FUNDED PROJECTS TOTAL PRIOR TOTAL PROJECT COST YEARS 2010 2011 2012 2013 2014 2015 2011 -2015 EW1101 Rings Road waterline Amhitectural\Engineenng fees 65.000 65.000 65,000 Acquisition 15.000 15,000 15000 Constmuion 650,000 650.000 650.000 Other ex enses o 0 Total 730.0001 0 0 0 0 0 730,000 0 730,000 EW1201 Dublin Road water tower Architecturel\Engineenng fees 150,000 150.000 150,000 Acquisiton 250.000 250.000 0 Constwcion 2.700.000 2,700,000 2.700.000 Otherexpenses 0 0 Total 3,100,000 0 250,000 150,000 2,700,000 0 01 0 2,850.000 EF0201 Slormwater improvements Arch ectural\Enginesnng fees 464W0 361.000 50000 30,000 25.000 105,000 Acquisition 32.000 32.000 0 Construction 2,875.000 2.260,000 435,000 180.000 615.000 Other expenses 0 0 Total 3,373,000 2,653,000 0 50,000 0 465,000 205,000 0 720,000 Total Utilities 12973,000 4883,000 1430000 560 4,700,000 465,000 935,000 0 6,660,000 ABO601 Municipal facilities ArUitectuaeEngineenng fees 67,000 67,000 0 Acquisition 0 0 0 Const,uepn 1,295,000 1.045,000 150.000 100,000 100000 OlM1erex nses 15,000 15,000 15000 Total 1,377,000 1.112.000 150,000 775.000 of 0 0 0 115.000 AB1001 Upgrade fuel facility for compressed natural gas(CNG) ArchitecturahEngineenng fees 0 0 Awuisi(on 0 0 ConsmU ron 2.175.000 2.175.000 0 Other ex enses 0 0 Total 2,175,0001 0 2,175.000 0 0 0 0 0 0 Total Facilities 3,552,0001 1,112000 2325,000 115,000 0 0 0 0 115 ABO602 Historic Dublin Arobiv,durahfingineenng tees 24.000 24,000 0 Acquisition 380,000 380000 0 Constud,i n 3.239.000 2.239,000 500.0001 250,000 250.000 500.000 Other expenses 0 0 Total 3,643,000 2,643,000 500,000 250,000 250,000 01 0 0 500,000 A61301 Bridge Street Corridor Architedual \En9ineennq fees 0 0 A,ua ifian 0 0 Construction 754W0 250,000 2500 00 250.0 00 750000 Other ex enses 0 0 Total 750,0001 0 0 0 0 250,000 250,000 250.000 750.000 A11101 Computer hardware /software E vipmenl 5.565.00 750,000 900.000 1,125.000 955,000 930.000 905,000 4815,000 Total 5,565,000 0 750,000 900.000 1,125,000 955.000 930.000 905,000 4,815,000 PP1101 PSAP equipment replacement E ui rr.M 420,000 420.000 420.000 Total 420,000 0 0 420,000 0 0 0 0 420%00 Fleet management program AV1101 Fleet replacements 4,780.000 1.114000 1065,000 780,000 1,020.00 565,000 244000 3.670,000 AV1103 Equipment additicWre lacements 2.305.000 365,000 295.000 345.000 360,000 $25000 415.000 19-0.00 Total 7,085,000 0 1675.000 1,360.000 1,725,000 1,380,000 7,090.000 655,000 5,610,000 Total Others 17,463,000 2 643 000 2 725 000 2,930 000 2,500,000 2 335 000 2,020 000 1 560 000 11,3455 ,000 G2nd Totals $136 $49 $16,640 $27 $14 $9,390 $13960000 $4 $70175000 ___9lial3ot0 46 u sn�Ceenn6Ny �to„cinriw pzw,nq�ew�n aaafn�'aSC.KCwb e+ City of Dublin 2011 — 2015 Capital Improvements Program Transportation — Maior Proicets COIC Roadway Improvements This project provides for the roadway improvements related to the Central Ohio Innovation Center. The overall project has been broken down into seven (7) project areas. The project areas are as follows: ET0609- Project Area 1 — West Area improvements This project area will be completed as required by future development. ET0607- Project Area 2 — Industrial Parkway relocation This project area includes the relocation of Industrial Parkway with right -of -way acquisition in 2008, construction was programmed in 2009 with completion in 2010 and landscaping in 2011. The City was awarded $1,000,000 in Federal stimulus funds as a result of the American Recovery and Reinvestment Act (ARRA) to help offset the cost of this project and the SR 161 improvements. Additionally, $200,000 will be received from Union County from a 629 Roadway grant awarded to the County. ET0606- Project Area 3 — Eiterman Road relocation This project area includes the relocation of Eiterman Road. Construction, originally programmed in 2010, has been deferred until beyond 2015 and will continue to be evaluated based on development needs. ET0611-Project Area 5 — SR 161 improvements This project area includes the widening of SR 161 from the ramp on the west side of the interchange to just east of Cosgray Road. Construction is programmed in 2009 and will be completed in 2010 with landscaping programmed for 2011. The project was included in the ARRA grant award and will be completed in conjunction with the Industrial Parkway relocation project. 4 -7 9/13/2010 M: \PA \Capital Budgets\201 ICIP\Pinal Document \4 Major section 4 \4 -7 COIL Roadway- Major.doc City of Dublin 2011 — 2015 Capital Improvements Program Transportation — Major Projects COIC Roadway Improvements (continued) ET0003- Project Area 6 — US33 /SR161 /Post Road interchange This project area provides for the improvements to the US33 /SR161 /Post Road interchange. Due to the developer's (Ohio Proton Therapy, LLQ inability to obtain financing, construction has been deferred until beyond 2015. The City will continue to evaluate opportunities for development and will adjust programming based on those opportunities. ET0902- Project Area 7 — Post Preserve access modification This project extends and connects Springview and Stillhouse Lane and then extends the roadway to Hyland Croy Road. Construction has been deferred until beyond 2015. The timing of this project is based on the timing of the anticipated completion of the interchange project. HE 9/13/2010 M1PA \Capital nudgets\2011CIP\Pinal DocumentA Major section 4 \4 -7 COIC Roadway- Major.doe City of Dublin 2011 - 2015 Capital Improvements Program Transportation —Major Projects Tuttle Crossine Boulevard Extension —Wilcox to Avery (Project #ET0103 This public infrastructure project provides for the extension of Tuttle Crossing Boulevard from its current terminus at Wilcox Road to Avery Road. The project includes the construction of a four -lane boulevard with curb and gutter, bikeway, sidewalk, street lights, traffic signals, a bikeway tunnel and landscaping. Funds for a preliminary alignment study have been programmed for 2012 partially due to the National Church Residence's (NCR) ability to secure financing for the construction of one and two bedroom housing units for seniors of mixed incomes and discussions with Homewood for development of the area north of the NCR site. The design and right -of- way acquisition have been programmed in 2013 and 2014, respectively. Construction is not programmed in this five year period. The construction is programmed to be funded by the issuance of long -term debt with the annual debt service obligations being retired by service payments from the Rings /Frantz TIP for the majority of the project costs and to the extent available, with any shortfall funded by an advance of income tax revenues. Sufficient funding is currently available in the TIF Fund for the design and acquisition that is programmed. The project will continue to be evaluated based on development needs. ,. 9/13/2010 MAWCapital Eudgets\201 ICIP\Pinai Docu nenl \4 Major section 4 \4 -9 Tuttle Cross Extension- Wilcox- Avery- Majocdoc City of Dublin 2011 — 2015 Capital Improvements Program Transportation — Major Projects Emerald Parkway- Riverside Drive to Billingsley Creek (Project #ET0104) This project provides for the continuation of Emerald Parkway and is the final phase to be completed. The current McKitrick TIF legislation has been modified and in the future will be utilized to fund a portion, or all, of the project to the extent service payments are available. Cardinal Health's construction of an additional office building on their site has allowed the construction of this project to be programmed. Design was completed in 2009. The right -of -way acquisition has been programmed in 2010 with construction currently programmed in 2011 and landscaping scheduled for 2012. Construction will be initiated upon completion of successful right -of -way acquisition negotiations. The McKitrick TIP Fund has sufficient reserves to fund the design and the current estimate for right -of -way. Long -term debt will be issued for the construction with the annual debt service payments being made from the McKitrick TIF Fund and, to the extent available, the Kroger Centre TIF Fund and the Lifetime Fitness TIF Fund. Prior year expenditures include the acquisition of the Jenmar Court properties and a noise study. 4 -10 9/13/2010 M: \FA \Capital Budgets\201 ICIP\Final DocumentA Major section 4 \4 -10 Emerald Pkwy -Riverside Dr to Billingsley Creek - Major.doc City of Dublin 2011 - 2015 Capital Improvements Program Transportation — Major Projects Emerald Parkway -Rings to Tuttle Crossing Boulevard (Project #ET0205) This project provides for the widening of Emerald Parkway from Rings Road to Tuttle Crossing Boulevard. The modification of the Emerald Parkway /Tuttle Crossing intersection was completed as part of the Tuttle Crossing Boulevard widening project. The City of Columbus and Dublin entered into a Cooperative Design and Right -of -Way Agreement on May 19, 2010. Design is approximately 90% complete and each City will acquire its own right-of-way. Construction of the overall project is currently anticipated to be administered by the City of Columbus. The project costs will be apportioned based on corporate boundaries. Right -of -way acquisition is mostly, if not all, in the City of Columbus' portion of the project. It is anticipated a significant portion of Dublin's right -of -way will be donated. The City of Columbus is currently working on issues related to right -of -way acquisition. Construction has been programmed in 2010; however, further evaluation may be necessary to determine the value of completing only the Dublin portion of the project should the City of Columbus be delayed, or unable to, acquire the necessary right -of -way. This project will be funded from a grant provided by the Ohio Public Works Commission (OPWC) from a grant submitted by the City of Columbus as long as the project is initiated in Spring 2011 as set forth in the grant agreement. Dublin will be reimbursed directly from OPWC for their share of the project. The City's share of the project can be funded by service payments generated from the Thomas /Kohler TIF, if necessary. 4 -11 9/13/2010 M: \PA \Capital Budgets\201 ICIP\Pinal Document \4 Major section 4 \4 -11 Emerald Pkwy -Rings to Tuttle- Major.doc City of Dublin 2011 - 2015 Capital ILnprovements Program Transnortation — Maior Proiects Relocated Rings Road (Proiect #ET11.19 Provides for the roadway extension from the existing Rings Road along the southwest boundary of the Ballantrae multi - family area, by- passing Amlin along its north side. This will be a three -lane roadway and is needed as a result of the planned future development. The project also includes water and sewer extensions and landscaping. Due to slowed growth and discussions with the developer, we have deferred the project. Design is scheduled for 2012, land acquisition in 2013 and construction in 2014. 4 -12 9/13/2010 MAIWCapital Budgets\2011CIP\rinal Document \4 Major section 4 \4 -12 Relocated Rings Rd - Major.doc City of Dublin 2011 - 2015 Capital Improvements Program Transportation — Maior Proieets Frantz Road utility burial (Proieet #ET1202 This project will fund improvements consisting of the burial of overhead utility lines along Frantz Road between Metro Place North and Rings Road. These improvements will be funded by the Pizzuti TIF. Funding has been programmed based on current service payment projections. 4 -13 9/13/2010 M: \PA \Capital 6udgets\2011CIP\Pinal Document \4 Major section 4 \4 -13 Frantz Road utility burial.doc City of Dublin 2011— 2015 Capital Improvements Program Transportation — Major Protects Frantz Road - Dublin Road connector (Project# ET0810) This project will provide a new section of two /three lane roadway to connect Frantz Road, north of SR 161, to the east to Dublin Road. This project will provide a roadway option north and west of the Historic District and will provide access to Cardinal Health South Campus and allow for possible future development of OCLC property. The Bridge Street corridor study will have significant implications on this project. Construction has been deferred from 2010 to 2011 and will continue to be evaluated. 4 -14 9/13/2010 WFA \Capital Budgets\201 ICIP\Pinal Document \4 Major section 4 \4 -14 Frantz-Dublin Rd connector- Major.doc City of Dublin 2011 — 2015 Capital Improvements Program Transportation — Major Projects Railroad Quiet Zone — $ouchard Road to Leap Road (ProiecM ET1101) This project will add Supplemental Safety Measures (medians or extra gates) at each public road /rail crossing. Once installed, locomotive horns would not routinely sound along the CSX line for seven consecutive crossings. The crossings include three in Franklin County, two in Hilliard, one in Columbus and one crossing in Dublin. The City has applied for State Capital Budget funding for the project. The cost to install the crossing in the City has been programmed in 2011; however, to achieve the desired results, all crossings would need to be upgraded and it is unlikely all jurisdictions will move forward without state funding. We have programmed the project based on recent funding from the State Capital Budget. 4 -15 9/13/2010 MAWCapital Budgets\2011C1P\Pinal Document\4 Major section 4 \4 -15 Railroad Quiet Zone - Houchard to Leap.doc City of Dublin 2011 -2015 Capital Improvements Program Transportation — Major Projects LLD Street Light Replacement (Proiect# ET1103) Funds are programmed to replace the existing 250 watt high pressure Kim street lights with Light Emitting Diode (LED) street lights. The cost is based on replacing approximately 1,500 street lights, programmed in 2011, and approximately 225 street light style fixtures in City owned parking lots, programmed for replacement in 2012. The estimated annual electric savings by switching to LED lights is $62,000 and the payback period for energy and maintenance costs is approximately 4.5 years. The useful life of the lights is approximately 12 years. 4 -16 9/13/2010 MAWCapital Eudgets\201 ICM1 DOCmnentA Major section 4 \4 -16 LED street light replacement.doc City of Dublin 2011— 2015 Capital Improvements Program Transportation — Major Projects Hyland -Croy Road /Brand Road (Project# ET0405) The majority of the funding for this project will be the service payments that will be received from the established Tartan West TIP. The Oak Park development is required to dedicate right -of -way and contribute to the construction. Oak Parks' financial contribution for the project has been received. The project will be initially funded by advances from the Capital Improvements Tax Fund and the General Fund. These advances will be repaid as service payments are received. The City began receiving a limited amount of service payments in 2007. An intersection analysis study was completed and identified that a roundabout is the preferred option for this intersection. The improvement will be a single lane roundabout expandable to a two lane roundabout. Design for the project was programmed in 2008 and is being completed. Right -of -way acquisition and construction have been programmed in 2011. 4 -17 9/13/2010 M AAA \Capital Budgets\2011CIP\Pinal Document \4 Major section 4\4 -17 Hyland Croy -Brand Rd Inter Impr- Major.doc City of Dublin 2011 — 2015 Capital Improvements Program Transportation — Major Projects Avery - Muirfield Drive /Perimeter Loop /Perimeter Drive (Project #TT0410) This project provides for the reconstruction of the intersections from signalized intersections to roundabouts. These projects were identified as future needs when the land to the west of Avery - Muirfield Drive and north of U.S. 33 /S.R. 161 was rezoned. The design for the project has been programmed in 2011, right -of -way acquisition in 2012 and construction deferred until 2014. The project will provide for the construction of a two -lane roundabout. Additional long -term improvements may be programmed beyond 2015. This project was included as a public improvement need in the Perimeter West TIF district; however, sufficient service payments for this TIF will not be available in the near future. The funding for this project will be service payments that will be received from the modified Ruscilli and Perimeter Center TIFs. These two (2) TIF districts were modified in December 2003 to provide for the implementation of a "non- school" TIF after the terms of the "straight" TIF expired and the addition of these intersections and other improvements in the area included as public improvements to be funded by the TIF districts. Service payments received through 2014 are estimated to be sufficient to fund this project. Originally included in this project were improvements at the Avery - Muirfield /Post Road intersection. These improvements have been completed and are no longer included as part of this project. 4 -18 9/13/2010 MAPA\Capital Budgets\201 ICIP\Pinal Document \4 Major section 4 \4 -18 Avery - Muirfield Dr- Perimeter Loop.doc City of Dublin 2011 — 2015 Capital Improvements Program Transportation — Maior Proiects Riverside Drive /SR 161 (Proiect 4 RT0508 This intersection and potential improvements have been under review in recent years. An alternatives analysis has been completed and signalization modifications and roundabout alternatives are being evaluated. Funding has been advanced from the Capital Improvements Tax Fund to the River Ridge TIF Fund to fund the alternatives analysis and design when it is determined to move forward with the improvements. The funding programmed in 2010 is an allocation for potential acquisition ($2,500,000). 2011 provides for estimated design costs ($400,000). Development in the surrounding area will impact what intersection improvements will be completed. The relocation of Riverside Drive to the east of its existing location is also being evaluated as part of the review and evaluation of the intersection improvements. The results from the recently completed Bridge Street corridor study is likely to have significant implications on this project. Construction is not currently programmed in the five year period. The amount reflected beyond 2015 is based on signal modifications and the addition of right turn lanes on northbound Riverside Drive and westbound S.R. 161. 4 -19 9/13/2010 M: \PA \Capital Budgels\201 ICIP\Pinal Document \4 Major section 4 \4 -19 Riverside -SR161 Inter Impr- Major.doc City of Dublin 2011 - 2015 Capital Improvements Program Transportation — Major Projects Averv- Muirfield /Tullvmore/Vallev Stream /Avery Road (Project PET0511 This project will provide for intersection improvements at the intersections of Avery - Muirfield Drive at Tullymore Drive, Valley Stream Drive, and Avery Road. The improvements will include new pavement, grading, shoulder work, drainage, and construction of medians to restrict left turning movements off Tullymore Drive, Valley Stream Drive and Avery Road. A feasibility study was initiated in late 2005. In 2008, cost effective striping was completed to add a northbound left turn lane from Tullymore to Avery - Muirfield Drive. The effectiveness of these changes continues to be evaluated. Design has been programmed in 2011 with right -of -way acquisition and construction programmed in 2013. This project will be funded by Permissive tax revenues. 4 -20 9/13/2010 MAWCapital Bodgets\201 ICIP\Pinal Document \4 Major section 4 \4 -20 Avery- Muirfeld- Tullymore- Avery- Major. doc City of Dublin 2011 — 2015 Capital Improvements Program Transportation — Major Projects Sawmill Road /Hard Road (Project 4ET0605) This project provides additional right turn lanes and modification to the traffic signal The design has been completed, right -of -way acquisition has been deferred by one year and is programmed in 2010 with utility relocation in 2011 and construction in 2013. Engineering staff has been coordinating with the City of Columbus on the third phase of their improvements on Hard Road from Smokey Row to Sawmill Road. The project will be funded by the developer contribution required as part of the Kroger Centre development and the Lifetime Fitness development and the service payments generated by the Kroger Centre and Lifetime Fitness TIF districts. The Kroger Centre developer contribution has not been finalized, however, it is estimated to be approximately $500,000. The funding will initially be advanced from the Capital Improvements Tax Fund with the advance being repaid as developer contributions and service payments are received. In accordance with the Lifetime Fitness TIF /EDA, Lifetime Fitness will be required to contribute $500,000 toward the project and then be reimbursed by service payments after the City has been reimbursed. 4 -21 9/13/2010 MAT WCapital Budgets\201 ICWTinal Document \4 Major section 4 \4 -21 Sawmill- Hard- Major.doc City of Dublin 2011 - 2015 Capital Improvements Program Transportation — Maior Proiects Coserav Road /Shier Rines (Proicet #ET1001 This project provides for the addition of turn lanes, ditch improvements and pavement widening. Based on a completed Alternative Analysis to quantify existing safety concerns and to evaluate intersection improvements, it has been determined a roundabout is the best solution for this intersection. The Ballantrae Traffic Impact Study identified this intersection as needing future improvements. Also, this intersection is currently the only access to Darree Fields. The project is currently under design with right -of -way acquisition and construction programmed in 2011. This intersection improvement will be evaluated for possible Ohio Public Works Commission grant funding. Timing for completion will be adjusted as more detailed funding information becomes available. 4 -22 9/13/2010 M AFWCapital Budgets\201 ICIP\Pinal Document \4 Major section 4 \4 -22 Cosgray -Shicr Rings- Major.doc City of Dublin 2011 — 2015 Capital Improvements Program Transportation — Major Proicets I-Tyland -Croy Road /McKitrick Road (Project# ET0809) This project will improve an existing two lane county road into a single lane roundabout with curb and gutter, street lights, crosswalks, storm drainage, and landscape. Based on slowed growth in the area, this project has been deferred. Design is scheduled in 2012, right -of -way acquisition in 2013 and construction in 2015. The developer of Tartan Ridge is required to contribute to this project. Tartan Ridge is required to contribute $118,125 when the Final Development Plan for the commercial area is approved or December 31, 2010, whichever occurs first. 4 -23 9/13/2010 M: \PA \Capital Budgets\201 ICIP\Pinal DOemlle1164 Major section 4 \4 -23 I lyland Croy - McKitrick Inter Impr- Major.doc City of Dublin 2011 - 2015 Capital Improvements Program Transportation — Major Projects Perimeter Drive /Commerce Parkway (Proiect #ET_0 As a result of the Cardinal Health expansion and subsequent redirection of Post Road, this project was added to provide for improvements at Perimeter Drive and Commerce Parkway. Funding provides for two lane roundabout approach for Perimeter Drive and a one lane approach for Commerce Parkway along with other site improvements. This project has been accelerated to comply with the terms of the Tax Increment Financing (TIF) agreement with Delta Energy and their commitment to build their corporate headquarters near this intersection. Design is currently being completed with construction scheduled for 2011. Based on preliminary estimates, service payments from the Ruscilli, Perimeter Center and Delta Energy TIFs will be used to fund the costs of the project. 4 -24 9/13/2010 MAPA \Capital 13 Lid gets\201 I CIP\Pinal Document \4 Major section 4 \4 -24 Perimeter Drive- Commerce Parkway sign al- Major.doc City of Dublin 2011 — 2015 Capital Improvements Program Transportation — Major Projects 1- 270 /US 33 interchange phase I improvements (Project# ET1401) This project includes phase 1 of the I- 270 /US 33 interchange rebuild, which includes an I -270 north -bound flyover ramp to west bound US 33. This work is meant to include the Alternatives refinement to the preferred alternative, environmental clearances and associated preliminary engineering, final design, and some right -of -way acquisition. The project cost assumes only Dublin's 20% local match contribution of the total cost for the elements above, for a total of $12,000,000. Total construction cost for the northbound to westbound flyover ramp is approximately $35,000,000. The City has initially been awarded funding from the Transportation Review Advisory Council (TRAC) for preliminary engineering and environmental assessments. The local match is $500,000 and has been programmed in 2010. The consultant is expected to be selected in October. The contract will be administered by the Ohio Department of Transportation (ODOT). 4 -25 9/13/2010 M: \rA \Capital Budgels\201 ICI%Pinal Document \4 Major section 4 \4 -25 1- 270 -US 33 interchange phase I- Major.doc City of Dublin 2011 - 2015 Capital Improvements Program Transportation — Major Projects Dublin Road and Glick Road (Project #ET1003 This project will add left turn lanes on each approach and improve the sight distance on the north leg of the intersection. Pedestrian facilities and modifications to the traffic signal will also be included. Potential funding sources include an OPWC grant that Delaware County will apply for on behalf of Shawnee Hills. If the grant is awarded, Delaware County will match local contribution up to $50,000. Shawnee Hills has committed to contributing $50,000. Acquisition, utility relocation and construction are not programmed in the five year period and will be evaluated once design has been completed. 4 -26 9/13/2010 M: \FA \Capital Budgets\201 I CIP\Final Document \4 Major section 4 \4 -26 Dublin Road and Glick Road intersection- Major.doc City of Dublin 2011 — 201.5 Capital Improvements Program Transportation — Maior Protects US33 /SR 161 /Post Road eastbound ramp (Project# ET1102 Since the US33 /SR 161 /Post Road interchange has been deferred, an allocation has been programmed in 2011 to provide funding for potential improvements. Improvements to this intersection could potentially improve traffic flow, enhance the western entrance into the City and assist in the marketing of the Central Ohio Innovation Center. Further analysis on the intersection will be needed once the Industrial Parkway relocation/SR 161 improvements are completed and time is given to realize the positive effects the improved roadway will have on the interchange. The Administration will continue to monitor this intersection and will include any recommendations in future CIP's. 4 -27 9/13/2010 M:UA \Capital nudgets\201 ICIP\Pinal DocumentA Major section 4 \4 -27 US33 -SR 161 -Post Road eastbound ratnps.doc City of Dublin 2011 — 2015 Capital Improvements Program Transportation — Major Projects Bikeway connections /additions Brand Road multi -use path /bike lanes (Project #ET1004) This project will provide for the construction of a multi -use path and bike lanes on Brand Road. Design is programmed in 2010 for both the multi -use path and the bike lanes. Construction is programmed in 2011 to complete a multi -use path and bike lanes between Muirfield Drive and Dublin Road. Funds programmed in 2012 are to construct bike lanes between Hyland Croy Road and Muirfield Drive. Dublin Road South (Project #1203) Funds have been programmed in 2012 and 2013 for the construction and landscaping of the Dublin Road South multi -use path between Historic Dublin (Karrer Place) and Tuttle Road. Glick Road (Proiect #1204) This project is for the completion of the Glick Road multi -use path between Avery Road and Muirfield Drive and will be completed in phases. Funds have been programmed in 2012 2013 design and acquisition for the entire path. Construction and landscaping between Carnoustie Drive and Muirkirk Drive is programmed in 2014. The remaining construction along Glick Road is identified beyond 2015. Muirfield Drive (Project #1104) Funds programmed in 2011 are for preliminary design and alignment for the construction of bike lanes between Brand Road and Glick Road. Emerald Parkway sharrows (Project #1005) Funds programmed in 2010 and 2011 are to add sharrows to Emerald Parkway. In 2010, plans are to add sharrows to a portion of the roadway for evaluation with the remaining roadway being completed in 2011 based on the results of the evaluation. 4 -28 9/13/2010 M: \FA \Capital Budgets\201 ICIP\Pina[ Docurnenl \4 Major section 4 \4 -28 Bikepalh connection- additions.doc City of Dublin Proposed 2011 -2015 Capital Improvements Program Park and Recreation — Maior Proieets Darree Fields Development (Proiect #GR9901 This project includes the development of the park in accordance with the completed Master Plan. Funding programmed in 2010 is for the construction of a storage /maintenance facility in the base of the water storage tank that was constructed in the park. Funding programmed in 2011 includes 14 dug out shade structures and an additional parking lot. Funding in 2012 includes design work to convert park facilities from well water to City water with construction programmed in 2013. Funding identified beyond 2014 includes the construction of an additional ball diamond with lighting, an additional restroom, bike paths, a woodland nature trail and tennis /basketball courts. 4 -29 9/13/2010 M: \PA \Capital Budgets \201 ICIP\Pinal DocumentA Major section 4 \4 -29 Darree Plds Dev - Major.doe City of Dublin Proposed 2011 -2015 Capital Improvements Program Park and Recreation — Maior Proiects Coffman Park Expansion (Proiect #GR City Council has adopted a policy to acquire the properties along Post Road from 6124 Post Road east to existing Coffman Park. The Coffman Park Expansion Plan Task Force (the Task Force) was created by City Council in 2002. The Task Force considered a wide range of optional park expansion ideas and formulated and compiled its recommendations and concept plans into the Coffman Park Expansion Task Force Report. The Task Force Report was reviewed and adopted by City Council on November 3, 2003. The final property previously identified to expand Coffman Park was acquired in early 2009. The funding programmed in 2010 provides for an analysis of potential phasing of the elements identified in the Task Force Report and preliminary cost estimates. This information is necessary to begin evaluating the timing and amount of funding needed to begin future development. 4 -30 9/13/2010 MArA \Capital Budgets\201 I C1P\Pinal Document \4 Major section 4 \4 -30 Coffman Pk Bxp- Major.doc City oI' Dublin Proposed 2011 - 2015 Capital Improvements Program Park and Recreation — Maior Proieets AmberleiEh Communitv Park (Proiect #GR The City acquired approximately 12 acres of riverfront property in 1997 and, as part of the Amberleigh North residential development, the developer dedicated approximately 11 acres of riverfrom property to the City. The two tracts of land abut and will be utilized to develop a community scale park along the Scioto River. The community park will provide access to the Scioto River and surrounding natural areas. Master planning was completed in 2001. The Master Plan provides potential homeowners with information on the plans for future development. The funding in 2010 provides for improvements that include a parking lot, community scale playground, central pavilion with restrooms, sidewalks and landscaping. Funding in 2013 and 2014 provides for design and construction of a river overlook, a foot bridge, trails, bikepath and a conditioned river access stairway that will complete phase I work. These elements, originally programmed in 2010, were deferred due to the decision to construct a central pavilion with restrooms rather than a group shelter. The funding programmed in 2015 provides for design of future park elements which include a children's discovery garden, a canoe launch, boardwalk/pier, bike paths, restrooms, trails, hard courts and a woodland overlook shelter. 4 -31 9/13/2010 M AFA\Capital 13udgels\2011CIP\Pinal Document \4 Major section 4 \4 -31 Amberleigh Canon Pk- Major.doc City of Dublin 2011 - 2015 Capital Improvements Program Park and Recreation — Maior Proicets Emerald Fields (N.E. Ouad Park) (Project #GR9904 This project provides for the development of the park in accordance with the completed Master Plan. Work completed in the park includes the neighborhood park component, grading and seeding of the soccer field area, the installation of a well and irrigation, ball diamonds, and the construction of a parking area for the soccer fields. Funds programmed in 2012 will complete the final phase of the Emerald Fields development. Improvements include an icon shelter and plaza area in the ball diamond area, sand volleyball and basketball courts adjacent to the central restrooms, parking lot lighting and irrigation system upgrades. 4 -32 9/13/2010 M: \FA \Capital Budgets\201 ICIP\Final DocumentA Major section 4 \4 -32 Emerald Fields (N B Quad Pk)- Major.doe City of Dublin Proposed 2011 - 2015 Capital Improvements Program Administration — Maior Proiects Parkland Acquisition (Project #ALI1021 The amount programmed is based on estimated revenue in the Parkland Acquisition Fund. For the most part, the revenue credited to this fund is from property tax revenue generated from the City's inside millage. The property tax revenue from the City's inside millage (1.75 mills) was allocated 100 percent to the Parkland Acquisition Fund from 2001 -2006. Beginning in 2007, the City began allocating .95 mills of the total 1.75 mills to the Parkland Acquisition Fund and the remaining .80 mills was allocated to the Capital Improvements Tax Fund. For 2010 and 2011, the City will allocate 1.4 mills to the Capital Improvements Tax Fund and the remaining .35 mills to the Parkland Acquisition Fund. Beginning in 2012, the proposed CIP allocates .80 mills to the Capital Improvements Tax Fund and the remaining .95 mills to the Parkland Acquisition Fund. The funding in the Parkland Acquisition Fund can be used for the acquisition of parkland, open space and /or sites for recreational facilities. Prior to the acquisition of land, legislation authorizing the acquisition is required to be adopted by City Council. The funding programmed also provides for the City's annual commitment of $385,000 to the Franklin County Metropolitan Park District and the annual debt service payments on the debt issued to acquire the land for the expansion of Coffman Park. The final debt service payment for the expansion of Coffman Park will be made in 2020 and the final payment to the Metro Parks is scheduled to be made in 2017. The following provides a recap of estimated revenues available less committed obligations: 2011 2012 2013 2014 2015 Estimated revenue $ 650,000 $ 1,725,000 $1,725,000 $1,725,000 $1,725,000 Less: Payment to Metro Parks (385,000) (385,000) (385,000) (385,000) (385,000) Debt service 22( 8,134) 225 684 22( 5,243) 242 632 23( 3,445) Estimated balance available $ 36,866 $ 1,114,316 $ 1,114,757 $1,097,368 $1,106,555 As discussed previously, staff is recommending that the Parkland Acquisition Fund be utilized to acquire right -of -way and /or easements for bikepath connections. We have estimated that we will need approximately $325,000 for acquisition to construct the Brand Road bikepath connection which is programmed for construction in 2010 and 2011. 4 -33 9/13/2010 M:\PA\Capital Budgets\2011CIP\Pinal Docummv \4 Major section 4 \4 -33 Parkland Acquisition -Major .doe City of Dublin 2011 - 2015 Capital Improvements Program Sanitary Sewer System -Major Projects Sewer lining and repair (Project #ES0701) The funds allocated will allow for the repair and lining of the sanitary sewer lines in Dublin. The lining of the City's clay pipe will reduce inflow and infiltration (I and I) of water in the sanitary sewer system. The future schedule for the repair and lining of the main sewer lines will be based on the guidelines and /or requirements established by the Ohio EPA. The 2010 allocation included funding to reline the 36" Dublin Road trunk sewer line. The City will receive American Recovery and Reinvestment Act (ARRA) stimulus monies of approximately $383,000. This project has been completed. An additional $2,000,000 in improvements has been programmed for 2012. The scope of work will be dictated based on the results of the Sanitary Sewer Evaluation Study (SSES) required from the "Director's Final Findings and Orders" issued by the Ohio Environmental Protection Agency (OEPA). The project is funded from the Sewer fund. 4 -34 9/13/2010 M\PA \Capital nudgets\201 IC1P\Rnal Document \4 Major section 4 \4 -34 Sewer lining and repair- MaJor.doe City of Dublin 2011 - 2015 Capital Improvements Program Sanitary Sewer Svstem -Maior Proiects South Fork sanitary extension (Proiect #ES0601 This project provides for the extension of a main sanitary sewer line to serve the area within the Central Ohio Innovation Center. The extension of sanitary sewer service in this area is in the Pre- Annexation Agreement for 7679 Post Road (Costner). This project has been added for economic development purposes. A portion of the project costs will be recovered from the benefiting properties. Approximately 45% of this project is for oversizing and will be the responsibility of the City. This project will be completed in two phases. Phase I is currently under construction and Phase 2 has been programmed for 2011. The City was awarded American Recovery and Reinvestment Act (ARRA) monies of approximately 163,000.to partially fund Phase 1 of the project. This project is funded from the Sewer fund 4 -35 9/13/2010 M: \FA \Capital Budgets\201 ICINFinal Document \4 Major section 4 \4 -35 South Fork Sanitary Extent - Major.doe City of Dublin Proposed 2011 — 2015 Capital Improvements Program Water Distribution System - Maior Projects Rings Road waterline (Project # EW1101) This project is to install a 16 inch waterline from Avery Road to "relocated Rings Road." This will create an additional main loop in the water distribution system to maintain pressures and fire flows in the Southwest area. The funding source for the project will be the Water Fund. 4 -36 9/13/2010 M: \I'A \Capital Budgets\201 ICIP\Pinal UocwneniA Major section 4 \4 -36 Rings Road waterline- Major.doc City of Dublin Proposed 2011 - 2015 Capital Improvements Program Water Distribution System -Maior Projects Dublin Road water tower (Project # EW1201) This project was identified as part of the utility infrastructure study completed in conjunction with the update of the Community Plan. This project has been accelerated based on need. Funding has been programmed in 2010 for acquisition of the site necessary to construct the tower, funds in 2011 are for design and funds programmed in 2012 are for construction. The tower will be located on Dublin Road near the Bogey Inn and will be funded from the Water Fund. The City plans to issue debt for the construction of the tower. 4 -37 9/13/2010 M: \PA \Capital Budgets\2011CIPTinal DocumentA Major section 4 \4 -37 Dublin Road water tank- Majordoc City of Dublin 2011 — 2015 Capital Improvements Program Storm Water Svstems - Major Projects Stormwater improvements (Project_ #_ FF0201 Funding over the next five years has been programmed for various improvement needs identified in the updated Stormwater Master Plan recently completed by Camp, Dresser & McKee. It is anticipated the final draft will be available for Council review in the fall. The projects programmed in the future are subject to change based on the results of the Study. The current funding in 2011 provides for preliminary design work of future stormwater improvements. Although no stormwater areas were considered critical, two projects were identified and programmed in the five year period. Blazer Parkway /Frantz Road /Waterford Village improvements were programmed in 2013 and Stonewall Court improvements were programmed in 2014. These projects were selected as the modeling analysis indicated that the system may have issues during a five (5) year rain event. A five year rain event is fairly frequent and is what the City uses to design the storm sewer system. 4 -38 9/13/2010 MAFA\Capital nudgets\201 )CIPTinal Document \4 Major section 4 \4 -38 StorniNku Improvements - Major.doc City of Dublin 2011 — 2015 Capital Improvements Program Administration — Maior Proiects Municipal Facilities (Proiect #AB0601 Based on City Council goals and recommendations included in the adopted Community Plan, the site for a future Municipal Building has been acquired. The annual debt service payments on the debt issued to acquire the site are programmed in the Parkland Acquisition Fund. In 2006, an evaluation of the City's space needs was finalized. Funding was programmed in 2007 to address near -term space needs and was utilized to complete the renovation project at the Dublin Community Recreation Center. Funds programmed in 2010 include costs to renovate areas of the Service Center. Renovations include the construction of offices and handicapped accessible restrooms. Funds programmed in 2011 are to add an additional parking area on the east side of the Service Center to accommodate the relocation of work units. The Fleet Building expansion for the sign shop operation and the addition of mechanics bays has been programmed beyond 2015. Additional review and analysis of the Fleet Building and operations will be completed before the project is initiated. M1 9/13/2010 M: \FA \Capital Budgea\201 ICIP\Final Document \4 Major section 4 \4 -39 Municipal Facilities - Major.doc City of Dublin 2011 —2015 Capital Improvements Program Service -Major Proiects Unerade fuel facility for Compressed Natural Gas (CNG) (Proleet 9AB1002 Clean Fuels Ohio, which is a statewide non -profit organization dedicated to promoting the use of cleaner, domestic fuels and efficient vehicles, has been designated by the Department of Energy as a Clean Cities Coalition. On behalf of twenty six different organizations including both local government and private industry, Clean Fuels Ohio coordinated the submission of a statewide project titled the Ohio Advanced Transportation Partnership. If fully funded, this $11 million dollar project would deploy 283 alternative fuel and advanced technology vehicles as well as multiple compressed natural gas and propane refueling stations and electric vehicle recharging stations. Dublin is one of the participating governments. The focus area for this grant includes the conversion of traditional fleets to alternative fuel or advanced technology vehicles as well as improving the necessary infrastructure to support these fleet conversions. This project includes funding for the infrastructure portion of the conversion to add the necessary infrastructure to dispense CNG at our current refueling station. In addition, the City intends to evaluate the use of these CNG fueling stations for limited access to the public. The City of Dublin is partnering with IGS Energy on the project and has agreed to share in the associated cost. IGS has committed a minimum of $275,000 towards the project. Clean Fuels Ohio will serve as the Grant Administrator for the United States Department of Energy (DOE). The City entered into a Grant Award Agreement with Clean Fuels Ohio in August. The City has been awarded a grant in the amount of $1,511,100 for the completion of the fuel facility for compressed natural gas (CNG) and the purchase of 44 CNG vehicles (programmed in Administration — Fleet Management). The City's minimum contribution towards the project is $2,209,108. 4 -40 9/13/2010 MAIWCapital Bud gels\20I ICIF \Final Document \4 Major section 4 \4-40 Upgrade fuel facility for CNG. doe City of Dublin 2011 - 2015 Capital Improvements Program Administration — Maior Projects Historic Dublin (Project #AB0602) Funding in the amount of $50,000 was carried over from 2009 for wayfinding in the Historic District. An additional $200,000 is programmed in 2010 for payment to American Electric Power (AEP) related to the burial of the overhead utilities. Based on the results of the Goody Clancy study, funding in the amount of $250,000 has been programmed in 2010 through 2012 to fund potential improvements that may be identified for the Historic District. i. 9/13/2010 M: \FA \Capital Budge(s\2011CIP\Final DoGument\4 Major section 4 \4-41 Historic Dublin- Major.doc City of Dublin 2011 - 2015 Capital Improvements Program Administration — Major Projects Bridge Street Corridor (Project #A131301) A significant focus area for 2011 and beyond will continue to be the Bridge Street Corridor. The intent is to develop a community -based vision for Bridge Street /State Route 161 from Interstate 270 to Sawmill Road, including the Historic District. Evaluation continues on the development and redevelopment opportunities of key sites within the corridor to create a more sustainable, walkable, urban environment and to seek ways to better capitalize on one of the City's most treasured assets, the Scioto River. An allocation has been programmed in 2013, 2014 and 2015 for potential improvements in this area. 4 -42 9/13/2010 MAM \Capital Budgets\201 ICIPTinal Document \4 Major section 4 \442 Bridge Street Corridor.doc City of Dublin 2011 — 2015 Capital Improvements Program Administration — Maior Proieets Computer hardware and soft vare (Project #AIl101) The annual requests reflect the Five -Year Technology Strategic Plan that has been developed by the Director of Information Technology. Detail justifications are included for 2011. 4 -43 9/13/2010 MAFA \Capital Budgets\2011CIPWinal Document \4 Major section 4 \4 -43 -0 Computer new Software - Major.doc 91212010 Information Technology 5 Year Budget Plan - 2011 -2015 Proposed - Dept/ Div City Wide City Mgr Office Legislat. Affaire Volunteer Servic Events Economic Dee Facilities Court Services Community Rel LU & LRP Finance Human Res IT Police (in priority) S &U (in priority) Fleet Engineering Bldg Slits Parks & Open Spaces Recreation Svcs TOTAL I CITY OP DUBLIN_ 2011 2012 2013 Citizen Service Request System $40,000 Upgrade City Hall iSenes or HTE to Windows $200,000 Citywide VAR enhanced utilization $25,000 Cityworks work orders - Web upgrade $20,000 Upgrade Redundant iSerles or HTE to Window; $50,000 Interactive voice response (IVR) enhancemt $1o,oao Enhance VAR /wireless systems 525.000 Citywide WiFi enhanced utilization $25,000 Network management/security upgrade $25,000 PCs upgrade operating system /office suite $85.000 PCs upgrade operating system /office suite $9g000 PCs upgrade operating system /office suite $90,000 Sewer and storage upgrades $35,000 Server and storage upgrades $35,000 Additional PC operating system /office suite $7,500 Additional Phone Equipment 510,000 Additional Phone Equipment sio0oo Server and storage replacement/upgrades $aL000 GIS enhancement/ data warehousing 525,000 GIS enhancement/ data warehousing $25,000 GIS enhancement/ data warehousing $25000 Network management / security upgrade $20,000 Network management / security upgrade 320,000 Customer Relationship (CRM) enhancement $10.000 Enhance Document Imaging $15000 Enhance Document Imaging sio 00o Enhance Document Imaging $10,000 Network storage upgrades $50,0Oo Network storage upgrades $50gDo Additional Phone Equipment $5.000 Vehicle GPS Mgmt enhancement 53000 Analyze /test HTE to Windows environment $25,000 Enhancements to HTENJindows environmel $25,000 Analyze /lest cloud computing applications s25,000 Cloud computing $25,000 Interactive voice response (IVR) enhancement $10,0D0 PC replacement $75,000 PC replacement $75,000 PC replacement SK000 Monitors (20) $5000 PCs - new positions $5,000 PCs - new positions $5,000 Printers 525,000 Monitors (20) $5,000 Monitors (20) $5,000 Cabling 510,000 Printers $25,000 Printers $25,000 Misc. hardware /software 520,000 Cabling $10,000 Cabling $5,000 Misc. hardware /software $20,000 Misc. hardware /software $25,000 Replace laptops for Council members (7) $8,000 Enhancement to Legislative applications $1eeno as Enhancement to Volunteer systems $10,000 DIP technology enhancements $7,500 DIF technology enhancements $7,500 DIF technology enhancements $7.500 CIS economic developement application $10,000 Handheld mobile devices- Facilities (2) $8,500 Work order enhancements $10,000 Vehicle GPS utilization (15) $12,000 Hundred mobile devices for Facilities $5,000 Digital recording system for Court ($5,000) (court Fu Digital microfilm scanner $35,000 Additional applications (court Fun Interactive voice response (IVR) ($20,000) (Conn Fund) Enhance Interne Iffi ranet/Community Rel $5,000 Enhance IntemeVlntranet/Community Rel $5,000 Enhance IntemeVlntran yb Community Pat $5,000 Aerial photography /layers for GIS $40,000 Aerial photography /layers for GIS $40000 Aerial photography /layers for GIS $50,000 Mobile computers (Code Enf -5) $25,000 Enhancements to Income Tax systems Sio,000 Photo ID enhancements $5,000 HR management system enhancements $5,000 Photo ID enhancements $5,000 Asset Data Collection update s25,00D Replace Dispatch Mapping system (911 fond)$95000 911 Fund Upgrade Justice iSenes or HTE to Windows $150.000 Upgrade to message broadcasting system $35,000 Mobile computers upgrade (10) $50,000 High Resolution displays for cmisers(10) $20,000 Communication center upgrades s oroo Cruiser mounts /console equipment $15,000 Mobile computers upgrade (10) 550,000 Mobile computers upgrade (10) $50,000 Cruiser WiFi /AVL enhancements $15,000 Cruiser mounts /console equipment $15,000 Cruiser mounts /console equipment $20,000 Mapping /Global positioning enhancement s15,0oo Mapping /GPS /Crime Analysis $25,000 Mobile computers for work orders (7) $35,000 Work Order system enhancement 510,000 Enhance sewer inspection technology $10,000 Mobile computers (5) $25,000 Enhance Vehicle GPS utilization (6) 34.800 Asset Mgmt / Data Collection $15.000 Asset Mgmt / Data Collection sle oo Service Complex Info Screen $3,000 Enhanced mobile device / GPS utilization $10,000 Enhance sewer inspection technology $20.000 Scanner 51,500 Fuel Mgmt enhancements $36,000 Fleet / Fuel system enhancement $10,000 Fleet Mgmt enhancements(graphicsil2addli an 510,000 Mobile GPS devices - work orders(Electric 2) 510,000 CAD / ArcView upgrade/enhancement SID 000 Work Order System enhancement $10,000 Pavement Management enhancements $25.000 LiDAR Data Acquisition (Elevation Data) $25.000 Review Servieea/Rldg Stds counter enhanceme $25,000 Inspectors mobile computers (7) $35,000 Additional applications/enhancements $25,000 Review Services technology enhancements 310,000 Mobile computers for work orders(7) $26,00D Asset Mgmt / Data Collection slo,000 Work Order /Cemetery system enhancement $10,000 Web -based Cemetery enhancement $2,500 Asset Mgmt / Data Collection 31g0o0 Scanner $1.500 Mobile devices for work orders(7) $35,000 Customer Service enhancements 315000 CUSiOmef Service enhancements $15.000 Customer Service enhancements Verde Photo ID enhancements 35,000 Oultloor pools technology enhancement Sto,000 $901,300 $1,122,500 $955,000 4.43 1 IT 5 Year Plan 2011 -2015 Proposeds25)4nal ds Page i of 2 91212010 Information Technology 5 Year Budget Plan - 2011 -2015 Proposed - Dept / Div City Wide City Mgr Office Legislat. Affairs Volunteer Servic Events Economic Dev Facilities Court Services Community Rel LU & LRP Finance Human Res IT Police (in prionty) S &ll (in priority) Fleet Engineering Bldg Side Parks & Open Spaces Recreation Svcs TOTAL 2014 2015 Citywide WiFi enhanced utilization $25,000 Citywide WiFi enhanced utilization $25.000 Interactive voice response (IVR) enhancement slo.000 Network management'securlty upgrade $25,000 Network management security upgrade $25.000 PCs upgrade operating system /office suite 595,000 PCs upgrade operating systemlomce suite $95,000 Additional PC operating system /office suite $7,500 Atltlilional PC operating system /office suite $7,500 Server and storage replacement/upgrades $35,000 Server replacements 7 upgrades $25,000 GIS enhancement/ data warehousing $25,000 GIS enhancement/ data warehousing $25,000 Network management /security upgrade $20,000 Enhance Document imaging stg000 Enhance Document Imaging sis,000 Additional Phone Equipment $5,000 Network storage upgrades $50,000 Enhancements to HTE(Windows environme S25,000 Additional Phone Equipment $10,000 Cloud Computing $25,00D Cloud Computing $25,000 Enhancements to HTEANindows applications $50,000 PC replacement $95.0eo PC replacement $85,000 PCs - new positions $5,000 PCs - new positions $5,000 Monitors (20) $5,000 Monitors (20) $5,000 Printers $25,000 Printers $15,000 Cabling $5,000 Cabling $5,000 Misc. hardware /software 525000 Misc. hardware /software $20.000 Replace laptops for Council members (7) $8,000 Enhancements to Volunteer systems $10000 DIF technology enhancements $7,500 DIF technology enhancements $7,500 Work order enhancements 55000 Work order enhancements $6,000 Handheld mobile devices for Facilities $5,000 Handheld mobile devices for Facilities $5,000 Records Mgmt enhancement 310,000 PCs /laptops for Court staff ($6,000) (coon TOr Enhance IntemeVintfanet/Communily Rel $5,000 Enhance Internet/Intranet/Community Rel $15,OOD Aerial photography / layers for CIS $40,000 Aerial photography /layers for GIS $50,000 Mobile computers (Code Enf -5) $25,000 Enhancements to Income Tax systems $10,000 HR management system enhancements $10,000 Photo ID enhancements $5.000 Plotter (GIS) $15,000 Enhancements to HTE/Windows environme $25,000 Enhance cruiser digital camera system(5) $35,000 High Resolution displays for cruisers(10) $20,000 High Resolution displays for cruisers(10) $20,000 Mobile computers upgrade (10) $50,000 Mobile computers upgrade (10) S50,000 Cruiser mounts /console equipment $20,000 Cruiser mounts /console equipment $15,000 Mapping /GPS /Crime Analysis $25,000 Communication center upgrades $5,000 Work Order system enhancement $10,000 Mobile computers (5) $25,000 Mobile devices for work Orders (4) $17,000 Asset Mgmt / Data Collection $10.000 Asset Mgml / Data Collection $10,000 Enhanced mobile device / GPS utilization $10.000 Fleet / Fuel system enhancement $10.000 Work Order system enhancement 51o.000 CAD / ArcView upgrade /enhancement $10,000 Inspectors mobile computers (8) $40.000 Pavement Management enhancements $25,000 CAD / ArcView upgrade/enhancement $10,000 Inspectors mobile computers (7) $35.000 Review Services /Bldg counter tech enhanceme $25,000 Review Services technology enhancements Sto,eoo Web application enhancements $25.000 Work Order /Cemetery system enhancemen sm,000 Asset Mgmt / Data Collection $10,000 Asset Mgmt / Data Collection 51o,0oo Mobile tlevices for work orders(7) $35,000 Customer Service enhancements $25.000 Customer Service /Registration enhancements slg000 Outdoor pools technology enhancement $5,000 $930,000 $905,000 7 1 1TY OF DUBLIN.. 4 -431 ITS Y¢ar Plen 2011 -2015 ProPOSatl(635)linal.xls Page 2 012 CIP TECHNOLGY REPORT FOR 2011 Information Technology Division "I'll This CIP technology report gives a brief narrative of the many citywide technology projects for 2011. These projects are in line with citywide and divisional goals and objectives to enhance customer services along with improving staff productivity. Citizen Service Request System $40,000 A Request system (or Citizen Request Management (CRM) system) was acquired as an integrated component of the newly implemented Cityworks work order system. A Web interface is desired in 2011 for citizen interaction that is also linked directly to our work order entry. Further enhancements to accommodate this system are anticipated, including the possible expansion to various call takers throughout the city. This application provides a Q &A database to respond to requests in a consistent manner, and the tracking citizen calls, work requests, complaints or compliments. Benefits: • Frontline call takers, who assist our residents on a daily basis, will have better resources at their fingertips for answering questions, routing calls, and handling requests in a consistent manner. • The Web based Self Service functionality will allow citizens to post chipper requests, missed trash complaints, etc. on line thereby providing a more modern approach to customer service, minimizing call volumes, and streamlining services. o Citizens can be automatically notified of the progress of their request • This will give us the ability to track requests; response times and ensure that requests are being addressed. • Staff time saved from manual work order entry enabling time for other necessary tasks • Performance measurement is available with request tracking Work Order system —Web Upgrade $20,000 A new citywide work order /asset management system (CityWorks) was implemented in 2008 in Streets & Utilities, Parks, Facilities and Engineering (Electric and Sign Shop) and is planned for use in other appropriate city work units. The upgrade to the Cityworks work order Web System will enble: • Growth — By increasing to any number of users with no additional work or cost • A mobile workforce is enabled without cost and implementation of supporting systems. The processing of work orders out in the field is desired by the divisions using this system as this will increase staff productivity, efficiency and work order accuracy. • Productivity will improve as Crew Supervisors will spend less time in the office and have more direct contact and management of their staff. • The expansion of CityWorks into a more customer service based system to centrally process citizen requests: See Citizen Service Request System above: Citywide WiFi enhanced utilization $25,000 Expanding the use of our citywide WiFi infrastructure is a continuous effort. High speed wireless connectivity to our city network opens up numerous areas for us to improve our efficiency, safety, and enhance our customer service. In 2011, the WiFi network will be greatly improved, providing connectivity throughout the majority of the city. These funds will allow us to improve and add additional video functionality for the skate park; allow us to install incident cameras along US33; provide a means to deploy cameras in areas that see spikes in criminal activity; additional traffic control communication; camera deployment for intersection observation; Police cruiser enhancements to upload video and to access to any WiFi camera; City buildings security access via the Web; outdoor pool connectivity to the city's network; and coordinate fiber uses with Dublin Schools for camera access and /or building security access systems. Significant savings would be realized by utilizing our WiFi network versus installing expensive fiber connectivity. These funds will ensure we can purchase the technology needed to get the most out of our capital investment in the network. Page I of 7 CIP Technololzv Report for 2011 Information Technoloay Division PC operating system /office suite $85,000 The Microsoft operating system, Office Suite (Word, Excel, Access, PowerPoint), Project, Photoshop and other Microsoft applications need to be continually licensed for all of the city's personal computers. • Server replacements / upgrades $35,000 Server upgrades are a continual need due to the continued increased processing demands and expansion of network applications. The need for continued expansion of our network storage space is also required. Additional Telephone System equipment $10,000 The City's telephone system will be finished for all City buildings in 2010. Any anticipated additional equipment is budgeted in 2011. • Telephones are added and repaired every year. Modifications are made due to changing business needs. We will also need to upgrade our call processing servers. • This will enable uninterrupted voice services for city staff • Future capabilities include benefits such as mobility features, call status features, enhanced phone book features, etc. GIS enhancement / data warehousing $25,000 GIS (Geographic Information Systems) is a technology that links valuable data to digital maps. In a government environment where almost everything is connected to a physical land location, GIS becomes important as an analysis, inquiry and reporting tool. The growth in GIS utilization has been dramatically realized over the last few years and with the dynamic development of the City of Dublin we anticipate a great deal of future growth. The proper use of GIS produces better planning, improved decision - making and increased staff efficiency that results in quicker and enhanced City services. This budget item is to allow maintaining a high standard and performing upgrades to our enterprise GIS server architecture. This includes our data storage system, data modeling, data analysis through server based geoprocessing and data dissemination (web GIS). New areas it will help us address are street networking and routing (to be used by Emergency Services, Streets and Utilities, Community Relations and the public) and 3D data analysis /presentation (used by LULRP, Engineering and the public). We also intend to create efficiencies by creating links between GIS and other enterprise data. Enhance Document Imaging $15,000 Document imaging applications have grown rapidly as the processing efficiencies, ease of information access and enhanced work flow have been realized by a variety of City divisions. Scanners and additional licensing is anticipated. Need: Building Standards and HR are two areas that will have significant document imaging growth in the upcoming year. One of Building Standards objectives is to automate the permitting process through redesigned workflow and software improvements which will require the purchase of additional software and consulting time. Additionally, Building Standards is scanning and microfilming Permit files that are classified as penmanent records. HR is in the process of scanning and micro filming inactive HR information that is classified as permanent records. Benefits: Building Standards will have more efficient access to historical permit files. Workflow will automate the permitting process reducing staff time and resources needed while providing improved communication between departments. HR will have efficient access to information needed for regulatory concerns as well as employee requests. The scanned documents will be accessed by Dublin staff through our network. The time spent performing manual searches fo documents answering customer questions, and filling document requests will be greatly reduced. The automation of the permitting process will provide greater efficiency and reduce redundant steps in the over all process. Page 2 of 7 CIP Tedmology Report for 2011 Information Technology Division Network Storage upgrades $50,000 • This is needed each year due to the ever increasing disk space needs and processing for new and upgraded applications. Base requirements increase every year. • This allows us to remain current on our applications and meet the requirements to perform the upgrades for which we are eligible. • This will allow us to accommodate increasing storage and backup needs. • We can add disk storage to keep short term backups and store files for our applications and customers. If we were not doing this we would have to increase our tape capacity each year which is equal to this cost. Either way it is required to function. • These enhancements will allow us to cooperate in joint ventures with other entities for items such as backup planning, remote connectivity, possible disaster recovery sites, radio communication, 911 backups, etc. • Analyze /test HT)✓ to Windows environment $25,000 An analysis and testing of moving our Sungard /I-ITE enterprise applications (Financial, Building Permits, Code Enforcement, Planning &Zoning, Police Records, Dispatch) from an iSeries to a Windows environment needs to examined. • Analyze /test cloud computing applications $25,000 An analysis and testing of moving our Office suite (Microsoft Word, Excel, Access, Powerpoint) and /or our e -mail messaging applications to a cloud computing environment needs to be examined. Cloud computing would process all applications and store information in an external Web environment. Interactive voice response (IVR) $10,000 An interactive voice response (IVR) system is a phone technology that allows a telephone caller to select options from a voice menu and interact with the phone system to process a transaction. This is not intended to remove any staff interaction with their customers, but to allow customers another avenue to transact business with the city. As this system is available on a 24/7 basis, this could be especially useful during staff non - working hours. This system will soon be implemented for building inspection requests in 2010. Other areas of potential users of this system in 2011 are for processing and general information access in LU &LRP, Police, Income tax, Recreation services, and general information about the City or an event, etc. • PC Replacement $75,000 Our PC rotation plan is to replace our staff PC equipment when it is 4 to 5 years old. • Printers $25,000 Instead of purchasing a significant quantity of printers in 2011, we are removing some of the older inefficient printers, including the copier /printers coming off of their lease. We changed our printer maintenance and toner vendor to Information Works in 2010. Information obtained fiom this vendor will give us a better management of printer maintenance, use and consumption cost. Thereby we will be able to start reducing the cost to print and inefficient hardware. • Mobile devices $81,500 Mobile devices for Streets & Utilities ($35,000), Parks ($28,000), Engineering ($10,000) and Facilities ($8,500) are desired for enabling remote access to the work order system. Facilities places this as a high priority while the other areas consider this a medium priority. This remote work order access is linked to the CityWorks work order system Web upgrade planned for 2011. The mobile devices will increase the productivity of staff by allowing them to receive, read and close work orders while in the field. Currently, our staff receives their work orders in paper form. A significant number of work orders per month are created just for scheduled preventive maintenance tasks. Staff must write down the time they spent on each work order and return it to their supervisor so that the work order can be closed. Page 3 of 7 CIP Teelinology Report for 2011 Information Technology Division Work being performed by Parks staff is documented detailing where they worked, what they did, how long did it take and what materials and equipment was used. This amount of data collection is currently being recorded manually and then transferred manually into the software system. In 2011 Parks proposes to try doing some of this data collection using mobile computers in the field to reduce some of the staff time and associated costs of collecting this data. The mobile devices will allow staff to call up their assigned work orders and enter in the pertinent information without having to keep track of the paperwork or return to the office to pick up more work orders. This will increase staff efficiency and productivity. The data itself will be used to better manage budgets and provide the information to predict future budget needs. The mobile devices for S &U work orders will provide them with the ability to open work orders in the field. Crew supervisors and administrators will be able to create the work order and input relative information while on job -site. This will keep the supervisors out in the field longer during the day and have them accessible to staff during the process. Additional Benefits will be increased tracking of work completed by field crews and thereby improve work order accuracy. This technology will also provide mobile access to GIS, live weather /radar, access to GPS tracking and reports while away from office. Using WiFi, administrators will have capability of monitoring snow and ice operations remotely. • Vehicle GPS utilization for Facilities and Streets & Utilities $16,800 An application that records the actual routes of the service trucks via GPS communication gives Streets & Utilities access to location - based, time sensitive information about the mobile workers and the associated assets via Internet access. Public inquiry to this data could be enabled. This system will enhance operation efficiency, maximize workforce productivity, improve vehicle management, enable actual vehicle tracking, increase accountability of valuable City assets, and allow for event analysis (snowplowing, street repair, etc.). The inclusion of 6 more vehicles with GPS communication is desired by S &U ($4,800) to make this system analysis more complete. Facilities would like to include 15 vehicles ($12,000) so that they can also utilize this equipment, workforce and process management application. Most facilities are utilized by both the first and second shifts, and GPS will enable management to determine how the vehicles are used (e.g. how many trips to City Hall do we make in one day ?) Analysis of the data may lead to a change in how work orders are assigned in order to reduce the overall number of vehicle trips. Benefits: • Improve asset management and improve productivity • Ability to manage and analyze events remotely (at home) • Customer service oriented as vehicles are tracked in real time • Aerial photography for GIS $40,000 With the continued growth and aging of our City, aerial photography linked to GIS mapping provides a tremendous analytical tool for LU & LRP, Engineering, Streets & Utilities, Parks, Police and Finance. Planning uses digital aerial photography on a daily basis to analyze development sites and to illustrate field conditions. This data is also used to track the status of development over time by comparing orthophotography flown in different years. This digital photography is also useful for Code Enforcement as well to establish certain dates of violations. Page 4 of 7 CIP Technology Report for 2011 Information Technoloy-v Division Asset Management /Data Collection $25,000 Various city divisions are in the process of improving their asset management to enable better work order processing and use of resources. The collecting of this information and getting the global positioning for GIS mapping is all part of this process. This information is also desired by the citywide asset management effort. GPS units are used to accurately map the various assets within the City and are useful in identifying and saving infrastructure improvements that might not be readily retrievable in the future. An example is when electric lines are being buried to serve ball diamond lights. Once the ground is restored, the exact location of the lines disappear. This could cause issues in the future when subsequent improvements occur in that area. There are numerous areas throughout Dublin where the storm sewer system is not mapped on GIS. S &U would like to ensure there are funds available to collect data from the field and be able to update all the appropriate data bases whether in Flexidata, CityWorks, and GIS. Eventually, there will be storm water modules created to track all inspections, cleanings and repairs made to the storm water system similar to that in the sanitary sewer program. Benefits: More reliable data will be available in GIS. When supervisors receive calls for service, having the proper information available in GIS will assist city staff in reducing response time to the resident or businesses. This could also provide a measure of improved safety when work is to be done on or near volatile assets. Police Division technology Replace Dispatch Mapping (High Priority) $95,000 The current mapping system used in the dispatch center was purchased and installed in 2004 and has served the center well. Working GIS, staff is recommending a mapping upgrade to take advantage of the enhanced features now available via the city's GIS system. These enhancements include automated vehicle location, dispatch by unit location technology, enhanced visual mapping, routing directions and improved plotting for wireless 9 -1 -1 calls. Benefits: • Improved plotting of wireless 9 -1 -1 calls • Improved dispatching capabilities with "dispatch using AVL" recommendations Mobile Computers Upgrade (Medium Priority) $50,000 Laptops assigned to fiont line cruisers are in use between 16 and 24 hours every day. In addition, these units are taken in and out of the cruiser several times a day to take incident and crash reports in the field. Every officer relies on these units for dispatching data, criminal history data and to take all incidents and crash reports as those processes are paperless. A plan to replace half of these systems every other year is proposed. Getting appropriate, accurate and timely information to the officers is critical to their safety, their ability to respond to the scene, and ultimately reflects upon their service to the community. Reliable units also ensure officers remain in the field to complete reports, greatly reducing the need for officers to come to headquarters to complete tasks. The computers that are replaced are passed on to other lower use functions within the division and to other departments & divisions for use. Cruiser mounts /console equipment (Medium Priority) $15,000 These funds are used for replacement of the electronics and physical docking stations that hold the laptop computer in the trunk of a cruiser and remote the screen and keyboard functions for use by the officer. Eight of these mounts are from the original MDC installation in 2001 & 2002 and have been removed and reinstalled in multiple cruisers. Repair costs are exceeding the value of these units and the manufacturer's offer of a maintenance agreement is cost prohibitive. Cruiser WiFi /AVL enhancements (Medium Priority) $15,000 With the build out of the Wi /Fi system, this project will allow for the installation of modem connectivity to make use of that system in the cruiser. In addition, this equipment will provide the global positioning data that will permit the real time monitoring of cruiser location for dispatching and tracking purposes. Benefits: • Improved dispatching • Improved Officer safety Page 5 of 7 CIP Technology Report for 2011 Information Technology Division • Enhance Fleet/ Fuel Management $46,000 (High priority) Fleet Management ($10,000) To better manage the vehicles, parts, and work orders the purchase of a graphics module for our Fleet Management system is desired to attach scanned images to various work processes. Two additional licenses are also desired to accommodate additional City staff. Benefits: • Asset management — documents linked to the asset to record damages, pictures, etc. • Parts management — warranties, etc. • Work orders — hand written requests, accident photos, etc. Fuel Management ($36,000) Rising fuel costs and vehicle maintenance are just two of the many concerns for our Fleet work unit. Our present fuel management system (GasBoy) has not been reliable, vendor support has been difficult, and is not readied to process alternative fuels. To more fully utilize both the Fleet and Fuel Management systems a replacement of the fueling system is planned for 2011. This will improve the management and accounting of all our fuel requirements along with improved vehicle maintenance via mileage tracking analysis. Our pumping stations will include 2 for gasoline, 4 for diesel, and I for compressed natural gas. Upgrading and enhancing current Fuel and Fleet Management systems will enables us to obtain accurate mileage figures, which will drive the PM scheduling of city equipment, and provide communication to customers that their vehicle has service due, as well as provide detail for various report requirements. (Billing, Fuel /Mileage Rpts, and CPM) Benefits: • Replacement of our current Fuel interface and reporting processes, with a more reliable, supportable, and efficient interface. • Ability to impose `mileage reasonability rules' at the fuel pumps, ultimately to restrict users from entering in mileage outside of a predetermined range for their vehicle. • Satisfy increasingly stringent fuel usage and mileage reporting requirements • Provide mileage driven preventative maintenance scheduling of city equipment, to ensure maintenance schedules are met • Improve conin unication with staff customers through email notification of service • Improve productivity • Better control of expenses • Current technology to accommodate the processing of alternate fuels Review Services /Building Stds counter enhancements, Web enhancements $25,000 Enhancements to improve the processing at the Building Division counter, the Plan Review area, and associated Web applications are desired in 2011. This could include document imaging, workflow changes, dual staff monitors, use of social media and other software or computer equipment. Continued implementation of an electronic review process will improve the plan review efficiency, more timely inspections, and enhance overall customer service. As Building Standards continues to refine its workflow processes and as they look at the new customer service demands that 21 st century technology has afforded, they need to look at technology enhancements that will help to advance their established processes to meet our ever - changing customer needs. With today's rapidly expanding information systems, a one size fits all approach, even in the mundane area of issuing building permits, cannot continue to be effective. To this end, Building Standards is requesting these technology enhancements as a "down- payment" for continual growth and development of the work unit. Our website needs to continue to be the information portal for customers to be able to obtain up -to -date information. Electronic permitting, Page 6 of 7 CIP Technology Report for 2011 Information Technology Division plan review and information sharing need to become a reality that our customers can benefit from its implementation. Along with Building Standards the use of electronic plan review will also be explored with the LU &LRP and Engineering divisions. Building Standards will continue to offer their traditional services with high quality. What is being requested will help them to enhance their traditional service delivery with new options for their customers. Web -based Cemetery enhancement $2,500 A web -based program that allows cemeteries to share their data and maps over the internet is desired by the Parks Division. Families and genealogists can search for burials by names or locations, can find a burial on a map of the cemetery, and then print it out. This is commonly used on the web, but the information can also be placed on a kiosk at the cemetery or City Hall. This will free up time spent locating gravesites for visitors and family members and allow our staff to concentrate on other City business. Customer service / Registration, Outdoor pools technology enhancements $15,000 Continual enhancements to customer service, technology enhancements to the renovated DCRC, and changes to the Recreation Center registration system are anticipated in 2011. Improved technology is also needed for the outdoor pools so that they are functionally equivalent to the operation at the DCRC. Recreation Services uses the RecTrac and WebTrac applications (fi om Vermont Systems) to process all memberships, registrations, sales and reporting. Our Recreation Services patrons and customers expect much of the same features /functionality as is available in the private /retail sector, and regular upgrades /updates helps us keep current with customer expectations. In response to numerous requests, key fob scanning and online payment of household account balances were implemented in 2010. In response to PCI (credit card) requirements, more secure credit card processing was implemented. Anticipated enhancements in 2011 include online ticket sales, membership renewals, and consolidation of ACH /monthly debit processing. Our application provider also offers an additional module, eRacTrac, a web -based version, which would allow staff to use the application off -site whether due to illness, emergency or increased responsiveness. An improvement must also be made to the network connectivity at the north pool. The current connectivity is unreliable for use in daily operation. Alternative means must be pursued in 2011 by means of the City WiFi or DubLink. Our point -of -sale units are also nearing their end of life. We need to replace these units with separate PC and touch screen monitors; both for the resulting cost savings and for ease of replacement should one component fail. Page 7 of 7 City of Dublin Proposed 2011 - 2015 Capital Improvements Program Police -Maior Protects Public Safety Answering Point (PSAP) equipment replacement (Project #PPI101) The current PSAP equipment was purchased and installed in 2001 and gave the Communications Center the capability to handle 20 digit caller ID and a mapping interface for the tracking of calls from wireless devices. This equipment still relies on traditional phone line trunking from AT &T which was the only option when purchased. Funding programmed in 2011 will upgrade the telephone equipment in the communications center to an internet protocol (IP) based network. This upgrade will allow for: • Advanced call routing and dynamic redundancy, giving the City the ability to send 9 -1 -1 calls to any other IP based PSAP in the state. • The ability to receive text messages, pictures and streaming video from wireless devices when that capability is provided by the telephone company. • A direct interface to the city's Cisco IP phone system. • Allow the dispatchers to start receiving caller ID information on all 10 digit calls and all intra -city calls placed to the communications center. • Upgrade to the current version of Windows. This project will be funded from the Franklin County 9 -1 -1 fund. 4 -44 9/13/2010 M:\PA \Capital Budgets\2011CIP\Pinal Document\4 Major section 4 \4-44 PSAP equipment replacement- Major.doc City of Dublin 2011 - 2015 Capital Improvements Program Administration -Maior Proiects Fleet Manaeement Program — Renlacements (Project #AV1101 The Fleet Management program was implemented to provide a replacement program that ensures the ongoing reliability of the City's fleet that is necessary to provide quality services. The program's goal is to provide efficient fleet and equipment while maximizing returns to the City through disposition. Revised in May 2006, vehicles are scheduled for replacement based on years of service and /or mileage. Based on additional evaluation of the City's fleet, some vehicles have been moved back based on low usage and condition. Final determination for replacement will be based on a physical evaluation of the vehicle. A listing of the vehicles to be replaced by department is included. The City is continuing its review of vehicle replacement criteria. Along with completing its annual physical inventory, the Director of Administrative Services has met with each department/division to ensure our current fleet is sufficient to effectively and efficiently meet the needs of our residents. Evaluations included quantity, quality and type of fleet. As a result of the evaluations, the City was able to identify potential areas of reduction through the use of pool cars as well as savings through "right- sizing" its fleet based on the need of the end user. It is anticipated that the City will be able to reduce its fleet by twelve to fifteen vehicles with an additional five vehicles being removed from individual fleets to be used as pool vehicles. Evaluations will continue as the City works toward Council's goal of environmental sustainability and the potential of replacing a large portion of its fleet with compressed natural gas (CNG) vehicles in cooperation with Clean Fuels Ohio (described below). On behalf of twenty six different organizations including both local government and private industry, Clean Fuels Ohio coordinated the submission of a statewide project titled the Ohio Advanced Transportation Partnership and submitted a grant through the United States Department of Energy titled the Clean Cities program. The focus area for this grant includes the conversion of traditional fleets to alternative fuel or advanced technology vehicles as well as improving the necessary infrastructure to support these fleet conversions. The City's portion of the grant includes the potential conversion of 44 City vehicles to compressed natural gas (CNG). Funding is included for the potential conversion of those vehicles. Funding to upgrade the fuel facility is listed as a separate CIP project. Also included is funding to replace three (3) dump trucks in 2010 and 2011. The City received a Diesel Emissions Reduction Grant (DERG) from the Ohio Department of Development. The DERG grant will pay 49% of the cost to replace the vehicles. Three vehicles qualifying for DERG funds were replace in 2009. All vehicles were due to be replaced by 2012. Two vehicles were moved from 2012 to 2011 to comply with the requirements of the grant. 4 -45 9/13/2010 M: \FA \Capital 6udgets\201 I CIP\Final Document \4 Major section 4 \445 Hart Maint Prog Rcpt - Maiocdoc City of Dublin 2011 - 2015 Capital Improvements Program (continued) Service -Major Projects Fleet Management Program —Replacements (Project 4AV1101) Dent. /Div. 2011 2012 2013 2014 2015 Streets /Utilities $160,000 $ 40,000 $275,000 $270,000 $240,000 Development 110,000 225,000 90,000 0 0 Parks /Facilities 635,000 225,000 560,000 210,000 0 Police 160,000 220,000 60,000 0 0 Miscellaneous 0 70,000 35,000 85,000 0 Total $1,065,000 $780,000 $1,020,000 $565,000 $240,000 4 -46 9/13/2010 M: \FA \Capital Budgets\201 ICINFinal Document \4 Major section 4 \445 Fleet Maint Frog Rep] -Major. doe City of Dublin 2011 - 2015 Capital Improvements Program Administration -Major Projects Equipment Management Program ( #AV1103) This request includes replacements and additions. Dept./Div. 2011 2012 2013 2014 2015 Streets /Utilities $220,000 $300,000 $100,000 $285,000 $55,000 Engineering -- -- -- -- Building Standards -- -- -- -- -- Parks and Open Space 75,000 45,000 260,000 240,000 360,000 Police -- -- -- -- -- Facilities Administration - -- -- Total $295,000 $345,000 $360,000 $525,000 $415,000 A breakdown of 2011 equipment includes: Streets and Utilities Replacements: Zero turn mowers (3) Wing mower for ditches Additions: Snow plows for smaller dump trucks Parks and Open Space Replacements: John Deere 5400 tractors (2) Slice seeder Zero turn mowers (3) Snow blower attachment Rotary broom attachment Skid steer Infield groomer Additions: Sports turf mower — Emerald Fields Utility vehicle — Emerald Fields Walk behind brush cutting unit 4 -47 9/13/2010 M: \FA \Capital nudgeu\201 IOPTinal Document \4 Major section 4 \4 -47 Equip Mgmt Prog - Major.doc 2011- 2015 Capital Improvements Program Funded Projects - Major By Category Others $119345,000 Facilities Parks $9,420,000 8% no )rtation 10,000 72% 1 13% �.4r ,...,. 2011 -2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM FUNDED PROJECTS Total Debt Debt Project Already to be Project Funding Project Cost Incurred Incurred Source Amount ET0 007 Central Ohio Innovation Center (COIC) roadway 9,829,000 Cash 859,000 improvements 412- Industrial Parkway relocation Federal funding 1,000,000 State funding 200,000 7,770,000 G.O. debt 7,770,000 ET0606 Central Ohio Innovation Center (COIC) roadway 545,000 Cash 545,000 improvements- 93- Eiterman Rod relocation G.O. debt ETO611 Central Ohio Innovation Center (COIC) roadway 1,325,000 Cash 1,325,000 improvements -NS -SR 161 improvements State funding G.O. debt ET0003 Central Ohio Innovation Center (CO)C) roadway 14,088,000 Cash 7,347,200 improvementsN6- US33 /SR 161 /Post Road interchange Service payments 500,000 Property taxes 6,240,800 G.O. debt ET0902 Central Ohio Innovation Center (COIC) roadway 191,000 Cash 191,000 improvements -0 -Post Preserve access modification ET0103 - I - uttle Crossing Boulevard extension- Plilcox Road to 2,465,000 Cash 90,000 Avery Road (TIP) Service payments 2,375,000 ET0104 Emerald Parkway-Riverside Drive to 13,110,000 Cash 764,000 Billingsley Creek(TIF) Property taxes State funding 900,000 Service payments 2,846,000 G.O. debt(scrvice payments) 8,600,000 ET0205 Emerald Parkway -Rings Road to Tuttle 2,964,000 Service payments 2,964,000 Crossing Boulvard (TIF) ETI 119 Relocated Rings Road 1,165,000 Cash 1,165,000 ET1202 Frantz Road utility burial (TIP) 825,000 Service payments 825,000 ET0810 Frantz Road - Dublin Road connector( TIP) 2,879,000 Service payments 2,879,000 ETI 101 Railroad Quiet Zones 490,000 Cash 20,000 State funding 470,000 ETI 103 LED street light replacement 2,300,000 Cash 300,000 G.O. debt 2,000,000 ET0405 Hyland Croy Road /Brand Road intersection (TIF) 2,973,000 Service payments 2,902,125 Developer contribution 70,875 ET0410 Avery- Muirfield Drive /Perimeter Loop / Perimeter Drive 4,340,000 Service payments 4,340,000 intersection (TIF) ET0508 Riverside Drive /SR161(TIF) 3,332,000 Service payments 3,132,000 ET0511 Avery- Muirfield/7'ullymore /Valley Stream /Avery Road 876,000 Cash 151,000 Permissive tax 725,000 ET0 005 Sawmill Road /Hard Road intersection (TIF) 2,685,000 Service payments 2,185,000 Developer contribution 500,000 ETI001 Cosgray Road /Shier Rings Road intersection 2,036,000 Cash 436,000 Permissive tax 1,600,000 E7 Hyland Croy- McKilrick Road roundabout 1,460,000 Cash 1,341,875 Developer contribution 118,125 ET0 004 Perimeter Drive /Commerce Parkway intersection and 1,617,000 Service payments 1,617,000 Perimeter widening E'r1401 1- 270 /US 33 Interchange phase I improvements 2,900,000 Cash 2,900,000 E7 Dublin Rd and Glick Rd intersection improvements 250,000 Cash 250,000 ET 1102 US33 /SR161 /Post Road eastbound ramps 150,000 Cash 150,000 ET 1004 Brand Road multi -use path/bike lanes 3,522,000 Cash 3,522,000 ET 1203 Dublin Road South multi -use connection 1,262,000 Cash 1,262,000 E Glick Road multi -use connection 690,000 Cash 690,000 M CFA \Captal Budget VD, I C10 -1 DO[ No MN01 eocr on 4k -EB RECCIP CIS 4-49 2011 - 2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM FUNDED PROJECTS Total Debt Debt Project Already to be Project Funding Noiect Cost Incurred Incurred Source Amount ET 1104 Muirfield Drive bike lanes 50,000 Cash 50,000 GT 1204 Emerald Parkway sharrows 180,000 Cash 180,000 GR9901 Darree Fields development 6,216,000 Cash Township funding 5,841,000 375,000 GR9902 Coffman Park expansion 50,000 Cash 50,000 0 GR9903 Amberleigh Community Park development 2,551,000 Cash 2,551,000 GR9904 Emerald Fields (N.E. Quad Park) development 5,503,000 1,225,000 Cash State funding G.O. debt 3,803,000 475,000 1,225,000 MAN Parkland acquisition 8,200,000 Property taxes(inside millage) 8,200,000 ES0701 Sewer lining and repair 5,073,000 2,200,000 2,000,000 Sewer Fund revenues Federal funding G.O. debt(Sewer Fund revenues) 489,800 383,200 4,200,000 ES0601 South Fork sanitary sewer extension 697,000 Sewer Fund revenues Federal funding 532,000 165,000 HW 1201 Rings Road waterline 730,000 Water Fund revenues 730,000 EW 1201 Dublin Road water lower 3,100,000 2,700,000 Water Fund revenues G.O. Debl(Water fund revenues) 400,000 2,700,000 EF0201 Stormwater improvements 3,373,000 Cash 3,373,000 ABO601 Municipal facilities 1,377,000 Cash 1,377,000 AB1001 Upgrade fuel facility for compressed natural gas (CNG) 2,175,000 Cash Federal funding 813,100 1,361,900 AB0602 Historic Dublin 3,643,000 Cash 3,643,000 AB1301 Bridge Street Corridor 750,000 Cash 750,000 AI0801 Computer hardware /software 5,565,000 Cash 5 PP 1101 PSAP equipment replacement 420,000 Franklin County funding 420,000 AV0801 AV0803 Fleet management program Fleet replacements Equipment add itions /replacements 4,780,000 2,305,000 Cash Federal funding Cash 4,460,000 320,000 2,305,000 9/13/10 TOTAL S136,807,000 511,195,000 S4,700,000 5136,807,000 1/ :lvMCePlvI8u0BVlE OV[umvnlW M,.— ... n<.4ERECCIP.. 4'56 2011-2015 Property Taxes $14,440,800 11% $26; 20% Five -Year Capital Improvements Program Funding Sources - Major TIF Service Payments $26,565,125 30% Cash Available $57,035,175 41% 4 -51 Utilities Other 2011-2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM MUNICIPAL DEBT This section provides information on the long -term debt obligations outstanding at December 31, 2009, the projected long -term income tax supported debt, a calculation of the long -term debt capacity and a recap of the annual debt service obligations. The Projected Long -Term Debt Schedule reflects that the estimated principal outstanding at the end of each year is within the recommended maximum amount. The Debt Service Payments Due (Income tax supported debt) schedule reflects that the total actual and estimated debt service obligations each year are within the actual and projected income tax revenue available for debt retirement. The difference between the two, or the "surplus ", will be used to "buy down" other capital project costs and issue less debt or be used to fund other capital projects. A schedule of debt service payments that are supported by sources other than income tax revenues is also included. 5 -1 9/13/2010 M: \FA \Capital Budgets\2011 CIP \Final Document \5 Municipal Debt section 5 \5 -1 Municipal debt.doc 2011 -201 5 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM LONG -TERM DEBT OBLIGATIONS As of December 31, 2009 Unvoted GO. Bonds Dale of Issue Date of Maturity Original Amount O/S Principal Paid From Income Taxes General Capital Fund Imp. Fund Other S ources(1) Water Tower Constuction 12/01/90 12/01/10 $2,200,000 $158,404 $0 $158,404 $0 Swimming Pool Construction 12/01190 12/01/10 1,200,000 84,921 0 84,921 0 Water System Improvements 12/01/90 12/01/10 1,550,000 111,309 0 111,309 0 Frantz Road Improvements 12101/90 12/01110 455,000 36,463 0 36,463 0 Service Complex 12/01190 12/01/10 2,400,000 173,200 0 173,200 0 Sanitary Sewer Lift Station 12/01/90 12/01/10 1,800,000 125,703 0 125,703 0 Rings /Blazer Water Tower 10/15/94 12/01114 4,100,00D 149D,000 0 0 1,490,000 Upper Scioto West Branch(2) 01/01/99 07/01/18 18,220,405 9,533,403 0 0 9,533,403 Avery- Muirfield Interchange 09/01/99 10/07/19 8,316,788 5,179,141 0 5,179,141 0 Rings Road Improvements(TIF) 12101/00 12101/20 3,535,000 2,425,216 0 0 2,425,216 Arts Facility Acquisition 12/01/00 12101/20 1,360,000 930,019 0 0 930,019 Arts Facility Renovation 12/01100 12/01120 755,000 519,036 0 0 519,038 Perimeter Drive Extension(TIF) 12101/00 12/01/20 3,940,000 2,713,069 0 0 2,713,069 Emerald Parkway -Phase 7A(TIF) 12/01/00 12/01/20 2,020,000 1,392,658 0 0 1,392,658 Service Complex 12/01/01 12/01/21 3,675,000 2,617,347 0 2,617,347 0 Municipal Pool South(OMB) 07/01/04 01/01/25 2,986,000 2,449,000 0 2,449,000 0 Industrial Parkway /SR 161 Improvement! 11/16/09 12/01/29 9,670,000 9,670,000 0 0 9,670,000 Darree Fields Water Tower 11116/09 12101129 2,015,000 2,015,000 0 0 2,015,000 Sanitary Sewer Lining 11/18109 12101/29 2,220,000 2,220,000 0 0 2,220,000 Total 72,418,194 43,843,891 0 10,935,488 32,908,403 Unvoted Special Assessment Bonds 2001 Special Assessment 12/01/01 12/01/21 1,700,000 1,217,653 0 0 1,217,653 Total 1,700,000 1,217,653 0 0 1,217,653 Voted G.O. Bonds #2 Sewer 07/01/79 12/01/10 225,000 5,000 0 0 5,000 Coffman Road Extension 12101190 12101110 315,000 21,000 0 21,000 0 Justice Center(Land) 12/01/90 12/01/10 890,000 60,000 0 60,000 0 N.E. Quadrant Parkland Acq. 12/01/90 12/01/10 1,225,000 80,000 0 80,000 0 Dublin Justice Center 10102/92 12101/11 4,100,000 449,000 0 449,000 0 Community Recreation Center 02/01/96 12/01/10 6,615,000 210,000 0 210,000 0 Community Recreation Center -Exp. 10/15/98 12101/18 3,998,000 2,085,000 0 2,085,000 0 Emerald Parkway Bridge 10/15198 12/01/17 7,518,000 3,862,000 0 3,862,000 0 Emerald Parkway, Phase 2(TIF) 10/15/98 12/01116 7,874,000 3,853,000 0 0 3,853,000 Woerner Temple Road 12/01/00 12/01/20 5,555,000 3,670,203 0 3,670,203 0 Emerald Parkway Overpass -Phase 7 12/01100 12/01/20 6,565,000 4,335,953 0 4,335,953 0 Coffman Park Expansion 12101/00 12/01/20 3,135,000 2,038,844 0 0 2,038,844 Total 48,015,000 20,670,000 0 14,773,156 5,896,844 Voted Special Assessment Bonds Tuller Road 10/15/94 12/01/14 1,185,000 450,000 0 0 450,000 Other Long -term Oblidalions Aryshire Drive Culvert(OPWC) 07/01104 01/01/14 279,748 125,887 0 125,887 0 279,748 125,887 0 125,887 0 Total Long -term Debt $123,597,942 $66,307,431 $0 $25,834,531 $40,472,900 (1) "Other Sources' include special assessment collections, real estate property taxes, water system revenues, service payments in lieu of taxes, and hotel /motel tax revenue. (2) Principal reduced per Change Order Agreement with City of Columbus. S'1312010 5 -2 M \FA \Capital 0u getsVO,CIPffloal Docume M Municipal Debt se<YOn $Qebl Inlo,malionals 4111 &411 V FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM PROJECTED LONG -TERM DEBT SCHEDULE (Income tax supported debt only) 2009 2010 2011 2012 2013 2014 2015 Principal outstanding at the beginning of the year Principal retired(1) Principalissued(2) Principal outstanding at the end of the year Recommended maximum amount of long -term debt(3) $29,853,852 $35,504,531 $31,686,918 $28,988,496 $28,358,231 $25,579,530 $22,664,715 4,019,321 3,817,613 2,698,422 2,630,265 2,778,701 2,914,815 2,960,864 9,670,000 0 0 2,000,000 0 0 $35,504,531 $31,686,918 $28,988,496 $28,358,231 $25,579,530 $22,664,715 $19,703,851 $75,918,559 $71,802,148 $81,621,096 $73,080,185 $71,737,270 $69,826,745 $69,527,696 (1) Based on long -term debt outstanding as of 12 -31 -09 and anticpated debt issuances. (2) Issuance of debt based on major project listing and anticipated funding schedule. The following isssues are anticipated: 2012 42,000,000 in long -term bonds for the installation of LED street lights. (3) Reflects the amount outstanding and the recommended maximum amount of additional debt from page 5 -4. 9/13/2010 M9FA \Capital Budgeta\ 011CIP \Final Document \5 Municipal Debt section 5 \Debt InformationAs 5 -3 2011 -2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM DEBT SERVICE PAYMENTS DUE (Income tax supported debt only) Debt Issue 2009 2010 2011 2012 2013 5,150,875 2014 Income tax revenue available for debt redrement(from page 3 -2) 20 15 9,886,140 Water Tower Construction $173,513 $161686 $0 $0 Balance available(3) $0 4,368,103 $0 4,869,725 s0 Swimming Pool Construction 92,785 86,681 0 0 $58,480,660 0 $51,286,380 0 $55,359,830 0 Water System Improvements 121,616 113,616 0 0 $ 47,162,030 0 0 0 Frantz Road Improvements 39,840 37,219 0 0 0 0 0 Service Complex 189,239 176,789 0 0 0 0 0 Sanitary Sewer Lift Station 137,342 128,308 0 0 0 0 0 Coffman Road Extension 26,194 21,435 0 0 0 0 0 Justice Center -land 69,850 61,243 0 0 0 0 0 N.E. Quad. Park Land 92,962 81,658 0 0 0 0 0 Justice Center Construction 326,978 320,304 140,760 0 0 0 0 Community Recreation Center 650,085 220,500 0 0 0 0 0 Community Recreation Center exp .(2018) 311,493 278,081 278,613 283,133 281,472 279,753 280.583 Scioto Brdge Construction(2017) 603,917 547,558 556,950 561,790 559,350 557,770 560,160 Avery- Muirfiield /US 33 interchange(2019) 610,786 610,786 610,786 610,786 610,786 610,786 610,786 Woerner- Temple extension(2019) 462,367 448,579 451,079 446,043 445,136 480,900 462,007 Emerald Pkwy - Perimeter /Shier Rings(2019) 548,135 528,780 530,957 525,042 523,991 566,106 543,886 Service Complex expansion(2021) 279,419 276,635 376,938 276,240 275,557 308,219 276,257 Swimming Pool Construction(2025) 221,004 220,598 219,787 218,587 218,022 217,104 216,830 Aryshire Drive culvert-OPWC loan(2014) 27,975 27,975 27,975 27,975 27.975 13,987 0 Land acquisition- economic development 500,000 500,000 489,500 0 0 0 0 Industrial Parkway /SR 161 improvements(1) 0 669,606 471,690 0 0 0 0 LED Street lighting(2) 0 0 0 246,000 246,000 246,000 246,000 Reserved for potential Bridge Street Corridor projects 0 0 0 500,000 500,000 500,000 500,000 Reserved for US 33 /SR 161 /Post interchange 0 0 0 1,048,350 1,048,350 1,048,350 1,048,350 Reserved for Eiterman Road relocation 0 0 0 321,900 321.900 321,900 321,900 Total 5,485,500 5,518,037 4,155,035 5,065,846 5,058,539 5,150,875 5,066,759 Income tax revenue available for debt redrement(from page 3 -2) 9,886,139 9,886,140 9,886,140 9,935,571 10,084,604 10,286,296 10,492,022 Balance available(3) 4,400,639 4,368,103 5,731,105 4,869,725 5,026,065 5,135,421 $ 5,425,263 Amount of additional debt that could be supported(4) $44904475 $44572480 $58,480,660 $49,691,065 $51,286,380 $ 52,402,255 $55,359,830 Recommended maximum amount of additional debt $40,414,028 $40,115,230 $52,632,600 $44,721,954 $46,157,740 $ 47,162,030 $49,823,845 (1) Beginning in 2012, the annual debt obligations will be paid from the Perimeter TIF Fund. (2) Estimated debt service obligations. (3) Funding not needed for debt service is utilized to fund cash basis projects. (4) It is not recommended that the total amount be issued in long -term debt. Estimate assumes 20 year bonds at 7.5% and level payments. Note - Payments include both principal and interest. The Avery- Muirfield /US 33 interchange and the swimming pool construction project includes the administrative fees for the State Infrastructure Bank loan program and the Ohio Municipal Bond program. s, J1010 M1FX,CapRal Budge,,011,t el D,wmMS MwJ T Debt section MDeW Infi, afion Ye 5-4 Hotel /Motel Tax Revenues Arts Facility 173,589 166,643 166,044 163,280 162,277 161,889 1 Total $ 823.0$6 = $7 413 15 $7„477 237 $�4$Q 1 $,� 490 4 S§ M=5, =5,, (1) Service payments are sufficient or exceed annual debt service obligations. (2) Private improvements are currently under construction. Until private improvements are completed and value established, the total amount will continue to be included in the Income Tax Supported Debt schedule. ' Amounts in 2009 -2011 trensfemed to the COIC Improvement Fund. TAICap M1Fg1Ca0;Ml BVE9aM2011oRFinaI OOCVmcnpS MUnitipvl Debt seNOnS \Debt lnfo,maOOn Krs 5 -5 2011 -2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM DEBT SERVICE PAYMENTS DUE (Debt supported by sources other than income tax revenue) 2009 2010 2011 2012 2013 2014 2015 Service Payments Emerald Parkway -Phase 2(2016) (1) $695.799 $641,166 $651,840 $650,540 $654,040 $646,240 $548.420 Rings Road improvements(2020) (1) 286,342 271,424 277,408 272,801 271,128 270,479 269,358 Woerner- Temple Road(2020) (2) 0 0 250,211 220,480 222,403 221,397 0 Perimeter Drive extension (2020) (1) 322,014 304,688 310,737 305,573 303,697 302,971 301,714 Emerald Parkway -Phase 7A(2020) (1) 165,481 159,071 160,057 157,391 156,422 156,048 155,400 Industrial Parkway /SR 161 improvements(1) 0 0 200,000 668,990 671,190 673,190 670,195 Emerald Parkway -Phase 8 (3) 0 0 843,900 843,900 843,900 843,900 843,900 1,469,636 1,376,349 2,694,153 3,119,675 3,122,780 3,114,225 2,788,987 Water and Sewer Funds Rings /Blazer Water Tower(2014) 355,550 360,360 358,400 355,480 356,600 356,440 0 Upper Scioto West Branch(2018) 1,350,725 1,350,725 1,350,725 1,350,725 1,350,725 1,350,725 1,350,725 Danee Fields Water Tower(2029) 0 138,486 139,773 138,173 141,573 139,873 138,215 Dublin Road Water Tower(2031) 0 0 0 140,000 140,000 140,000 140,000 Sewer Line Repairs(2029) 0 154,952 155,814 154,014 152,214 155,414 153,562 Sewer Line Repaim(2031) 0 0 0 160,000 160,000 160,000 160,000 1,706,275 2,004,523 2,004,712 2,298,392 2,301,112 2,302,452 1,942,502 Property Taxes(Voted) #2 Sewer 10,975 5,325 0 0 0 0 0 10,975 5,325 0 0 0 0 0 Special Assessments Tuller Road 108,800 108,680 108,240 107,480 106,400 0 Ballantrae improvements 126,942 176,431 128,616 128,299 129,537 128, 235,742 285,111 236,856 235,779 235,937 128,624 Property Taxes(Inside millage) Parkland acquisition- Coffman Park(2020) 252,046 236,485 228,134 225,684 225,243 242,632 233.445 Parkland acquisition -Hard Road(2009) 330,535 0 0 0 0 0 0 Metro Park contribution(2017) 385,000 385,000 385,000 385,000 385,000 385,000 385,000 Reserved for US 331SR 161 /Post interchange` 1 1,650,000 1,650,000 1,048,350 1,048,350 1,048,350 1, 2,462,581 2,271,485 2,263,134 1,659,034 1,658,593 1,675,982 1,666,795 Hotel /Motel Tax Revenues Arts Facility 173,589 166,643 166,044 163,280 162,277 161,889 1 Total $ 823.0$6 = $7 413 15 $7„477 237 $�4$Q 1 $,� 490 4 S§ M=5, =5,, (1) Service payments are sufficient or exceed annual debt service obligations. (2) Private improvements are currently under construction. Until private improvements are completed and value established, the total amount will continue to be included in the Income Tax Supported Debt schedule. ' Amounts in 2009 -2011 trensfemed to the COIC Improvement Fund. TAICap M1Fg1Ca0;Ml BVE9aM2011oRFinaI OOCVmcnpS MUnitipvl Debt seNOnS \Debt lnfo,maOOn Krs 5 -5 2011-2015 FIVE -YEAR CAPITAL IMPROVEMENTS PROGRAM NON -MAJOR PROJECT FUNDING Guidelines have been established for several key areas which the Administration has utilized in projecting the non -major capital needs. These are summarized as follows: Park Development The neighborhood park development priority is based upon the timing of subdivision build -out and input from residents. Evaluate the adequacy of active /athletic facilities in the community and the neighborhood parks. Identify opportunities to develop joint neighborhood and community parks with other governmental jurisdictions (i.e. Dublin City Schools and Washington Township). Program adequate funding for maintenance of existing assets. Bikeway System Improvements Bikeways are included as part of the City's major public roadway projects and include multi -use paths, bike lanes and sharrows. Identify connections and /or additions to the bikeway system which provide an alternate transportation system linking neighborhoods, community facilities and commercial destinations. Coordinate local system design with other governmental jurisdictions such as the Mid - Ohio Regional Planning Commission (MORPC), the Ohio Department of Transportation (ODOT) and other appropriate regional efforts. Identify the connections and /or additions that can be constructed by developers as part of private development. Annual Street Maintenance Program Investment for street resurfacing is based on anticipated life of the asset. A comprehensive pavement management system has been established to ensure acceptable levels of service are maintained in a cost - effective manner. The City evaluates the pavement maintenance needs annually and programs improvements based on roadway conditions. 6 -1 9/132010 MAWCapital Budgets\201 I CIP\Final Document \6 Non -major section 6 \Non -Major Project Funding.doc Guidelines — Non -major funding (continued) Asset maintenance Maintain the City's existing assets to ensure long -term viability. Maintain a comprehensive listing of the City's assets and identify the anticipated need for maintenance, repair or replacement. Evaluate and update the City's asset maintenance needs annually. As identified, specific budget requests will be included in the annual C1P budget and a final review and evaluation made by City Council as part of the Operating Budget review process. M S 9/13/2010 MAMCapital Budgets\201 I CIP\Final Document \6 Non -major section 6\Non -Major Project Funding.doc CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 DEPARTMENT/ 254 1,175 1,495 1,160 885 950 930 5,420 0 TOTAL DIVISION PRIOR 0 0 0 0 0 0 TOTAL BEYOND TO BE PARKS & RECREATION YEARS 2010 2011 2012 2013 2014 2015 11 - 15 2015 BUDGETED NON -MAJOR PRn.IFCTS ADMINISTRATION 254 1,175 1,495 1,160 885 950 930 5,420 0 5,420 SERVICE 0 0 0 0 0 0 0 0 0 0 PARKS & RECREATION 6,547 1,475 2,215 1,675 1,270 940 1,445 7,545 1,485 9,030 POLICE 60 130 340 90 35 0 0 465 0 465 SANITARY SEWER 0 15 0 0 0 0 0 0 400 400 TRANSPORTATION 1,006 4,585 4,120 4,655 3,945 4,090 4,200 21,010 830 21,840 WATER DISTRIBUTION 472 690 1,165 585 0 775 305 2,830 900 3,730 STORM WATER SYSTEM ol 3001 300 300 300 300 300 1,500 0 1,500 TOTAL 8,339 8,3701 9,6351 8,4651 6,4351 7,0551 7,1801 38,7701 3,6151 42,385 9/13/10 MAMCapital Budgets\2011CIPTinal Document \6 Non -major section 6 \Project summaries\ 6 -3 CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 PROJECT PROJECT PRIOR 125 0 0 0 0 0 0 0 TOTAL NO. DESCRIPTION I YEARS 0 60 450 400 400 400 TOTAL BEYOND TO BE AB1101 Building maintenance /renovations $000 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED ADMINISTRATION / NONMAJOR PROJECTS AL1101 Land ac uisition 0 125 0 0 0 0 0 0 0 0 AU1101 Utility service improvements 0 0 60 450 400 400 400 1,710 0 1,710 AB1101 Building maintenance /renovations 0 620 930 355 260 325 305 2,175 0 2,175 ABO802 Technology improvements 254 205 280 130 0 0 0 410 0 410 AA1101 Contingencies 0 225 225 225 225 225 225 1,125 0 1,125 9/13/2010 TOTAL 254 1,175 1,495 1,160 885 950 930 5,420 0 5,420 MAMCapital Budgets\2011 CIP inai 0OWment \6 Nonnmajor secfion 6Wroject summaneslADMINCIP Summary.xis 6 -4 City of Dublin Proposed 2011 — 2015 Capital Improvements Program Administration — Non -Major Projects AL1101 Land acquisition — The funding ($500,000 per year) that had been allocated in the past for general land acquisition has been used for the land that was acquired near the US 33/SR161 /Post Road interchange for economic development purposes. The property was acquired using various funding sources including an advance from the General Fund in the amount of $2.5 million. Funds included in 2010 are to reimburse the Water Fund. Funding to acquire the land needed for the location of a new water tower originally sited in this area were expended out of the Water Fund. Due to the location of the water tower construction changing to Darree Fields, the Water Fund will be reimbursed. The advance is being repaid over a five year period using the annual funding that had been programmed for land acquisition. Instead of allocating the $500,000 in the land acquisition project, the $500,000 has been programmed as a transfer in the Capital Improvements Tax Fund and has been reflected in the Debt Services Payments Due schedule. The funds are transferred to the Land Acquisition Fund and then advanced to the General Fund. The repayment of the advance will be finalized in 2011. No funding has been programmed for general land acquisition during the five year programming period. AU110I Utility service improvements — The City had been allocating $400,000 for utility service improvements. Funding programmed in 2011 provides for preliminary design and cost estimates for the burial of existing overhead utilities in Historic Dublin. These improvements are reflective of Council's goal of enhancing further development in Historic Dublin by providing more reliable utility service and a more aesthetically pleasing streetscape. This project also aligns favorably with the streetscape within the Bridge Street Corridor and reduces potential overhead conflicts with trees. An added benefit allows for future Dublink facilities to be extended throughout Historic Dublin. Completing the design will allow the City to phase the utility burial projects. The funding programmed in 2012 is based on the City's Economic Development Agreement with IGS Energy and the commitment to burying overhead utility lines near the IGS site. Service payments from the Thomas /Kohler TIF will be used to fund the project. Additionally, the $400,000 allocation for utility service improvements has been programmed for 2013 through 2015. Sites have not been prioritized for utilizing these allocations. Utility burial projects along Post Road (2008) and Frantz Road (2013) were, or will be, funded from TIF Funds. rim 9/13/2010 MAMCapital Budgets\201 I CIPTinal Document \6 Non -major section 6\Pmject descriptions\Administration- Non- Major.doc City of Dublin Proposed 2011- 2015 Capital Improvements Program Administration - Non -Major Proiects (continued) AB1101 Building maintenance /renovations - This request provides allocations for necessary maintenance to City buildings. The amount requested for 2011 is broken down as follows: Location Description Amount Chamber of Commerce HVAC unit replacements $10,000 Municipal Building HVAC unit replacements 15,000 Ceiling the replacement 10,000 Install ice guards 10,000 5800 Building Replace sealant on exterior stone 10,000 HVAC rooftop unit replacements 35,000 Replace Planning break room floor 5,000 Replace bathroom floors/countertops 5,000 Fleet Maintenance Paint building exterior 20,000 Add wash bay HVAC to Automated Logic 10,000 Paint interior of service bay 20,000 Justice Center Paint metal roof 95,000 Paint interior common area walls 5,000 Replace ceiling tiles 15,000 Replace carpet in Court Services 15,000 Replace carpet in radio room and locker rooms 15,000 Install ice guards 15,000 Avery Park Re -roof DSL/DYL concession stands 25,000 Heritage House Replace cedar roof and repair concrete floor 40,000 Karrer Barn Replace roof and stone foundation repairs 55,000 Red Trabue log cabin Exterior repairs 10,000 Dublin Recreation Center Photovoltaic(solar panels) installation (grant application to be submitted 245,000 HVAC unit for meeting room 2 15,000 Replace ceiling tiles in Tallas 10,000 Paint gymnasium 40,000 Replace second floor ceiling tiles 15,000 Paint exterior window and door frames 70,000 Replace service entrance and mechanical room doors and add automatic openers 10,000 Redesign and refurbish leisure pool slide 5,000 New trash/recycling trash/recycling containers 5,000 All locations HVAC and pump replacements 25,000 Small in -house renovations 15,000 New facility access security systems 30,000 New trash/recycling trash/recycling containers 5,000 Total $930,000 6 -6 9/13/2010 MAMCapital Budgets\201 I CIPTinal Document \6 Non -major section 6\Project descrlptions\Administmtion- Non - Major.doc City of Dublin Proposed 2011— 2015 Capital Improvements Program Administration — Non -Maior Proiects (continued) ABO802 Technology improvements — $130,000 has been programmed in 2010, 2011 and 2012 and will complete the project outlined in Ordinance 20 -08 approved by Council to partner with DHB to acquire assets, engineer, deploy, maintain and operate a Wi -Fi system for the balance of the City not currently covered (Phase II deployment). In 2010, High Speed Air, Inc. (HSA) acquired all of the Dublin assets of DHB and will complete the remaining obligations to the City. Also, in 2010, funding is programmed to deploy optical fibers into the DubLink conduit system in the COIC at an estimated cost of $75,000. To further support the City's Wi -Fi system, additional funding in the amount of $150,000 has been programmed in 2011 for the City's share to extend the fiber backbone into residential areas to reach remote City, School and Township properties. This project will be a partnership between the City, Dublin City Schools and Washington Township. The total cost of the project is estimated to be $300,000. AA1101 Contingencies - This is an allocation that is utilized for change orders related to projects that are carried over from one year to the next or minor projects that were unanticipated. $225,000 is allocated each year. 6 -7 9/13/2010 MAFA \Capital Budgets\201 I CIP\Final Document \6 Non -major section 6 \Project descriptions\Administmtion- Non -Major .doc CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 PROJECT PROJECT PRIOR TOTAL NO. DESCRIPTION I YEARS 1 1 TOTAL I BEYOND TO BE $000 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED SERVICE / NONMAJOR PROJECTS 9/13/2010 TOTAL I ol ol ol ol ol ol ol ol 0 0 MAFA1Capital 6udgetsU011CIRFinal DO menM Non- ajorsetion6 \ProjWsummaneslSERVICECIPsummary.xis 6-8 CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 PARKS & RECREATION / NONMAJOR PROJECTS AR1101 Park renovations/improvements PRIOR 395 300 450 450 450 450 2,100 0 TOTAL PROJECT DESCRIPTION YEARS 30 250 0 370 0 1 TOTAL BEYOND TO BE I NO. Avery Park $000) 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED PARKS & RECREATION / NONMAJOR PROJECTS AR1101 Park renovations/improvements 0 395 300 450 450 450 450 2,100 0 2,100 GR0108 Ballantrae Park 5,079 30 250 0 370 0 0 620 0 620 GR0502 Avery Park 1,404 445 0 0 0 0 0 0 0 0 GR0505 Skate Park redesign 0 0 0 40 90 0 0 130 0 130 GR0710 Kiwanis Boardwalk extension 0 0 85 0 0 0 0 85 0 85 GR0910 Belvedere Park 0 150 0 0 0 0 0 0 0 0 GR0911 Riverside Drive Park 0 50 505 0 0 0 0 505 275 780 GR0913 Post Preserve Park 62 135 0 0 0 0 0 0 0 0 GR0914 Dublin Sprinq Park 0 20 150 0 0 0 0 150 0 150 GR1010 Cam den LakesNded ewood Glen Park 0 0 0 150 0 0 0 150 0 150 GR1011 Llewellyn Farms South Park 0 0 0 0 0 0 0 0 210 210 GR1012 Emerald Parkway Bridge Park 0 0 45 435 0 0 0 480 0 480 GR1110 Rivenvalk Emerald Parkway to SR161 0 0 0 0 40 0 995 1,035 0 1,035 GR1111 Sycamore Ride Park 0 0 0 0 0 490 0 490 0 490 GR0008 Martin Commons Park 2 250 0 0 0 0 0 0 0 0 GR1112 Hutchins Property 0 0 1 275 0 0 0 0 275 0 275 GR1113 IGS Park (TIF) 0 0 0 280 0 0 0 280 0 280 GR1114 Holder Tract 0 0 80 0 0 0 0 80 1,000 1,080 GR1115 Dublin Community Pool North Renov 0 01 525 1 320 1 320 01 01 1,1651 0 1,165 9/13/2010 TOTAL 6,547 1 1,4751 2,215 1 1,675 1 1,270 1 940 1 1,445 1 7,5451 1,485 9,030 MAMG9pital Budgett=ICIP�nal D umenn6 Non- major section 6 \Project summanWPARKSCIP S mma,xls 6 -9 City of Dublin Proposed 2011— 2015 Capital Improvements Program Parks and Recreation - Non -Major Projects ARI001 Park renovation/improvements - This project is for renovation/ improvements to various existing parks. In 2011 rehabilitation is a focus of the CIP for Parks and Open Space. The following renovations and improvements are programmed: Location Description Amount Avery Park New ball field fencing around diamonds $75,000 North end concession area asphalt repairs 31,000 Coffinan Park Basketball court resurfacing 8,000 Poured in place safety surfacing to bring East playground up from ADA compliant to Universally Accessible 67,000 Donegal Cliffs Park New three rail fencing 5,000 Dublin Arts Council Drainage tile for parking lot 25,000 Dublin Cemetery Exterior mausoleum concrete repairs 5,000 Bridge Street wall repair 5,000 Earlington Barn Concrete floor addition 10,000 Llewelln Farms Park Basketball court resurfacing 5,000 M.L. "Red" Trabue Park Two rail fence replacement 7,000 Trinity Park New basketballs stem 7,000 Wellington Park New tennis court fencing 15,000 Tennis and basketball resurfacing 15,000 Shannon Glen Park Playground safety surfacing repairs 9,000 Park sips 11,000 Total 1 $300,000 GRO108 Ballantrae Park — Due to the popularity and increased utilization of the spray park, funds have been programmed in 2010 for the redesign of the filtration system with improvements programmed to be completed in 2011. The original filtration system was not designed to handle the volume of users that are currently utilizing the amenities of the park. The funding in 2013 will provide for a shelter house, permeable parking area, overlook plaza adjacent to the shelter, and a bike path running between the shelter area and the spray park. These park elements were identified in the original park master plan. Due to the extremely high utilization of the park this summer, modifications to the filtering system are being evaluated. 6 -10 9/13/2010 MAFMCapital Budgets\201 I CIP\Final Document \6 Non -major section 6\Project descriptions\Parks & Rec Non - Major.doc City of Dublin Proposed 2011 -2015 Capital Improvements Program Parks and Recreation — Non -Major Projects (continued) GR0502 Avery — South -end renovation complete. GRO505 Skate Park redesign — The funding provides for the redesign of part of the existing skate park. This is being requested based upon user input. GR0710 Kiwanis Boardwalk extension — Funding in 2011 will extend the existing path from Kiwanis Park to 161. The park trail is in need of renovation. The wetland nature of the park has overtaken some of the trail and the balance is in a state of disrepair. Additional funds have been programmed in 2011 to provide for these renovations. GR0910 Belvedere Park — Park development complete. GR0911 Riverside Drive Park — This is a high visibility wooded open space along Riverside Drive. The development plans include an extensive walking path system (similar to Indian Run Falls) designed to compliment the HS cross country teams, karst landscape boardwalk, new parking lot & associated landscaping, and a stately shelter (similar to the new Scioto Park). The price increase is a result of adding three needed footbridges and the new karst observation boardwalk. A public meeting to discuss the park was held in July. Access off of Hard Road is being evaluated. GR0913 Post Preserve Park — Park development complete. GRO914 Dublin Spring Park - Funding is programmed to rebuild the spring outlet, create an access point from 161 bridge deck, and control new spring using BMP stormwater controls. This project has been reviewed by the Architectural Review Board. GR1010 Campden Lakes/Wedgewood Glen Park — A large land mass ties together two adjacent neighborhoods. Development will include bike paths, landscaping, site furnishings, and a "rural character" fishing deck/pier. A playground and gazebos /shelters had been programmed before, but are not needed as part of the development. The playground equipment and gazebo /shelter previously programmed have been eliminated. 6 -11 9/13/2010 M:\FA \Capital Budgels\2011CIP\Final Document \6 Non -major section 6\Projmt c1mrlptions\Parks & Rec Non- Major.doc City of Dublin Proposed 2011 -2015 Capital Improvements Program Parks and Recreation — Non -Maior Proiects (continued) GR1011 Llewellyn Farms South Park — This park is being deferred to re- evaluate the necessity of a playground with poured -in -place safety surfacing, gazebo, landscaping, and site furnishings. This will provide the opportunity to look at industry trends that are under -served in the community. Once a thorough evaluation is completed, staff will revisit placement in the CIP. GR1012 Emerald Parkway Bridge Park — This project will provide access to the Scioto River at the Emerald Parkway Bridge. The project will include a permeable surface parking area, pathways and landscaping. This project is in line with Council's goal of providing access to the Scioto river corridor. There is potential for grant monies. Design is scheduled in 2011 and construction in 2012. The timing of this project has taken into consideration construction of the Emerald Parkway — Phase 8 project. GR1110 Riverwalk (Emerald Parkway to S.R. 161) = This project will provide a scenic pedestrian path along the east side of the Scioto River from the Emerald Bridge to S.R. 161 and connecting to the existing Kiwanis Riverway Park just south of S.R. 161. Additional land or easements will need to be acquired. Design is programmed in 2013 with funds programmed in 2015 for construction. Additional acquisitions need to be evaluated and the results of the Bridge Street corridor study could have an impact on the timing and /or development of this project. GRl 111 Sycamore Ridge Park — Funds will provide neighborhood park amenities including a large looping bikepath system, shelter house, playground, site furnishings, landscaping and potentially a second dog park. The Bridge Street corridor study could have an impact on the timing and /or development of this project. GR0008 Martin Commons Park - This is a small isolated neighborhood park in the S.E. part of the City that is an under served area with no other neighborhood parks. Plans include a shelter house, 2 -5 and 5 -12 year old age group play structures, a bikepatb and landscaping. Neighborhood meetings have been held and the project is scheduled for 2010. GR1112 Hutchins property and south — This is a recently acquired large tract of land east of the Scioto River and west of Wedgewood Hills. Construction in 2011 will add bike paths connecting it to the Wedgewood Hills subdivision. 6 -12 9/13/2010 MAWCapital Budgets\201 I CIP \Final Document \6 Non -major section 6\Project dmeriptionsWarks & Rm Non- Major.doc City of Dublin Proposed 2011 -2015 Capital Improvements Program Parks and Recreation - Non -Maior Proiects (continued) GR1113 IGS Park - This project will provide a park area adjacent to commercial areas. The land for the park will be provided by IGS Energy as discussed in the Economic Development Agreement with the City. 2012 includes a bikepath, bridge, landscaping, shelter house and associated site furnishings The bikepath and bridge will be funded from the Thomas/Kohler TIF and the shelterhouse will be funded from the Capital Improvements Tax Fund. GR1114 Holder tract - This park is an important archeological and historical site. Funding includes preservation/enhancement of Native American mounds, a path system, house preservation, parking lot and associated site amenities. The funding programmed in 2011 provides for master planning of the site. GR1115 Dublin Community Pool North renovations - Funds programmed in 2011 are to renovate the spray park and for bike rack expansion, 2012 includes renovation of the existing shade structures and 2013 includes funding for expansion of the concession stand, landscape renovations, fencing upgrades, updated sign packages and building painting. 6 -13 9/132010 MAFA \Capital Budgets\201 ICIP\Final Document \6 Non -major section ffrojmt descriptlons\Parks & Rm Non- Majondoc CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 PROJECT PROJECT PRIOR 20 0 25 0 0 0 25 0 TOTAL NO. DESCRIPTION YEARS 35 0 40 0 0 0 TOTAL BEYOND TO BE PP0805 OptiCom ($000) 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED POLICE I NONMAJOR PROJECTS PP0803 Replacement lasers 17 20 0 25 0 0 0 25 0 25 PP0804 Replacement radars 28 35 0 40 0 0 0 40 0 40 PP0805 OptiCom 15 0 25 25 0 0 0 50 0 50 PP1002 Covert surveillance & investigative equipment' 0 40 0 0 0 0 0 0 0 0 PP1003 Uninterrupted power supply replacement 0 35 0 0 0 0 0 0 0 0 PP1102 Dublin Emergency Warning System Upgrade 0 0 280 0 0 0 0 280 0 280 PP1103 Portable Sign Board System 0 0 0 0 35 0 0 35 0 35 PP1104 Digital Video Recorders for Motors 0 0 35 0 0 0 0 35 0 35 9/1312010 TOTAL 60 130 340 90 35 0 0 465 0 465 rUu Tunas M1FA1CapHal Budgets12011CIRFinal DO menN Nommajorsedon 6\Project summanesWOLCIP summary.xis 6 -14 City of Dublin Proposed 2011— 2015 Capital Improvements Program Police Non -Major Proiects PP0803 Replacement lasers — Funds are for the purchase of lasers to replace aging lasers over the course of three non- consecutive years. The lasers have an estimated life of 10 years. PP0804 Replacement radars — Fund will be used to purchase radars to replace aging radars currently used, over the course of three non - consecutive years. The radars have an estimated life of 10 years. PP0805 OptiCom — This allocation provides funds to purchase the needed vehicle based equipment to allow police cruisers to utilize the OptiCom traffic signal pre - emption system. Ten of the traffic signals within the City have the pre - emption system installed. Equipment is currently installed in four front line cruisers. Funding programmed in 2011 and 2012 will complete the installation in all front line cruisers. PP 1002 Covert surveillance & investigative equipment — Funds programmed in 2010 provides for the replacement of outdated covert surveillance equipment to enhance surveillance and investigative activities. Purchases will include digital recording devices, infrared scopes and GPS units. This project will be funded from the Law Enforcement Trust Fund. PP 1003 Uninterrupted power supply replacement — Funds have been allocated in 2010 to replace existing equipment that provides back -up power for the Communications Center to insure uninterrupted service to the community. The current equipment has exceeded its maximum life span/warranty and is in need of repair. PP 1102 Dublin emergency system warning upgrade — Programming provides to upgrade the Dublin Emergency Warning System. The upgrade is programmed in 2011 and will be completed in three phases outlined below: Phase 1 — Radio infrastructure - The Federal Communications Commission (FCC) issued a mandate that all radios operating in bands below 800MHz switch to narrowband capabilities by January 1, 2013. The current radios in the siren sites are wideband only and must be upgraded to meet the FCC mandate. The City has worked with Whelen and Motorola to provide a cost effective, easy to install option that will allow us to upgrade the system with no down time. Implementing this 6 -15 9/13/2010 M:TWCapital Budgets\201 I CIPTinal Document \6 Non -major section 6\Project descriptions \Police- Non - Major.doc Police Non -Major Projects (continued) solution will mean the only down time will be at each single site while it is changed over. The City will receive reimbursement in the amount of $16,500 from a Homeland Security grant secured by the Franklin County Emergency Management Agency. The estimated cost of this phase is $30,000. Phase 2 — Additional Siren sites - The siren system was last expanded in 2008 with the addition of a site at Coffman Park specifically to cover events held at that location. Prior to that, three Washington Township sirens were converted to the DEWS system and an additional siren was added at Glacier Ridge Elementary. Funds are programmed to add four additional sites to help improve coverage along the west edge of the city. Sites identified are 1) Municipal Pool - South; 2) Hyland Croy /Bishops Crossing; 3) Dublin Jerome High School and 4) Hyland Croy /McKitrick (Tartan West). This will add coverage in what are now marginally covered areas of the city. The estimated cost of this phase is $120,000. Phase 3 — Power components upgrade and conversion to solar - Many of the existing siren sites are using the original power components that were installed in 1990. Funding includes power upgrades to all sites including new poly- phasers to protect the sites from lightning damage. Funding also includes upgrading all sites to solar that will save on electric costs and increase the reliability of the power sources. Currently, the Glacier Ridge Elementary site has been running on solar since it was installed in 2008 and has been very successful. The estimated payback for converting the sirens to solar is four years. PP 1103 Portable sign board system — Funds programmed in 2013 are for a portable electronic message board to display a high visible electronic message(s) in a neighborhood in order to deliver important crime prevention, crime awareness, traffic safety, or special event information. PP 1104 Digital video recorders for motorcycles — Funds allocated in 2011 are provided for the installation of digital video systems on each of the four motorcycles. The City has been converting video recorders in police cruisers from VHS to digital. The manufacturer now has a reliable solution for motorcycle units. The digital video systems will allow motorcycle units video recording capabilities to capture incidents at the scene. 6 -16 9/13/2010 M: \rA \Capital 13udgets\201 ICIP\Pinal Document\6 Nan -major section 6 \Project descriptions\Pol ice - Non- Major.doc CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 PROJECT PROJECT I PRIOR 01 ol ol ol ol ol 400 400 TOTAL NO. DESCRIPTION YEARS ol ol ol ol ol 4001 TOTAL BEYOND TO BE ($000) 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED ES1110 9/13/2010 SANITARY SEWER SYSTEM \ NONMAJOR North Fork sewer - capacity improvement 0 ol 01 ol ol ol ol ol 400 400 TOTAL ol ol ol ol ol ol ol ol 4001 400 KWA \Capital Sudgets\2011CIP\Pinal DO menM Non- majorseebon 6Tmj"tsummaneslSNSEWCIP s mmary.xls 6 -17 City of Dublin Proposed 2011— 2015 Capital Improvements Program Sanitary Sewer System - Non -Major Projects ES 1110 North Fork sewer capacity improvement — This project has been identified as a future project. No funding has been programmed in the five -year period. MM 9/13/2010 M:\AA \Capital Budgets\2011CIP\Pinal Document \6 Non -major section 6\Pmject descriptions \Sanitary Sewer - Non- Major.doc CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 TRANSPORTATION /NONMAJOR PROJECTS AT1101 lAnnual street maintenance program PRIOR 2,725 3,000 3,150 3,300 3,465 3,640 16,555 0 OTAL REF. PROJECT I YEARS I 85 85 85 85 85 TOTAL 1 BEYOND TO BE 1 1\10. DESCRIPTION $000 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED TRANSPORTATION /NONMAJOR PROJECTS AT1101 lAnnual street maintenance program 0 2,725 3,000 3,150 3,300 3,465 3,640 16,555 0 16,555 AT1102 Annual roadside improvement program 0 85 85 85 85 85 85 425 0 425 AT1103 Annual bike path maintenance 0 40 350 350 100 100 100 1,000 0 1,000 AT1104 Annual bike path connections /additons* 0 0 45 230 20 0 0 295 0 295 AT1106 Annual sidewalk program 0 125 125 125 125 125 125 625 0 625 AT1107 Annual parking lot maintenance 0 355 100 100 100 100 100 500 0 500 AT1108 Annual pedestrian tunnel maintenance 0 100 250 200 50 50 50 600 0 600 AT1109 Annual infrastructure repairs(previously programmed in Service 0 75 75 75 75 75 75 375 0 375 AT1110 l Annual guardrail replacement 0 65 65 65 65 65 01 260 01 260 AT1111 Annual bike rack installation 0 0 25 25 25 25 25 125 01 125 AT1105 Traffic calming program 0 0 0 0 0 0 0 0 0 0 ET0403 Pedestrian tunnels 746 0 0 0 0 0 0 0 650 650 ET0504 Metro Center street lighting/pedestrian improvements (TIF) 184 750 0 0 0 0 0 0 0 0 ET0711 Riverside Drive overlay-SR 161 to north limits 0 265 0 0 0 0 0 0 0 0 ET1118 Riverside Drive /Hard Road turn lane 76 0 0 250 0 0 0 250 0 250 ET1201 Shannon Glen Park bikepath bridge 0 0 0 0 0 0 0 0 180 180 9/13/2010 TOTAL 1,006 4,585 4,120 4,655 3,945 4,090 4,200 21,010 830 21,840 Large connections(Brand, Glick, Dublin Rd.) moved t0 major. KWXCapital Mgetst20110IP nalD menM Non- majorsection 6\Polectsumma6es%TR NSCIPsummary.xls 6-19 City Of Dublin Proposed 2011 - 2015 Capital Improvements Program Transportation — Non -Maior Proiects ATI 101 Annual street maintenance program - This is an annual allocation for repairing the City's roadways. Based on the condition assessment of the City's roadways completed by the Division of Engineering, the level of funding programmed should be sufficient to maintain a high percentage of our roadways rated as "good" or better. The 2007 condition assessment determined that 90.1% of the City's road -miles were considered to be in good condition or better. This percentage was up from 86.6% established in the 2004 assessment. In 2010, the City contracted with Stantec Consulting Services, Inc. to provide a comprehensive map based pavement condition inventory to aid in planning future maintenance. The pavement analysis will be completed in the fall. The allocation for 2011 reflects a 10% increase over 2010 with the remaining years reflecting an annual increase of approximately 5 %; however, the results of the pavement analysis will allow the City to more accurately identify pavement conditions and program repairs accordingly in the five year CIP. AT1102 Annual roadside improvement program - This is an annual allocation to improve conditions along City roadways. This program is completed in conjunction with the Annual Street Maintenance Program. $85,000 has been allocated for each year of the CIP. As with other annual programs, the intent is to establish a list of the areas needing improvement and to identify years in which we anticipate the work being completed. AT1103 Annual bikepath maintenance - This is an annual allocation to maintain the City's bikeways. This project is completed in conjunction with the Annual Street Maintenance Program. Engineering and Parks and Open Space have identified several bikepaths that are in need of maintenance in the next two years. As a result, $350,000 has been programmed in 2010 and 2011 to repair the identified bikepaths. Additionally, an annual allocation of $100,000 has been programmed in 2013, 2014 and 2015 to ensure the bikepaths are properly maintained. Based on the age of the bikepath system, additional efforts evaluating the pavement condition will be made in the future. AT1104 Annual bikepath connections /additions - These funds are utilized in areas where roadway projects or developer contributions are not likely or in locations where pedestrian safety is an issue. 6 -20 9/13/2010 MAFA \Capital Budgets\201 I CIPTinal Document \6 Non -major section 6\Project descriptions \Tmnsponation - Non- Major.doe City Of Dublin Proposed 2010 — 2014 Capital Improvements Program Transportation — Non - Maior Proiects (continued) AT1104 Annual bikepath connections /additions (continued) As a result of City Council's 2007 goal- setting session, the funding for bikepath connections increased from the previous annual allocation of $150,000 to fund the design, construction and landscaping of the Brand Road, Dublin Road and Glick Road bikepaths. These projects, based on the estimated costs, have been included separately in Transportation — Major and details will be included in their individual project descriptions. Funding has been programmed in 2011, 2012 and 2013 for the design, construction and landscaping for the completion of the Martin Road and Stoneridge Lane bikepaths. These connections, along with the bikepath included as part of the Martin Road Park development, will complete the connectivity from Riverside Drive to Dublin Center Drive. AT1106 Annual sidewalk program - This is an annual allocation to replace deficient sidewalks throughout the City. A condition assessment was completed by the Division of Engineering and the replacements will be made based on the assessment. A component of the program is the replacement of the street trees where necessary. Paying for the cost of sidewalk repairs is unique to the City of Dublin. The more common practice is for the property owner to bear the cost of sidewalk repairs. ATl 107 Annual parking lot maintenance — The project will be administered by the Division of Engineering and will likely be completed in conjunction with the Annual Street Maintenance Program. The funding programmed in 2010 is for the Dublin Community Recreation Center. $100,000 has been allocated for anticipated parking lot maintenance for the remaining four years. We will complete an evaluation of the various parking areas and begin a more formal process of programming the improvements in the future. Staff is currently evaluating the potential to use Stantec to complete a pavement analysis on a number of the City parking lots. 6 -21 9/13/2010 M:TA \Capita] Budgels\201 I CIPTinal Document \6 Non -major section 6\Projw descriptions \Tmnspoeation - Non- Majondoe City Of Dublin Proposed 2010- 2014 Capital Improvements Program Transportation — Non -Major Projects (continued) ATI 108 Annual pedestrian tunnel maintenance — To better track pedestrian tunnel maintenance, a separate project was added to the CIP. A preliminary assessment of the pedestrian tunnels has been completed. Several tunnels are in need of repair. $100,000 has been programmed in 2010 to complete the most critical repairs for the tunnels under Muirfield Drive. Engineering staff is currently in the process of completing a condition analysis of the tunnels. Necessary improvements will be prioritized and cost estimates completed. The funds programmed are allocations. ATI 109 Annual infrastructure repairs — Previously funded, on an as needed basis, in the Annual Street Maintenance Program, this funding will allow for various repairs in the right -of -way. Examples include bridge railings, stone walls and other right -of -way repairs. This project was moved from Service. ATI 110 Annual guardrail replacement — This funding will allow for the wood guardrails within Dublin to be replaced in compliance with current standards. The replacement should be completed in 2014. ATI l l l Annual bike rack installation — The City, as well as the Bicycle Advisory Task Force (BATF), has identified the need for several additional bike racks as a result of the increased use of bicycles in the City. Funding is provided for the installation of additional bike racks throughout the City. Racks will consist of a mix of standard, custom and functional sculpture bike racks based on location and need. ATI 105 Traffic calming prowam — No allocation has been programmed for the next five years. ET0403 Pedestrian tunnels - A pedestrian tunnel study was adopted by City Council on December 15, 2003. This study included a priority listing of tunnel locations to be programmed. A tunnel at Brand Road /Bristol Parkway was completed in 2005/2006 and Dublin Road /River Forest Road was completed in 2006. Funding has not been programmed in the five year period. 6 -22 9/13/2010 M AFA \Capital Budgets\201 I CIP\Final Document \6 Non -major section 6\Project descrlptionsUmnsponation - Non- Major.doc City Of Dublin Proposed 2010- 2014 Capital Improvements Program Transportation — Non -Major Projects (continued) ET0504 Metro Center street li hting/pedestrian improvements - This project will provide for the removal of obsolete and ineffective street lights and install new lights that will be owned and maintained by the City. The project will include the installation of sidewalks or bikepaths to improve pedestrian movement in the area. The City also plans to resurface the roadway through the Metro Center and plans are to complete the resurfacing at the same time as the bikepath and street lights. This is an important commercial center for the City and this project will help keep the area competitive. The construction for this project will be completed in 2010. This project will be funded out of the Pizzuti TIF. ET0711 Riverside Drive (State Route 257) overlay — State Route 161 to north corporation limits — This project will be coordinated by the Ohio Department of Transportation (ODOT) and the programming of this project by ODOT is based on their Pavement Condition Rating (PCR). The City's share of the project is 20% of the cost to construct with the remaining 80% funded by ODOT. ODOT had originally programmed the project for fiscal year 2011; however, funds were available in 2010. As a result, the project has been accelerated and is scheduled for completion in 2010. Funded out of the State Highway Fund, the City has submitted its share of the project to ODOT for construction in the amount of approximately $184,000. ET1118 Riverside Drive (State Route 257)/Hard Road turn lane — To improve traffic operations and safety at this intersection, programming is provided to install a northbound right turn lane from Riverside Drive to Hard Road. The project will include new pavement, grading, shoulder work and drainage. Design has been completed and construction is scheduled for completion in 2012. This project will be funded out of the State Highway Fund. ET1201 Shannon Glen Park Bikepath Bridge — This project will provide a bikepath bridge over a tributary of the North Fork of Indian Run. No funding is included in this five year period. 6 -23 9/13/2010 M:\FA \Capital Budgets\2011CIP\Final Document \6 Non -major section 6\Project dmiiptionffmnsportation - Non- Majondoe CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 PROJECT PROJECT PRIOR 0 0 0 0 0 0 0 0 TOTAL NO. DESCRIPTION I YEARS I 1 1 1 0 470 1 TOTAL BEYOND TO BE AW0604 Booster station upgrades ($000) 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDC,ETED WATER DISTRIBUTION SYSTEM \ NONMAJOR PROJECTS AW1102 Water line oversizing 0 0 0 0 0 0 0 0 0 0 AW1001 Water line replacement 0 0 0 500 0 470 0 970 0 970 AW0604 Booster station upgrades 0 195 580 85 0 0 0 665 50 715 EW0102 Water tower maintenance 472 495 500 0 0 305 305 1,110 680 1,790 EW1102 Post Road water tower decommissioning 0 0 85 0 0 0 0 85 0 85 EW1501 12" waterline - Ballantrae Section 9 to Cosgray 0 0 0 0 0 0 0 0 170 170 9/13/2010 ITOTAL 472 690 1,165 585 0 775 305 2,830 900 3,730 KTA \Capital Buogets\2011CIP \Final Document\6 Non -major section 6 \Project summaries\ 6-24 City of Dublin Proposed 2011 - 2015 Capital Improvements Program Water Distribution System - Non -Maior Proiects AW1102 Water line oversizine - An annual allocation of $75,000 had been programmed in recent years. We are not currently aware of any potential oversizing projects and therefore have not programmed any funding during the next five years. AW 1001 Water line replacement - The City's water system is relatively new and we have not needed to replace existing lines. There are areas in the City that have older 2" and 3" main lines that have been identified for replacement with a 6" main line. The smaller lines tend to experience more problems with breaks. Engineering staff will prepare a comprehensive list of areas and complete an analysis of the lines to determine when replacement should occur. There is funding allocated in 2012 and 2014 to begin replacing the 2" and 3" lines. Once a comprehensive list is prepared and the analysis of the condition of the lines is completed, a more detailed plan will be prepared. It is possible that significant replacements could be grouped and scheduled to be completed in the same year allowing long -term debt to be issued instead of programming annual allocations. AW0604 Booster station up rg ades - This project will ensure that water supply to the storage tanks is adequate. Based on system evaluations completed by ms consultants, the City of Columbus and Dublin staff in 2007, funds have been programmed for pump replacements at the City's booster stations. Based on the evaluation recently completed by ms consultants, the following upgrades have been programmed: 2010 - Replace the three existing pumps at the Tartan booster station. 2011 - Repair and /or replace the two existing 100 horse power pumps and replace the 5 horse power pump with an additional 100 horse power pump at the Post Road booster station. 2012 - Various maintenance and repairs at the Brand Road booster station. No repairs have been recommended at the Rings Road booster station. Staff will be working on preparing a comprehensive schedule for future maintenance and repairs associated with the booster stations. 6 -25 9/132010 M9FA \Capital Budgets\2011CIP\Final Document \6 Non -major section 6 \Project descriptions \Water- Non- Major.doc City of Dublin Proposed 2010 - 2014 Capital Improvements Program (continued) EW0102 Water tower maintenance — This project provides for the interior and exterior painting and other maintenance needs such as electrical equipment replacement associated with the City's three (3) existing water towers. The funding programmed in 2010 is for the external painting of the Avery Road tower. The Post Road tower had been scheduled for painting in 2008, the painting was deferred because the future need of the tower was uncertain. Funds have been programmed under a separate project in 2011 to dismantle and remove the Post Road tower. The funding programmed in 2011 is for the exterior painting of the Blazer tower, funds in 2014 is for wet interior painting of the Avery tower, and 2015 includes funds for wet interior painting of the Blazer tower. EW 1102 Post Road water tower decommissioning — Funds have been programmed in 2011 to dismantle and remove the Post Road water tower. This tower will no longer be necessary because of the construction of the Darree Fields water tower. EW1501 12" waterline — Ballantrae Section 9 to Cos rayRoad — This project is for a 12" waterline connecting Ballantrae Section 9 to Cosgray Road and has been identified to improve existing water pressures in the area. The City has initiated discussions with the developer to enter into an agreement to be reimbursed for the cost of the extension upon development of Ballantrae Section 9. 6 -26 9/13/2010 M:\FA \Capital Budgets\201 I CIP\Final Document \6 Non -major section 6\Pmject descriptions \Water- Non- Majocdoc CITY OF DUBLIN CAPITAL IMPROVEMENT PROJECTS 2011 -2015 PROJECT PROJECT PRIOR 300 300 300 300 300 300 1,500 0 TOTAL NO. DESCRIPTION YEARS TOTAL BEYOND TO BE ($000) 2010 2011 2012 2013 2014 2015 11 -15 2015 BUDGETED STORMWATER SYSTEM INONMAJOR PROJECTS AF1101 Annual stormwater maintenance 0 300 300 300 300 300 300 1,500 0 1,500 0 0 0 0 9/13/2010 TOTAL 0 300 300 300 3001 300 300 1,500 ol 1,500 M.XFA\Ca0Ilal BudgeNN2011CIMFiml DO menM Nonmjorsecfion 6Tmje summades STRMCIP summary.xls 6-27 City of Dublin Proposed 2011 - 2015 Capital Improvements Program Stormwater System - Non -Major Projects AF1101 Annual stormwater maintenance - This project provides funding for maintenance of the City's stormwater system as identified in the Stormwater Master Plan. This is an annual maintenance program that was initiated in 2000. The funds are utilized to maintain and repair existing stormwater lines, curb inlets, catch basins, ditches, man-made channels and other structures that discharge stormwater runoff. This is an important component of the City's efforts to meet NPDES Phase II regulations. M . 9/13/2010 M:TA \Capital Budgets\2011 CIPTinal Document %Non -major section 6\Pmject descriptions\Stonnwtr System- Non- Major.doc