Loading...
Resolution 40-22 To: Members of Dublin City Council From: Dana L. McDaniel, City Manager Date: August 2, 2022 Initiated By: Paul A. Hammersmith, PE, Director of Engineering/City Engineer Brian D. Gable, PE, Deputy Director of Engineering - Design & Construction Kenneth B. Richardson, PE, PS, Senior Civil Engineer Re: Resolution 40-22 – Accepting the Lowest and Best Bid for the Shawan Falls Drive Bridge Replacement Project (21-011-CIP) Summary On July 21, 2022 seven (7) bids were received and publicly opened for the Shawan Falls Drive Bridge Replacement Project (the “Project”). The scope for this work was developed as part of the Annual Vehicular Bridge Maintenance for 2022. The Project will replace the existing structurally deficient two- lane bridge with a new widened three-lane bridge including a five-foot wide sidewalk (see the included location map). In addition to the bridge replacement, the Project will replace the existing span-wire traffic signal at West Bridge Street and Shawan Falls Drive/Corbin’s Mill Drive with a new mast arm traffic signal. A five-foot wide sidewalk will also be constructed on the west side of Shawan Falls Drive beginning at Bridge Street and continuing to the Indian Run Falls Park and United States Post Office frontage. For Council’s reference, a copy of the construction drawings for the Project have been provided electronically or a print version can be provided to Council upon request. The Engineer’s estimate for this project is $1,800,000. The budgeted funds in the 2022-2026 Capital Improvements Program (CIP) for the Shawan Falls Drive Bridge Replacement are $1,625,000 in account AT22C - Annual Vehicular Bridge Maintenance. Axis Civil Construction LLC submitted the lowest and best bid of $2,092,889.58. Staff has reviewed all bids and a summary is listed below. Bidder Bid as Read Bid as Read Corrected Bid Over (+) or Under (-) Engineer’s Estimate Axis Civil Construction LLC $2,092,889.58 +16.3% n/a The Ruhlin Company $2,162,575.77 +20.1% n/a Double Z Construction Company $2,175,052.59 +20.8% n/a The Righter Co., Inc. $2,353,714.61 +30.8% n/a Complete General Construction Company $2,398,990.04 +33.3% n/a George J. Igel & Co., Inc. $2,403,851.79 +33.6% n/a Sunesis Construction Co. $2,503,315.61 +39.1% n/a Office of the City Manager 5555 Perimeter Drive • Dublin, OH 43017-1090 Phone: 614.410.4400 • Fax: 614.410.4490 Memo Resolution 40-22 – Accepting the Lowest and Best Bid for the Shawan Falls Drive Bridge Replacement Project (21-011-CIP) August 2, 2022 Page 2 of 3 The seven bids received were higher than the Engineer’s estimate. Staff has determined this is due to multiple factors: overall high inflation, increased trucking and fuel costs, material costs increases, and ductile iron pipe shortages. Engineering has consulted with Finance, and staff anticipates being able to cover the additional Program cost using funds previously appropriated as part of the 2022-2026 CIP. These funds are available from one or more projects appropriated as part of the 2022-2026 CIP that will not proceed in 2022 and will be included in 2023-2027 CIP. As detailed in the June 14, 2022 City Manager update memo, “Ductile Iron Water System Components Supply”, there is presently an extended delivery time for ductile iron components. This has also caused the material cost of these same components to be inflated beyond the cost used to determine the Engineer’s estimate. These cost increases are reflected in the submitted bids for this project. It is also expected the lead-time to secure the ductile iron components for this project will be nine to twelve months from the time of order. The waterline relocation portion of this project must occur early in the project and is critical to the widening of the structure to the west. Due to the ductile iron waterline not being available for several months, the completion date for this project is being extended from May 2023 to October 20, 2023. Presently, the construction of this Project is not expected to commence prior to April 1, 2023. Since the bridge was previously determined through annual inspections to be structurally deficient, temporary shoring was placed beneath the bridge in 2018 to provide additional support and will remain in place until the bridge is replaced. Furthermore, the bridge is restricted to 85 percent of legal loads as a result of its present condition. With these measures in place, staff is confident the bridge will remain safe until it is replaced. Shawan Falls Drive will remain open to traffic in both directions for the duration of the construction through multiple phases of work. The completion date for the project is October 20, 2023. The typical and customary communication methods will be used to convey construction information with the commercial properties adjacent to this project and the traveling public throughout the duration of the Project. Recommendation Staff has thoroughly reviewed the bid submitted by Axis Civil Construction LLC. Axis Civil Construction LLC has not performed previous work for the City of Dublin. They are Ohio Department of Transportation (ODOT) pre-qualified for roadway and bridge construction and have performed multiple roadway, drainage, and structure construction projects in the last five years for ODOT. The Contractor references contacted by staff provided verification that the quality of work has been favorable and they have more than adequate resources to perform the work for this Project. Although the lowest and best bid for this Project is over the Engineer’s Estimate for the reasons previously mentioned, staff recommends Council approval of Resolution 40-22 accepting as lowest and best the bid of Axis Civil Construction LLC in the amount of $2,092,889.58 and authorizing the City Manager to enter into a contract with Axis Civil Construction LLC for this Project. There has been no indication from suppliers and other industry professionals that construction prices will significantly reduce in the near term. Additionally, given the present condition of the existing bridge, this Project is necessary for the safety of those using Shawan Falls Drive and crossing the bridge. Resolution 40-22 – Accepting the Lowest and Best Bid for the Shawan Falls Drive Bridge Replacement Project (21-011-CIP) August 2, 2022 Page 3 of 3 Location Map 5-18-2022 5-18-2022 NJL 66 4/7/22 58074 P:\PR58074\FRA\000000\Design\Roadway\Sheets\GN001.dgn Sheet 5/6/2022 5:10:16 PM jkelleyJMK NJL MSL 2 REPLACEMENT BRIDGE SHAWAN FALLS GENERAL NOTES NONE 2BRIDGE REPLACEMENTSHAWAN FALLS DRIVEGENERAL CONNECTION BETWEEN EXISTING AND PROPOSED GUARDRAIL AND OTHER FOREIGN MATERIAL OF 1/2" OR GREATER IN ANY DIMENSION. ALL TOPSOIL MATERIALS AND FINAL AREA OF SUBGRADE PREPARATION SHALL BE FREE FROM ROCK TOPSOIL REMOVAL IS INCLUDED IN ITEM 203 - EXCAVATION. REMOVAL OF EXCESS TOPSOIL AS REQUIRED TO OBTAIN A SUITABLE SUBGRADE. PAYMENT FOR ACCORDANCE WITH THE SPECIFICATIONS. NO EXTRA COMPENSATION WILL BE PAID FOR THE TOPSOIL SHALL BE REMOVED AND WASTED OR UTILIZED IN NON-LOAD BEARING FILLS IN FOR SEPARATELY, BUT SHALL BE INCLUDED IN THE COST OF THE VARIOUS CONTRACT ITEMS. IS PLACED. THE COST OF EXCAVATION AND DISPOSAL OF SURPLUS MATERIALS WILL NOT BE PAID CITY WILL NOT MAKE ADDITIONS OR DEDUCTIONS TO THE EARTHWORK QUANTITIES WHERE TOPSOIL ALLOW PLACEMENT OF 4 INCHES OF TOPSOIL UNLESS OTHERWISE DIRECTED BY THE ENGINEER. THE PLACE 4 INCHES OF TOPSOIL. IN FILL AREAS, THE EMBANKMENT HEIGHT SHALL BE ADJUSTED TO PLACING TOPSOIL IN CUT AREAS, THE EARTH SHALL BE EXCAVATED TO A DEPTH SUFFICIENT TO A MINIMUM 4 INCHES OF TOPSOIL SHALL BE PLACED IN ALL AREAS TO BE SEEDED. PRIOR TO PAINTED GUARDRAIL AND ANCHOR ASSEMBLIES ITEM 606-ANCHOR ASSEMBLY, MGS TYPE E THE ENGINEER. USE OF CALCIUM CHLORIDE WILL NOT BE PERMITTED. DUST CONTROL OPERATIONS SHALL BE PERFORMED BY THE CONTRACTOR AT THE DIRECTION OF CONTROL, WHICH MAY CAUSE TRACKING, IS NOT PERMITTED. UNNECESSARY NOISE, DUST, AND ODORS. THE USE OF OIL OR OTHER MATERIAL FOR DUST THE CONTRACTOR'S CONSTRUCTION ACTIVITIES SHALL BE CONDUCTED SO AS TO ELIMINATE ALL AUTHORIZATION FOR EXTENDED HOURS FROM THE CITY ENGINEER. A.M. TO 7:00 P.M., MONDAY THROUGH SATURDAY, UNLESS THE CONTRACTOR RECEIVES WRITTEN WITHIN THE CITY OF DUBLIN, CONSTRUCTION ACTIVITY IS RESTRICTED TO THE HOURS OF 7:00 FOR THE REASONABLE AND EFFICIENT PERFORMANCE OF THAT EQUIPMENT. OR IN SUCH A MANNER THAT THE NOISE CREATED SUBSTANTIALLY EXCEEDS WHAT IS CUSTOMARY CONSTRUCTION NOISE. IN ADDITION, POWER EQUIPMENT SHALL NOT BE OPERATED AT ANY TIME BE USED IN COMPLIANCE WITH APPLICABLE ORDINANCES AND REGULATIONS PERTAINING TO TO MINIMIZE NOISE-RELATED IMPACTS, ANY POWER-OPERATED CONSTRUCTION EQUIPMENT SHALL LAND USE ADJACENT TO THIS PROJECT MAY BE AFFECTED BY CONSTRUCTION NOISE. IN ORDER NOTIFICATION BY THE CITY. TIME FOR ALL STREETS INVOLVED ON THIS CONTRACT IS 1 HOUR FROM THE TIME OF OF A DEDUCTION FROM THE CONTRACTOR'S NEXT PAYMENT UNDER THE CONTRACT. REASONABLE THE CITY SHALL BE REIMBURSED BY THE CONTRACTOR IN THE AMOUNT PROVIDED HEREIN BY WAY FAILS WITHIN A REASONABLE TIME TO PERFORM OR CAUSE THE PERFORMANCE OF SUCH WORK, CONTRACTOR OF THE NECESSITY TO PERFORM SUCH WORK. IF THE CONTRACTOR REFUSES OR REQUIRED TO NOTIFY OR ATTEMPT TO NOTIFY THE DESIGNATED REPRESENTATIVE OF THE MATERIALS, AND EQUIPMENT NECESSARY TO PERFORM SUCH WORK. THE CITY SHALL BE SHALL REIMBURSE THE CITY AT THE RATE OF 2.5 TIMES THE ACTUAL COST OF LABOR, CONTRACTOR TO PERFORM SUCH WORK AS REQUIRED BY THE CONTRACT, THE CONTRACTOR OTHER WARNING OR PROTECTIVE DEVICES) BECAUSE OF FAILURE OR REFUSAL OF THE IMMEDIATE NATURE (SUCH AS THE PLACEMENT OF BARRICADES OR REPLACEMENT OF SIGNS AND IN THE EVENT THAT IT BECOMES NECESSARY FOR THE CITY TO PERFORM WORK OF AN 623 - CONSTRUCTION LAYOUT STAKES. PAYMENT FOR CONSTRUCTION LAYOUT SHALL BE MADE AT THE LUMP SUM PRICE BID FOR ITEM GRADES, ELEVATIONS, AND DIMENSIONS CALLED FOR ON THE DRAWINGS AND TYPICAL SECTIONS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE FINISHED WORK CONFORMING TO THE LINES, SURVEYOR AS APPROVED BY THE CITY ENGINEER AT THE CONTRACTOR'S EXPENSE. RESTORATIONS. RESETTINC OF MARKERS SHALL BE PERFORMED BY AN OHIO PROFESSIONAL WILLFUL OR CARELESS DESTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR POINTS, STAKES, AND OTHER SURVEY REFERENCE MONUMENTS OR MARKERS. IN CASES OF THE CONTRACTOR SHALL CAREFULLY PRESERVE BENCH MARKS, PROPERTY CORNERS, REFERENCE AUTHORIZED BY THE CITY ENGINEER. DEFINED AS PERMANENT AND/OR TEMPORARY CONSTRUCTION EASEMENTS, UNLESS OTHERWISE THE CONTRACTOR SHALL RESTRICT CONSTRUCTION ACTIVITY TO PUBLIC RICHT OF WAY, AREAS LUMP SUM PRICE BID FOR ITEM SPECIAL - PROOF SURVEY. WORK. THE COST OF THE PROOF SURVEY, INCLUDINC PDF REVISIONS, WILL BE PAID AT THE ORIGINAL PDF IN RED INK, TO THE SATISFACTION OF THE CITY, SHOWING ALL CHANGES IN THE BY AN OHIO PROFESSIONAL ENGINEER/SURVEYOR. THE CONTRACTOR SHALL REVISE THE AS PART OF THIS PROJECT. THE PROOF SURVEY SHALL BE PREPARED, SIGNED, AND SUBMITTED DIMENSIONS, SLOPES AND ALIGNMENTS OF ALL PUBLIC UTILITIES (STORM, WATER) COMPLETED CONTRACTOR TO THE DIVISION OF ENCINEERINC THAT DOCUMENTS "AS BUILT" ELEVATIONS, FOLLOWING COMPLETION OF CONSTRUCTION, A PROOF SURVEY SHALL BE PROVIDED BY THE BY THE CITY ENGINEER, CITY OF DUBLIN. ANY MODIFICATION TO THE WORK SHOWN ON DRAWINCS MUST HAVE PRIOR WRITTEN APPROVAL WAY PERMIT IS OBTAINED. WATERWAY BELOW THE ORDINARY HICH WATER MARK DURING CONSTRUCTION UNTIL THE WATER PERMITS. THE CONTRACTOR IS NOT AUTHORIZED TO PLACE ANY FILL OR WORK WITHIN ANY THE CITY IS RESPONSIBLE FOR OBTAINING AND PROVIDING TO THE CONTRACTOR ALL NECESSARY WORKINC DAYS PRIOR TO BEGINNING CONSTRUCTION. THE CONTRACTOR SHALL NOTIFY THE CITY OF DUBLIN DIVISION OF ENCINEERING AT LEAST 14 PERFORM WORK ACCORDING TO THE CONTRACT DOCUMENTS. RESPONSIBLE FOR SAFETY ON THE WORK SITE, OR FOR FAILURE BY THE CONTRACTOR TO SEQUENCES OF CONSTRUCTION THAT ARE NOT SPECIFIED HEREIN. THE CITY ENCINEER IS NOT THE CITY ENGINEER IS NOT RESPONSIBLE FOR MEANS, METHODS, PROCEDURES, TECHNIQUES, OR THE UNIT PRICE BID FOR THE VARIOUS RELATED ITEMS. IS PROVIDED SHALL BE PERFORMED BY THE CONTRACTOR WITH THE COST TO BE INCLUDED IN ALL ITEMS OF WORK CALLED FOR ON THE PLANS FOR WHICH NO SPECIFIC METHOD OF PAYMENT CODE CONCERNING CONSTRUCTION CONTRACTS. ODOT CONSTRUCTION AND MATERIAL SPECIFICATIONS, AND CHAPTER 5525 OF THE OHIO REVISED WITH THE OHIO DEPARTMENT OF TRANSPORTATION IN ACCORDANCE WITH SECTION 102 OF THE THE CONTRACTOR INTENDING TO SUBMIT A BID FOR THIS PROJECT SHALL BE PREQUALIFIED LISTED FOR THESE PORTIONS REFER TO ODOT CMS ITEM NUMBERS UNLESS OTHERWISE NOTED. SPECIFICATIONS (ODOT CMS), 2019 EDITION, AND ANY SUPPLEMENTS THERETO. ITEM NUMBERS GOVERNED BY THE OHIO DEPARTMENT OF ENGINEERING CONSTRUCTION AND MATERIAL TRAFFIC, SIGNAL, AND MAINTENANCE OF TRAFFIC PORTIONS OF THIS PROJECT WILL BE NUMBERS LISTED REFER TO C.O.C. CMS ITEM NUMBERS UNLESS OTHERWISE NOTED. THE DIVISION 100 SHALL GOVERN ALL CONSTRUCTION ITEMS UNLESS OTHERWISE NOTED. ITEM EDITION, AND ANY SUPPLEMENTS THERETO, ALONG WITH CITY OF DUBLIN CENERAL CONDITIONS, THE CITY OF COLUMBUS CONSTRUCTION AND MATERIAL SPECIFICATIONS (C.O.C. CMS), 2018 GUARDRAIL IS ALSO INCLUDED IN THE UNIT BID PRICE. AND EXCAVATION NOT SEPARATELY SPECIFIED, AS REQUIRED BY THE MANUFACTURER. PAINTING THE INCLUDING ALL RELATED TRANSITIONS, REFLECTIVE SHEETING, HARDWARE, GRADING, EMBANKMENT MATERIALS NECESSARY TO CONSTRUCT A COMPLETE AND FUNCTIONAL ANCHOR ASSEMBLY SYSTEM, ASSEMBLY, MGS TYPE E, A.P.P., EACH AND SHALL INCLUDE ALL LABOR, TOOLS, EQUIPMENT AND PAYMENT FOR THE ABOVE WORK SHALL BE MADE AT THE UNIT BID PRICE FOR ITEM 606 - ANCHOR SHEET. THIS ANCHOR ASSEMBLE IS LOCATED ALONG SHAWAN FALLS AT STA. 102+20 AS SHOWN ON THE PLAN LOCATED ON THIS PAGE. BE PAINTED PER THE GUIDELINES IN THE NOTE "PAINTED GUARDRAIL AND ANCHOR ASSEMBLIES" THIS ITEM SHALL BE THE SAME AS ITEM 606 - ANCHOR ASSEMBLY, MGS TYPE E EXCEPT IT SHALL ITEM 606-ANCHOR ASSEMBLY, MGS TYPE E, A.P.P. ITEMS. USED. PAYMENT SHALL BE INCLUDED IN THE CONTRACT PRICE FOR THE RESPECTIVE GUARDRAIL A W-BEAM RAIL SPLICE AS SHOWN IN AASHTO M 180, EXCEPT THE BEAM WASHERS ARE NOT TO BE EXISTING GUARDRAIL SHALL BE CUT, DRILLED, OR PUNCHED. THE CONNECTION SHALL BE MADE USING WHEN IT IS NECESSARY TO SPLICE PROPOSED GUARDRAIL TO EXISTING GUARDRAIL, ONLY THE AND EXCAVATION NOT SEPARATELY SPECIFIED, AS REQUIRED BY THE MANUFACTURER. INCLUDING ALL RELATED TRANSITIONS, REFLECTIVE SHEETING, HARDWARE, GRADING, EMBANKMENT MATERIALS NECESSARY TO CONSTRUCT A COMPLETE AND FUNCTIONAL ANCHOR ASSEMBLY SYSTEM, ASSEMBLY, MGS TYPE E, EACH, AND SHALL INCLUDE ALL LABOR, TOOLS, EQUIPMENT AND PAYMENT FOR THE ABOVE WORK SHALL BE MADE AT THE UNIT PRICE BID FOR ITEM 606, ANCHOR STRUT DOES PROJECT MORE THAN 4 INCHES ABOVE THE GROUND LINE. ON-SITE GRADING IS REQUIRED IF THE TOP OF THE FOUNDATION TUBES OR TOP OF THE GROUND GUARDRAIL HEIGHT OF 31 INCHES FROM THE EDGE OF THE SHOULDER. SHOULD BE AN APPROPRIATE DEPTH BELOW THE LEVEL LINE IN ORDER TO MAINTAIN THE FINISHED SHOULD BE LESS THAN 4 INCHES ABOVE THE GROUND. THE PLACEMENT OF THE FOUNDATION TUBES GRADING AROUND THE FOUNDATION TUBES AND GROUND STRUT. THE TOP OF ANY FOUNDATION TUBE REFER TO THE MANUFACTURER'S INSTRUCTIONS REGARDING THE INSTALLATION OF, AND THE SHEETING, PER CMS 730.19. THE FACE OF THE TYPE E IMPACT HEAD SHALL BE COVERED WITH A SHEET OF TYPE G REFLECTIVE THE PLANS, IN ACCORDANCE WITH THE MANUFACTURER'S SPECIFICATIONS. APPROVED GUARDRAIL END TREATMENTS. INSTALLATION SHALL BE AT THE LOCATIONS SPECIFIED IN AS LISTED ON ODOT ROADWAY ENGINEERING'S WEB PAGE UNDER ROADSIDE SAFETY DEVICES FOR THIS ITEM SHALL CONSIST OF FURNISHING AND INSTALLING ANY OF THE GUARDRAIL END TERMINALS ITEM 606 - MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1, A.P.P. ITEM 606 - ANCHOR ASSEMBLY, MGS TYPE T, A.P.P. ITEM 606 - ANCHOR ASSEMBLY, MGS TYPE E, A.P.P. ITEM 606 - GUARDRAIL, TYPE MGS, A.P.P. THE COST OF THIS WILL BE INCIDENTAL TO APPLICABLE 606 ITEMS: LIEU OF PAINTING. CHIP SHALL BE SUBMITTED FOR APPROVAL TO THE CITY ENGINEER IF POWDER COATING IS USED IN THOMARIOS IN AKRON IS AN APPROVED POWDER COATING COMPANY. SPECIFICATIONS AND PAINT ACCEPTABLE IF PROCESSES AND MATERIALS EQUAL OR EXCEED THE PAINTING REQUIREMENTS. POWDER COATING OF ALL GALVANIZED GUARDRAIL COMPONENTS IN LIEU OF PAINTING WILL BE POWDER COATING: THE WOOD POSTS SHALL NOT BE PAINTED. PAINT SHALL BE HIGH QUALITY, ALL WEATHER PAINT SUITABLE FOR USE ON GALVANIZED METAL. APPLIED IN TWO COATS, EACH WITH A MINIMUM 2.0 MILL DRY FILM THICKNESS FOR EACH COAT. A UNIFORM, CONSISTENT, AND EVEN APPLICATION ON THE SURFACE. SHER-CRYL PAINT SHALL BE SHERWIN-WILLIAMS ON THE STEEL GUARDRAIL AND STEEL HARDWARE. EACH COAT TO BE APPLIED IN AND EVEN APPLICATION. AFTER PRIMER, APPLY TWO COATS OF SHER-CRYL PAINT BY SURFACES. PAINT ALL METAL SURFACES WITH THE PRO-CRYL PRIMER IN A UNIFORM, CONSISTENT, 614-299-2116. FIRST, USE PRIMER PAINT COAT PRO-CRYL BY SHERWIN-WILLIAMS ON ALL GALVANIZED PAINTED WOLF GREY AS SUPPLIED BY SHERWIN-WILLIAMS PAINT - KING AVENUE COMMERCIAL STORE ALL STEEL GUARDRAIL SURFACES AND STEEL HARDWARE ALONG SHAWAN FALLS DRIVE SHALL BE PAINTING: FOR ITEM 202 - SIDEWALK REMOVED AND DISPOSED OF (CONCRETE). AND DISPOSAL OF CONCRETE SIDEWALK WILL BE PAID AT THE UNIT PRICE BID PER SQUARE FOOT BE PAID AT THE UNIT PRICE BID PER LINEAL FOOT UNDER THE APPROPRIATE ITEM 202. REMOVAL THE COST FOR REMOVAL AND DISPOSAL OF CONCRETE CURB AND CONCRETE CURB AND GUTTER WILL YARD UNDER ITEM 203 - EXCAVATION. REMOVAL OF ASPHALT STREET, DRIVEWAY, AND BIKE PATH PAVEMENTS WILL BE PAID PER CUBIC AND COMPENSATION FOR HAULING SHALL BE INCLUDED IN THE UNIT PRICE BID FOR ITEM 203. EXCESS EXCAVATED MATERIAL FROM THIS PROJECT SHALL BE HAULED OFFSITE BY THE CONTRACTOR AND STRAWED AT THE CONTRACTOR'S EXPENSE. - SEEDING AND MULCHING, A.P.P. ALL AREAS DISTURBED OUTSIDE THESE LIMITS SHALL BE SEEDED LIMITS OF DISTURBANCE AS SHOWN, SHALL BE SEEDED AND STRAWED IN ACCORDANCE WITH ITEM 659 ALL NON-PAVEMENT AREAS DISTURBED WITHIN THE DESIGNATED EASEMENTS, RIGHT-OF-WAY, AND INSPECTION SHALL BE INCLUDED IN THE UNIT PRICE BID FOR THE VARIOUS RELATED ITEMS. WITHOUT PROOF OF INSPECTION SHALL NOT BE APPROVED FOR INSTALLATION. THE COST OF THAT INSPECTION HAS BEEN PERFORMED BY THE CITY OF DUBLIN. PRECAST CONCRETE PRODUCTS APPROVED PRECAST CONCRETE PRODUCTS WILL BE STAMPED OR HAVE SUCH IDENTIFICATION NOTING ALL PRECAST CONCRETE PRODUCTS SHALL BE INSPECTED AT THE LOCATION OF MANUFACTURE. CONTRACT. COST OF THIS WORK SHALL BE INCLUDED IN THE PRICES BID FOR THE VARIOUS ITEMS OF THE FIRST BE COORDINATED WITH THE U.S. POSTAL SERVICE AND AFFECTED PROPERTY OWNERS. THE ORIGINAL LOCATION OR APPROVED NEW LOCATION. ANY RELOCATION OF MAILBOX SERVICES MUST COMPLETION OF THE WORK AND SHALL ALSO INCLUDE THE RESTORATION OF MAILBOXES TO THEIR LIMITED TO RELOCATION OF MAILBOXES TO A TEMPORARY LOCATION THAT WILL ALLOW THE PROJECT LIMITS IS NOT DISRUPTED BY CONSTRUCTION OPERATIONS. THIS RESPONSIBILITY IS THE CONTRACTOR SHALL BE RESPONSIBLE FOR ENSURING THAT U.S. MAIL DELIVERY WITHIN THE OPERATION. OR BARRICADES DURING NONWORKING HOURS. CLEAN UP SHALL FOLLOW CLOSELY BEHIND TRENCHING THESE AREAS SHALL BE BACKFILLED OR SHALL BE PROTECTED BY APPROVED TEMPORARY FENCING CONSTRUCTION DRAWINGS OR SECURELY PLATED DURING NONWORKING HOURS. TRENCHES OUTSIDE ALL TRENCHES WITHIN PUBLIC RIGHT-OF-WAY SHALL BE BACKFILLED ACCORDING TO THE APPROVED COST OF THIS WORK SHALL BE THE RESPONSIBILITY TO THE CONTRACTOR. AND CONNECTED TO THE PUBLIC STORM SEWER SYSTEM AS DIRECTED BY THE CITY ENGINEER. THE ALL FIELD TILE BROKEN OR ENCOUNTERED DURING EXCAVATION SHALL BE REPLACED OR REPAIRED THE CONTRACTOR. SATISFACTION OF THE CITY ENGINEER. THE COST OF THIS WORK SHALL BE THE RESPONSIBILITY OF DISTURBED OR DAMAGED DURING CONSTRUCTION SHALL BE REPLACED OR REPAIRED TO THE ALL SIGNS, LANDSCAPING, STRUCTURES, OR OTHER APPURTENANCES WITHIN RIGHT-OF-WAY CONTRACTOR. AND CLEAN AFFECTED AREAS, THE COST OF WHICH SHALL BE THE RESPONSIBILITY OF THE DEBRIS, OR SPILLAGE, THE CITY OF DUBLIN RESERVES THE RIGHT TO REMOVE THESE MATERIALS CONTRACTOR AT NO COST TO THE CITY. IF THE CONTRACTOR FAILS TO REMOVE THE MUD, DIRT, CODE OF ORDINANCES. ANY SUCH OCCURRENCE SHALL BE CLEANED UP IMMEDIATELY BY THE DRIVES, SIDEWALKS, OR BIKE PATHS IS PROHIBITED ACCORDING TO SECTION 97.38 OF THE DUBLIN TRACKING OR SPILLING MUD, DIRT, OR DEBRIS UPON STREETS, RESIDENTIAL OR COMMERCIAL CONSTRUCTION. CONSTRUCTION SHALL BE RESTORED TO THE GRADES AND CROSS-SECTIONS THAT EXISTED BEFORE EXISTED BEFORE CONSTRUCTION. DRAINAGE DITCHES OR WATER COURSES THAT ARE DISTURBED BY THE CONTRACTOR SHALL RESTORE ALL DISTURBED AREAS TO EQUAL OR BETTER CONDITION THAN WITHOUT WRITTEN PERMISSION FROM THE CITY ENGINEER. NON-RUBBER TIRED VEHICLES SHALL NOT BE MOVED ON OR ACROSS PUBLIC STREETS OR HIGHWAYS OBTAIN ADDITIONAL INFORMATION AT HIS OWN EXPENSE, IF NECESSARY, IN HIS JUDGMENT. ACTUAL SUBSURFACE CONDITIONS. THE CONTRACTOR SHALL EXAMINE THIS INFORMATION AND PROVIDED IN THE BIDDING DOCUMENTS. LOGS AND TESTS ARE NOT WARRANTED TO SHOW THE SUBSURFACE INVESTIGATIONS WERE PERFORMED FOR DESIGN AND ESTIMATING PURPOSES AND ARE ITEM 653-TOPSOIL FURNISHED AND PLACED, A.P.P. (T=4") NJL 66 4/7/22 58074 P:\PR58074\FRA\000000\Design\Roadway\Sheets\GN001.dgn Sheet 5/6/2022 5:10:17 PM jkelleyNJL 3 REPLACEMENT BRIDGE SHAWAN FALLS GENERAL NOTES NONE 3BRIDGE REPLACEMENTSHAWAN FALLS DRIVEMSL JMK ITEM 659-SEEDING AND MULCHING, A.P.P. TREES DRAINAGE SUBGRADE ITEM 204 EXCAVATION OF SUBGRADE ITEM 204 GRANULAR EMBANKMENT, NO. 2 STONE PAVEMENT AMERICANS WITH DISABILITIES ACT (ADA) 30 C.Y. 30 C.Y. DESIGN THE NEW PAVEMENT. PROVIDING SUBGRADE SUPPORT PARAMETERS EQUAL TO OR GREATER THAN THE VALUES USED TO ALL BORROW SOILS PLACED WITHIN 3 FEET OF THE FINAL SUBGRADE LEVEL SHALL BE CAPABLE OF ALLOWANCE FOR BIDDING PURPOSES. UANTITIES HAVE BEEN INCLUDED AS AN AND REPLACED PER SECTION 204.04. THE FOLLOWING Q SATISFACTORY COMPACTION CANNOT BE OBTAINED, THE UNSTABLE MATERIAL SHALL BE REMOVED WHERE SOFT SUBGRADE IS ENCOUNTERED DUE TO NO FAULT OF THE CONTRACTOR, AND 16 ITEM 204 - PROOF ROLLING 2 HOURPROOF ROLLINGITEM 204 REQUIRING PROOF ROLLING. THE FOLLOWING QUANTITY IS PROVIDED IN THE GENERAL SUMMARY TO ADDRESS LOCATIONS DRAIN OUTLETS SHALL BE INCLUDED IN THE VARIOUS STORM SEWER ITEMS. DITCH OR STORM SEWER, AS APPROVED BY THE ENGINEER. THE COST FOR REESTABLISHING PRIVATE DOWNSPOUTS, FOUNDATION DRAINS, CATCH BASINS, YARD DRAINS, ETC., INTO THE NEAREST NEW CONTRACTOR SHALL REESTABLISH THE OUTLETS OF ALL PRIVATE DRAINS ENCOUNTERED SUCH AS WHERE THE WORK CALLS FOR RELOCATION OF EXISTING DITCHES OR STORM SEWER, THE THIS WORK SHALL BE INCLUDED IN THE PRICES BID FOR THE VARIOUS ITEMS OF THE CONTRACT. RESTORING NORMAL FUNCTION TO THE TILE, AS DIRECTED BY THE CITY ENGINEER. THE COST OF IN LIKE KIND AND CONNECTED TO THE NEAREST STORM SEWER OR OPEN CHANNEL OUTLET, ALL FIELD TILE BROKEN OR ENCOUNTERED DURING EXCAVATION SHALL BE REPLACED OR REPAIRED SEPARATE PAYMENT. DESIGNATED. EXISTING HEADWALLS SHALL BE REMOVED AND DISPOSED AS INDICATED WITH NO DISPOSED OF BY THE CONTRACTOR IN ACCORDANCE WITH THE APPLICABLE 202 ITEM WHERE NOT SPECIFICALLY DESIGNATED FOR REMOVAL. STORM SEWER PIPE SHALL BE REMOVED AND SHALL BE PROTECTED FROM DAMAGE BY THE CONTRACTOR DURING THE COURSE OF THE WORK IF EXISTING STORM SEWERS LOCATED WITHIN THE WORK LIMITS AND THEIR ASSOCIATED STRUCTURES CONTRACT. PAYMENT FOR THIS SHALL BE INCLUDED IN THE PRICES BID FOR THE VARIOUS ITEMS OF THE SHALL BE RESTORED BY THE CONTRACTOR TO A CONDITION SATISFACTORY TO THE CITY ENGINEER. COURSES ENCOUNTERED AND DISTURBED OR DESTROYED DURING THE PROSECUTION OF THE WORK COMPLETED AND PUT INTO SERVICE. THE FLOW OF ALL STORM SEWERS, DRAINS, AND OTHER WATER SEWER, DRAIN, AND DITCH FLOWS THROUGH EXISTING FACILITIES UNTIL NEW FACILITIES ARE THE CONTRACTOR SHALL CONDUCT HIS OPERATIONS SO AS TO MAINTAIN AT ALL TIMES STORM 204.03. THE COST SHALL BE INCLUDED IN THE UNIT PRICE BID FOR ITEM 203, EXCAVATION. FOLLOW THE REQUIREMENTS FOR COMPACTION UNDER DRIVEWAYS AS DESCRIBED IN SECTION E. SUBGRADE COMPACTION SHALL BE REQUIRED UNDER SIDEWALKS AND BIKE PATHS, AND SHALL ACCORDANCE WITH ODOT ITEM 204.06. PAVEMENT SUBGRADE ELEVATION, THE PAVEMENT SUBGRADE SHALL BE PROOFROLLED IN D. AFTER EMBANKMENT FILL HAS BEEN PLACED IN FILL AREAS TO ACHIEVE THE REQUIRED ODOT ITEM 204.06. SUBGRADE FOR PAVEMENTS AND EMBANKMENTS SHALL BE PROOFROLLED IN ACCORDANCE WITH C. SUBSEQUENT TO MOISTURE CONDITIONING AND RECOMPACTION EFFORTS, THE EXPOSED 204.03. MOISTURE CONDITIONING SHALL BE IN ACCORDANCE WITH ITEM 203.07.A. A DEPTH OF 12 INCHES, MOISTURE CONDITIONED, AND RECOMPACTED IN ACCORDANCE WITH ITEM THE PROPOSED PAVEMENT SUBGRADE ELEVATION THE EXPOSED SURFACE SHALL BE SCARIFIED TO B. IN AREAS TO RECEIVE EMBANKMENT FILL AND IN AREAS WHERE ANY CUT HAS BEEN MADE TO REMOVED FROM THE ENTIRE FOOTPRINT OF THE PROPOSED ROADWAY OR EMBANKMENT AREA. ENTIRE ROOT MASS, VEGETATION, AND OTHER MISCELLANEOUS MATERIALS SHALL BE COMPLETELY A. EXISTING PAVEMENTS, STRUCTURES, SOD AND TOPSOIL, EXISTING TREES INCLUDING THEIR FOLLOWING PROCEDURES: THE CONTRACTOR SHALL PREPARE ALL SUBGRADES FOR PAVEMENTS AND EMBANKMENTS USING THE M GAL7 SY500 TON0.18 SY1366 CY152 DURING CONSTRUCTION. THE CONTRACTOR TO INSTALL ADDITIONAL FENCING IN AREAS WHERE TREES COULD BE DAMAGED PLAN PRIOR TO THE START OF ANY CONSTRUCTION. THE CITY RESERVES THE RIGHT TO DIRECT PROTECTED WITH HIGH VISIBILITY TREE PROTECTION FENCING AS REQUIRED ON THE TREE REMOVAL THE PLANS OR NOT, SHALL BE PRESERVED WITHOUT DAMAGE. TREES TO BE PRESERVED SHALL BE ALL TREES WITHIN THE CONSTRUCTION AREA NOT DESIGNATED FOR REMOVAL, WHETHER SHOWN ON EMBANKMENTS SHALL BE PLACED USING MATERIALS CONFORMING TO ODOT 703.16A. THE WORK, AND SHALL MAKE ANY NECESSARY REPAIRS AT NO COST TO THE CITY. RIGHT-OF-WAY AND PUBLIC EASEMENTS FOR A PERIOD OF ONE YEAR FROM FINAL ACCEPTANCE OF THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE CONDITION OF THE TRENCHES WITHIN THE HOURS. CLEAN UP SHALL FOLLOW CLOSELY BEHIND THE TRENCHING OPERATION. SHALL BE PROTECTED BY APPROVED TEMPORARY FENCING OR BARRICADES DURING NON-WORKING PLATED DURING NON-WORKING HOURS. TRENCHES OUTSIDE THESE AREAS SHALL BE BACKFILLED OR ALL TRENCHES WITHIN PAVEMENT, BERM, AND SHOULDER LIMITS SHALL BE BACKFILLED OR SECURELY VARIOUS 901 PIPE ITEMS. COST OF ITEM 911 AND ITEM 912 BACKFILL SHALL BE INCLUDED IN THE UNIT PRICE BID FOR THE ALL NON-GRANULAR BACKFILL SHALL BE FURNISHED AND PLACED IN ACCORDANCE WITH ITEM 911. THE MATERIALS AND SAND ARE UNACCEPTABLE. CONSIST OF NATURAL, BROKEN, OR CRUSHED ROCK CARBONATE. SYNTHETIC OR MANMADE CONTROLLED DENSITY BACKFILL ACCORDING TO ITEM 613, TYPE II. ITEM 912 MATERIAL SHALL GRANULAR BACKFILL SHALL BE COMPACTED GRANULAR MATERIAL ACCORDING TO ITEM 912 OR WITH COMPACTED GRANULAR MATERIAL ACCORDING TO ITEM 912 OF THE STANDARD SPECIFICATIONS. SIDEWALK, BIKE PATH, OR WHERE SPECIFICALLY CALLED FOR ON THE PLANS, SHALL BE BACKFILLED TRENCHES WITHIN 2 FEET OF PROPOSED PAVEMENT, CURB AND GUTTER, BERM, SHOULDERS, STANDARD SPECIFICATIONS SHALL BE USED ELSEWHERE. STANDARD SPECIFICATIONS OR FLOWABLE CDF, TYPE 2 ACCORDING TO ITEM 613. ITEM 911 OF USE PATHS, ETC.) SHALL BE COMPACTED GRANULAR BACKFILL ACCORDING TO ITEM 912 OF THE OTHER PUBLIC INFRASTRUCTURE (PAVEMENT, SIDEWALKS, CURBS, HEADWALLS, WINGWALLS, SHARED BACKFILL WITHIN A 1:1 INFLUENCE LINE OF EXISTING STRUCTURES (HOUSES, GARAGES, ETC.) OR WALK, CURBS OR STRUCTURES. FIBROUS TYPE EXPANSION MATERIAL SHALL NOT BE USED. (RECYCLED EXPANSION MATERIAL) SHALL BE UTILIZED WHERE NEW CONCRETE WORK MEETS EXISTING FULL DEPTH EXPANSION MATERIAL ONE-HALF (1/2) INCH THICK CONFORMING TO ASTM D 1752, TYPE 1 NON-TRACKING TACK COAT FOR ESTIMATING PURPOSES ONLY. QUANTITIES INDICATE AN AVERAGE APPLICATION RATE OF 0.15 GALLONS PER SQUARE YARD OF ON THE PLANS SHALL BE SUBJECT TO ADJUSTMENT AS DIRECTED BY THE CITY ENGINEER. PLAN TO REPAVING. THE RATE OF APPLICATION OF ITEM 407, NON-TRACKING TACK COAT AS INDICATED ALL PLANED ASPHALT SURFACES SHALL RECEIVE A NON-TRACKING TACK COAT PER ITEM 407 PRIOR THE CONTRACTOR SHALL NOT USE ANY RECLAIMED MATERIALS IN ITEM 304. SHOWN ON THE PAVEMENT DETAILS SHALL GOVERN. DUE TO PAVEMENT CROSS SLOPEWARPING. IN ALL CASES, THE TOP OF PAVEMENT ELEVATIONS DEVIATIONS FROM THE ROADWAY PROFILES AND TYPICAL SECTION CROSS SLOPES IN SOME AREAS TOP OF PAVEMENT ELEVATIONS SHOWN ON THE INTERSECTION DETAIL (SHEET ) MAY REFLECT STD. CONSTRUCTION DWG. BP-3.1. BUTT JOINTS BETWEEN EXISTING AND NEW PAVEMENT SHALL BE MADE IN ACCORDANCE WITH ODOT REQUIRED BY THE CITY ENGINEER. PAVEMENTS SHALL BE CUT IN NEAT, STRAIGHT LINES TO THE FULL DEPTH OF THE PAVEMENT, OR AS ITEM 203 - EMBANKMENT, A.P.P. AREAS TO A HEIGHT OF 2 TO 3 INCHES. MOWING TO MAINTAIN SPECIFIED HEIGHT WITHOUT CUTTING MORE THAN 1/3 OF GRASS HEIGHT. MOW MOW TURFGRASS SEED MIX AREAS AS SOON AS TOP GROWTH IS TALL ENOUGH TO CUT. REPEAT RAINFALL PRECIPITATION IS ADEQUATE. WATER TURF WITH FINE SPRAY AT A MINIMUM RATE OF 1 INCH PER WEEK FOR 5 WEEKS UNLESS MATERIALS AND INSTALLATION AS THOSE USED IN THE ORIGINAL INSTALLATION. ERODED AREAS AND REMULCH TO PRODUCE A UNIFORMLY SMOOTH TURF. PROVIDE THE SAME REPLANTING TO ESTABLISH HEALTHY, VIABLE TURF. ROLL, REGRADE, AND REPLANT BARE OR MAINTAIN AND ESTABLISH TURF BY WATERING, FERTILIZING, WEEDING, MOWING, TRIMMING, AND TURF MAINTENANCE: LIMITS AND WERE DERIVED FROM CADD AREAS. CONSTRUCTION LIMITS. QUANTITY CALCULATIONS FOR SEEDING AND MULCHING ARE BASED ON THESE SEEDING AND MULCHING SHALL BE APPLIED TO ALL AREAS OF EXPOSED SOIL WITHIN THE ITEM 659 - WATER ITEM 659 - REPAIR SEEDING AND MULCHING, A.P.P. ITEM 659 - COMMERCIAL FERTILIZER ITEM 659 - SEEDING AND MULCHING, A.P.P. ITEM 653 - TOPSOIL FURNISHED AND PLACED, A.P.P. (T=4") AREAS: THE FOLLOWING QUANTITIES ARE PROVIDED TO PROMOTE GROWTH AND CARE OF PERMANENT SEEDED PRECIPITATION IS ADEQUATE, FOR 5 CONSECUTIVE WEEKS. WATER TURF WITH FINE SPRAY AT A MINIMUM RATE OF 1 INCH PER WEEK UNLESS RAINFALL PROVIDE THE SAME MATERIALS AND INSTALLATION AS THOSE USED IN THE ORIGINAL INSTALLATION. HYDRO-SEEDING IS PERMITTED. HYDRO-MULCHING IS NOT PERMITTED. BE PAID FOR BY THE CITY. DIRECTED BY THE ENGINEER. COST OF EROSION CONTROL BLANKETS, MATERIAL, AND LABOR SHALL PROTECT SEEDED AREAS WITH SLOPES EXCEEDING 3:1 WITH EROSION CONTROL BLANKETS AS BLOWN OR WASHED AWAY IN AREAS THAT ARE NOT COVERED WITH EROSION CONTROL MATS. SOW SEED AT A TOTAL RATE OF 7-9 LB. / 1000 SF. THOROUGHLY COVER WITH STRAW FROM BEING SEEDING: 2. 50 PERCENT PERENNIAL RYEGRASS (LOIUM PERENNE). CULTIVARS. TWO "IMPROVED" 1. 50 PERCENT KENTUCKY BLUEGRASS (POA PRATENSIS, MINIMUM OF SUN AND PARTIAL SHADE MIXTURE PROPORTIONED BY WEIGHT AS FOLLOWS: THAN 98 PERCENT PURE SEED, AND NOT MORE THAN 0.5 PERCENT WEED SEED. SEED SPECIES SHALL BE AS FOLLOWS, WITH NOT LESS THAN 90 PERCENT GERMINATION, NOT LESS TOLERANCES. "JOURNAL OF SEED TECHNOLOGY" RULES FOR TESTING SEED FOR PURITY AND GERMINATION GRASS SEED MUST BE FRESH, CLEAN, DRY, NEW-CROP SEED COMPLYING WITH THE A.O.S.A. SPECIFICATION AS FOLLOWS: SEEDING AND MULCHING TO BE PER COLUMBUS C&MS ITEM 659, CLASS 1 EXCEPT FOR THE SEED PATH. BE IN ADDITION TO ANY OVERLAPPING PAYMENTS PER SQUARE FOOT FOR SIDEWALK OR PEDESTRIAN PRICE BID PER SQUARE FOOT FOR ITEM 608 - DETECTABLE WARNING PANELS, A.P.P., AND SHALL RED COLOR SHALL BE USED, FED. 22144. THE COST OF THIS WORK WILL BE PAID AT THE UNIT ALL DETECTABLE WARNINGS SHALL BE TUFTILE, A WET-SET CAST IRON (REPLACEABLE) TILE. BRICK WORK IS IN ACCORDANCE WITH ADA GUIDELINES. MADE BY THE CONTRACTOR BASED ON THE AS-BUILT INFORMATION TO INSURE THAT THE FINISHED EXISTING WALK PRIOR TO THE START OF RAMP CONSTRUCTION. ADJUSTMENTS IN GRADE SHALL BE AS-BUILT ELEVATIONS OF ADJACENT NEW OR EXISTING CONCRETE CURB AND ADJACENT NEW OR DESIGN THAT IS COMPATIBLE WITH ADA GUIDELINES. THE CONTRACTOR SHALL DETERMINE THE THE ELEVATIONS AND SLOPES PROVIDED ON THE DRAWINGS ARE INTENDED TO CONVEY A ACCESSIBILITY GUIDELINES FOR BUILDINGS AND FACILITIES (ADAGG). ACCORDANCE WITH THE LATEST STANDARDS OF THE AMERICANS WITH DISABILITIES ACT ALL SIDEWALKS, PEDESTRIAN PATHS, CURB RAMPS, AND DRIVEWAYS SHALL BE CONSTRUCTED IN NJL 66 4/7/22 58074 P:\PR58074\FRA\000000\Design\Roadway\Sheets\GN001.dgn Sheet 5/6/2022 5:10:20 PM jkelleyNJL 4 REPLACEMENT BRIDGE SHAWAN FALLS GENERAL NOTES NONE 4BRIDGE REPLACEMENTSHAWAN FALLS DRIVEMSL JMK STORM SEWER ITEM SPECIAL - CONCRETE FLARED END SECTION INCIDENTALS REQUIRED TO INSTALL COMPLETE AND ACCEPTED. SHALL BE AT THE UNIT PRICE BID PER EACH INCLUDING ALL LABOR, MATERIALS, EQUIPMENT, AND SECTION AS MANUFACTURED BY FORTERRA PIPE AND PRECAST, OR APPROVED EQUAL. PAYMENT THE OUTLETS OF ALL NEW STORM SEWER AND CULVERT PIPES SHALL HAVE A CONCRETE FLARED END STRUCTURE PROPOSED MANHOLES PROPOSED CATCH BASINS PROPOSED CURB INLETS "TC" ELEVATION LOCATION TOP OF CASTING TOP OF CASTING TOP OF CURB OF DRAIN LEADER PIPE REPLACED WHERE NOT INCLUDED UNDER OTHER PAY ITEM(S). CONNECTORS, EQUIPMENT, AND OTHER INCIDENTALS. WORK IS TO BE PAID PER LINEAR FOOT (LF) THE UNIT PRICE FOR THIS ITEM SHALL INCLUDE ALL LABOR, MATERIALS INCLUDING APPROVED DIAMETER FOR COMMERCIAL, OR AS SPECIFIED. AT THE TIME OF THE BACKFILL OPERATION. PIPE SIZE IS 3" DIAMETER FOR RESIDENTIAL AND 4" ON COMPACTED BEDDING EQUAL DENSITY TO SURROUNDING STRATUM. REPLACEMENT SHALL BE DONE MAINTAINING THE SAME GRADIENT AS EXISTING IF FEASIBLE. REPLACED DRAIN TILE SHALL BE LAID OF THE CONTRACTOR'S OPERATIONS SHALL BE REPLACED WITH SCHEDULE 40 PIPE OR BETTER, ALL DOWNSPOUT DRAIN TILE AND STORM SEWERS DAMAGED, DISTURBED, OR REMOVED AS A RESULT AS DIRECTED BY THE ENGINEER AND IN ACCORDANCE WITH THE CMSC. PERFORMED IN CONJUNCTION WITH SIDEWALK AND CURB AND GUTTER REPLACEMENT OR OTHER WORK THIS ITEM CONSISTS OF THE REMOVAL AND REPLACEMENT OF EXISTING ROOF DRAIN PIPES ITEM SPECIAL - DRAIN LEADER PIPE ITEM SPECIAL - CURB CAN HOLES INSTALLED BEYOND THE TWO FEET LIMIT WHERE DIRECTED BY ENGINEER. PAYMENT WILL BE MADE UNDER ITEM SPECIAL - DRAIN LEADER PIPE FOR ADDITIONAL PIPE MANNER APPROVED BY THE ENGINEER AS SOON AS POSSIBLE AFTER CURB FORMS ARE REMOVED. DRAIN LEADERS SHALL BE REPLACED UP TO TWO (2) FEET BEHIND THE CURB AND RECONNECTED IN A DRAIN OPENINGS WILL BE UNDER ITEM SPECIAL - CURB CAN HOLES. INCIDENTAL TO THE CURBING, OPENINGS IN THE CURB ARE TO BE CORED, AND NOT FORMED IN PLACE. PAYMENT FOR CORING THE THE CONTRACTOR SHALL IDENTIFY, MARK, AND RESTORE ALL DRAIN OPENINGS IN THE CURB. DRAIN BE INCLUDED IN THE CONTRACT PRICE FOR THE PERTINENT CONTRACT ITEMS. PAYMENT FOR THE DETERMINATION OF LINE AND GRADE OF EXISTING UTILITIES AS REQUIRED SHALL WHICH WOULD BE AFFECTED BY THE CONFLICT. SHALL BE NOTIFIED BEFORE STARTING CONSTRUCTION ON ANY PORTION OF THE PROPOSED CONDUIT SEWER OR UNDERGROUND UTILITY WHEN CONSTRUCTED AS SHOWN ON THE PLAN, THE CITY ENGINEER IF IT IS DETERMINED THAT A PROPOSED CONDUIT WILL CONFLICT WITH AN EXISTING SANITARY AFFECTED BY THE VARIANCE IN THE EXISTING ELEVATIONS. BEFORE STARTING CONSTRUCTION OF ANY PORTION OF THE PROPOSED CONDUIT WHICH WILL BE TO BE CONNECTED DIFFERS FROM THE PLAN ELEVATION, THE CITY ENGINEER SHALL BE NOTIFIED IF IT IS DETERMINED THAT THE ELEVATION OF THE EXISTING CONDUIT OR EXISTING APPURTENANCE OR UTILITIES FOR BOTH LINE AND GRADE PRIOR TO THE START OF PIPE LAYING. SANITARY SEWER OR UNDERGROUND UTILITY, THE CONTRACTOR SHALL LOCATE THE EXISTING PIPES WHERE PLANS CALL FOR CONDUIT TO BE CONNECTED TO, OR CROSS OVER OR UNDER AN EXISTING SHALL BE INCLUDED IN THE CONTRACT PRICE FOR THE RELATED ITEMS. PAYMENT FOR ALL INSPECTIONS, CLEANING, AND MAINTENANCE OF EXISTING AND NEW STORM SEWER PROJECT WILL BE ACCEPTED BY THE CITY. PROJECT SHALL BE FREE OF ALL FOREIGN MATTER AND IN A CLEANED CONDITION BEFORE THE ALL NEW CONDUITS, INLETS, CATCH BASINS AND MANHOLES CONSTRUCTED AS A PART OF THE ENGINEER AT THE CONTRACTOR'S EXPENSE. OPERATIONS SHALL BE CORRECTED BY THE CONTRACTOR TO THE SATISFACTION OF THE CITY ORIGINAL INSPECTION. ANY CHANGE IN THE CONDITION RESULTING FROM THE CONTRACTOR'S MAINTAINED AND LEFT IN A CONDITION REASONABLY COMPARABLE TO THAT DETERMINED BY THE ALL EXISTING SEWERS INSPECTED INITIALLY BY THE ABOVE MENTIONED PARTIES SHALL BE CITY. FROM FIELD OBSERVATIONS. RECORDS OF THE INSPECTION SHALL BE KEPT IN WRITING BY THE THE CONDITION OF THE EXISTING CONDUITS AND THEIR APPURTENANCES SHALL BE DETERMINED EXISTING SEWERS WHICH ARE TO REMAIN IN SERVICE AND WHICH MAY BE AFFECTED BY THE WORK. CITY, REPRESENTATIVES OF THE CITY AND THE CONTRACTOR SHALL MAKE AN INSPECTION OF ALL BEFORE ANY WORK IS STARTED ON THE PROJECT, AND AGAIN BEFORE FINAL ACCEPTANCE BY THE OTHER DRAINAGE STRUCTURES SHALL BE INCLUDED IN THE PRICE BID FOR THOSE STRUCTURES. APPROXIMATE. THE COST OF CASTING ADJUSTMENTS FOR NEW OR RECONSTRUCTED MANHOLES OR GRADE BY THE CONTRACTOR. TOP OF CASTING ELEVATIONS PROVIDED ON THE PLANS ARE ALL EXISTING AND PROPOSED CASTINGS SHALL BE ADJUSTED TO MATCH THE SURROUNDING FINISH ENGINEER. NO SEPARATE PAYMENT. LENGTH OF BACKFILL SHALL BE FOR ALL EXPOSED PORTIONS OF PIPE, OR AS DIRECTED BY THE OR AA-S149 (FLEXIBLE PIPE), TYPE 1 BEDDING USING ITEM 905 CLASS "A" CONCRETE. THE TOTAL WORK SHALL BE IN ACCORDANCE WITH CITY OF COLUMBUS STANDARD DRAWING AA-S151 (RIGID PIPE), WHERE CONCRETE ENCASEMENT IS INDICATED ON THE PLANS, OR DIRECTED BY THE ENGINEER, THE LIMITS CALLED FOR, AS REQUIRED, TO MAKE OUTLET CONNECTIONS. AVAILABLE ALONG THE LINE OF FLOW. CONTRACTOR SHALL PROVIDE UNDERDRAIN BEYOND THE ROADWAY UNDERDRAINS SHALL BE DISCHARGED INTO THE NEAREST STORMWATER STRUCTURE STRUCTURE AT THE FACE OF CURB PER ODOT STANDARD DRAWING CB-2.1. OFFSETS ARE PROVIDED FOR CURB INLETS, THEY SHALL BE MEASURED TO THE CENTERLINE OF THE INLETS WITHIN THE CURB LINE IN ACCORDANCE WITH THE STANDARD DRAWINGS REFERENCED. WHERE WHERE BASELINE OFFSETS ARE NOT PROVIDED, THE CONTRACTOR SHALL PLACE CURB AND GUTTER SHALL BE UNDERSTOOD AS MEANING THE FOLLOWING: WHEREVER REFERENCE IS MADE TO THE ELEVATION TERM "TC" ON THE PLANS, THIS ABBREVIATION ALL CATCH BASINS AND CURB INLETS MUST BE FURNISHED WITH BIKE SAFE GRATES. ALL INLETS, CATCH BASINS, AND MANHOLES SHALL BE CHANNELIZED. CLASS III FOR 18 INCHES AND LARGER. TO ASTM DESIGNATION C76, WALL B, CLASS IV FOR PIPE DIAMETERS 12 INCHES TO 15 INCHES AND UNLESS OTHERWISE INDICATED, STORM SEWERS SHALL BE REINFORCED CONCRETE PIPE CONFORMING NJL 66 4/7/22 58074 P:\PR58074\FRA\000000\Design\Roadway\Sheets\GN001.dgn Sheet 5/6/2022 5:10:21 PM jkelleyNJL 5 REPLACEMENT BRIDGE SHAWAN FALLS GENERAL NOTES NONE 5BRIDGE REPLACEMENTSHAWAN FALLS DRIVEMSL JMK UTILITIES CONTACT INFORMATION. UTILITIES KNOWN TO BE LOCATED WITHIN THE LIMITS OF THIS PROJECT ARE LISTED BELOW WITH STANDARD DRAWING LIST CITY OF DUBLIN CITY OF COLUMBUS O.D.O.T. MADE AT THE UNIT PRICE BID PER EACH. PERFORMED BY AN OHIO PROFESSIONAL SURVEYOR AS APPROVED BY THE CITY. PAYMENT WILL BE ON ODOT STANDARD CONSTRUCTION DRAWING RM 1.1. RESETTING OF MONUMENTS SHALL BE REESTABLISH RIGHT OF WAY MONUMENTS AND ASSEMBLIES IN ACCORDANCE WITH THE DETAILS SHOWN BELOW SHALL BE CONSIDERED A PART OF THESE PLANS. CURRENT VERSIONS OF THE STANDARD DRAWINGS AND SUPPLEMENTAL SPECIFICATIONS LISTED TO INDUSTRY PRACTICES. WORK AFFECTED. THE CONTRACTOR IS REMINDED TO KEEP THEIR OUPS TICKET UPDATED ACCORDING RELOCATED UTILITY FACILITIES. COSTS TO EXPOSE CONDUIT SHALL BE INCLUDED IN THE ITEMS OF THE CONTRACTOR SHALL EXERCISE CAUTION WHEN WORKING IN THE PROXIMITY OF EXISTING AND/OR ENGINEER. CONSTRUCTION, THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE UTILITY OWNER AND THE CITY WHEN UNKNOWN OR INCORRECTLY LOCATED UNDERGROUND UTILITIES ARE ENCOUNTERED DURING ITEMS OF THE CONTRACT. CONTRACTOR. THE COST OF THIS WORK SHALL BE INCLUDED IN THE PRICES BID FOR THE VARIOUS APPURTENANCES, SHOWN OR NOT SHOWN ON THE PLANS, SHALL BE THE RESPONSIBILITY OF THE LOCATION, SUPPORT, PROTECTION AND RESTORATION OF ALL EXISTING UTILITIES AND RESULTING CONTINGENT DAMAGE. CAUSED, THE CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIR OF THE SAME AND FOR ANY FOR THE ACCURACY OR DEPTHS OF UNDERGROUND FACILITIES SHOWN ON THE PLANS. IF DAMAGE IS UNDERGROUND UTILITY. THE CITY OF DUBLIN AND THE CITY ENGINEER ASSUMES NO RESPONSIBILITY HAVE BEEN SHOWN ON THE PLANS AS ACCURATELY AS PROVIDED BY THE OWNER OF THE THE IDENTITY AND LOCATIONS OF EXISTING UNDERGROUND UTILITIES IN THE CONSTRUCTION AREA GIVEN AT LEAST 2 WORKING DAYS BEFORE START OF CONSTRUCTION. THAT ARE NOT MEMBERS OF A REGISTERED UNDERGROUND PROTECTION SERVICE. NOTICE SHALL BE SERVICE (TELEPHONE NUMBER 811 OR 800-362-2764) AND TO OWNERS OF UNDERGROUND UTILITIES THE CONTRACTOR SHALL GIVE NOTICE OF INTENT TO CONSTRUCT TO OHIO UTILITIES PROTECTION ABBREVIATIONS BUTYL SEALANT. BASIN, THE RINGS, AND THE RINGS AND COVER FRAME SHALL BE SEALED UTILIZING AN APPROVED MANUFACTURE'S RECOMMENDATIONS ONLY. THE ANNULAR SPACE BETWEEN THE RINGS AND CONE POLYETHYLENE PLASTIC MOLDING AND EXTRUSION MATERIALS). INSTALLATION SHALL BE PER PLASTIC AS IDENTIFIED IN ASTM DESIGNATION D-1248 (STANDARD SPECIFICATION FOR ADJUSTMENT RINGS. THESE ADJUSTMENT RINGS SHALL BE MANUFACTURED FROM POLYETHYLENE COVERS AND FRAME ASSEMBLIES USING INJECTION MOLDED HIGH DENSITY POLYETHYLENE (HDPE) THE CONTRACTOR WILL MAKE ALL FINAL GRADE ADJUSTMENT OF MANHOLE, CATCH BASIN AND INLET 1/15/2021TST-1-99 7/20/2018PSBD-2-07 7/17/2020PCB-91 7/18/2003DS-1-92 7/20/2018BD-1-11 1/18/2019AS-2-15 7/17/2015AS-1-15 1/15/2021RM-1.1 4/18/2014SS-846 1/19/2018MGS-6.1 7/15/2016MGS-5.3 7/15/2016MGS-5.2 1/19/2018MGS-3.1 1/19/2018MGS-2.1 7/16/2021MGS-1.1 1/17/2020BP-3.1 7/19/2013F-1.1 1/15/2016DM-4.3 COLUMBUS, OH 43231 3765 CORPORATE DRIVE PHONE (OFFICE): (614) 481-5047 PHONE (CELL): (614) 348-2966 SAM LUTZ WIDE OPEN WEST (WOW) COLUMBUS, OH 43204 3760 INTERCHANGE RD PHONE: (614) 402-1979 EMAIL: JOSEPH.VLOCK@CHARTER.COM JOSEPH VLOCK CHARTER COMMUNICATIONS (USIC) COLUMBUS, OH 43215 111 NORTH 4TH ST PHONE: (614) 329-2195 EMAIL: TL9569@ATT.COM MIKE LEPLEY AT&T-OHIO (USIC) COLUMBUS, OH 43215 111 NORTH 4TH ST PHONE: (614) 208-9312 EMAIL: KG1963@ATT.COM KEVIN GLASER AT&T-OHIO (USIC) AKRON, OH 44303 120 RAVINE ST PHONE (C): (330) 329-5495 PHONE (O): (330) 253-8267 EMAIL: ALLAN.GUEST@VERIZON.COM AL GUEST MCI 7/1/2021COC 4163 7/9/2012AA-S171 7/9/2012AA-S153 7/9/2012AA-S151 7/9/2012AA-S150 10/15/2014AA-S149 12/6/2013AA-S138 12/6/2013AA-S113 1/1/2020WA-01 1/1/2020RD-11 1/1/2020RD-10 1/1/2020RD-07 1/1/2020RD-05 1/1/2020RD-04 1/1/2020RD-03 1/1/2020RD-02 1/1/2020RD-01 1/1/2020PD-09 1/1/2020PD-08 1/1/2020PD-07 1/1/2020PD-06 1/1/2020PD-03 1/1/2020PD-02 1/1/2020PD-01 10/18/2019SS 907 10/18/2019SS 816 7/17/2020MT-101.90 1/17/2020MT-101.70 1/20/2017MT-97.11 4/19/2019MT-97.10 1/18/2019MT-96.26 7/15/2016MT-96.20 4/16/2021MT-96.11 7/20/2018TC-85.20 4/17/2020TC-85.10 7/21/2017TC-83.20 1/17/2020TC-83.10 7/16/2021TC-81.22 7/16/2021TC-71.10 1/15/2021TC-52.20 10/18/2013TC-42.20 10/18/2013TC-41.20 4/17/2020TC-22.10 7/16/2021TC-21.21 4/17/2020HL-10.13 1/15/2021HL-30.11 COLUMBUS, OH 43215 1366 DUBLIN RD PHONE: (614) 850-4400 PHONE: (614) 395-9701 EMAIL: MABLACKSTONE@COLUMBUSFIBER.NET MATT BLACKSTONE DUBLINK DEVELOPMENT/FISHEL DUBLIN, OH 43016 6555 SHIER RINGS RD PHONE: (614)410-4734 EMAIL: MHUGHES@DUBLIN.OH.US MASON HUGHES PHONE: (614) 410-4631 EMAIL: KRICHARDSON@DUBLIN.OH.US KEN RICHARDSON, PE, PS CITY OF DUBLIN SANITARY/WATER/ENGINEERING: COLUMBUS, OHIO 43231 3550 JOHNNY APPLESEED CT PHONE: (614) 818-2109 EMAIL: MCHRISTMAN@NISOURCE.COM MARK CHRISTMAN (UTILIQUEST) COLUMBIA GAS OF OHIO GAHANNA, OHIO 43230 700 MORRISON RD PHONE: (614) 883-7832 EMAIL: DAHARRIS@AEP.COM DEBRA HARRIS AEP OHIO (USIC) ITEM 604-RIGHT OF WAY MONUMENTS, A.P.P. ITEM 604 - CURB INLET MANHOLE ADJUSTED TO GRADE, A.P.P. ITEM 604 - CATCH BASIN RECONSTRUCTED TO GRADE, A.P.P. ITEM 604 - CATCH BASIN ADJUST TO GRADE, A.P.P. TP = TREE PROTECTION C&G = CURB AND GUTTER WV = WATER VALVE TR = TO REMAIN TBRR = TO BE REMOVED AND RELOCATED TBR = TO BE REMOVED RTG = RECONSTRUCT TO GRADE ATG = ADJUST TO GRADE P:\PR58074\FRA\000000\Design\Roadway\Sheets\GG001.dgn Sheet 5/6/2022 5:10:24 PM jkelley66 NJL 4/7/22 58074 JMK NJL NONE SUMMARY GENERAL 6 6 MSLBRIDGE REPLACEMENTSHAWAN FALLS DRIVEGENERAL SUMMARY SPECIFICATIONS. CITY OF COLUMBUS CONSTRUCTION AND MATERIAL (LATEST EDITION). ALL OTHER ITEMS REFERENCE CONSTRUCTION AND MATERIAL SPECIFICATIONS DENOTES OHIO DEPARTMENT OF TRANSPORTATION* ITEM DESCRIPTION TOTAL UNIT ITEM DESCRIPTION TOTAL UNIT PAVEMENT ROADWAY 253 FULL DEPTH PAVEMENT REPAIR 19 SY 201 STUMP REMOVED (18" SIZE)1 EA 254 1.25" PAVEMENT PLANING 776 SY 201 STUMP REMOVED (30" SIZE)1 EA 301 6" BITUMINOUS AGGREGATE BASE (TWO COURSES OF 3")206 TON 201 CLEARING AND GRUBBING 1 LUMP 301 3" BITUMINOUS AGGREGATE BASE 24 TON 202 CONCRETE CURB REMOVED AND DISPOSED OF 44 LF 304 6" AGGREGATE BASE (ROADWAY)103 CY 202 CONCRETE CURB & GUTTER REMOVED AND DISPOSED OF 816 LF 304 6" AGGREGATE BASE (DRIVEWAYS)48 CY 202 PAVEMENT REMOVED AND DISPOSED OF (ASPHALT)1140 SY 407*TRACKLESS TACK COAT 179 GAL 202 SIDEWALK REMOVED AND DISPOSED OF (CONCRETE)1094 SF 441 VARIABLE DEPTH (1.25" TO 6") ASPHALT CONCRETE SURFACE COURSE TYPE 1, (448), PG. 64-22 MT 36 TON 202 PIPE REMOVED AND DISPOSED OF, 24" AND UNDER 84 LF 441 1.25" ASPHALT CONCRETE SURFACE COURSE TYPE 1, (448), PG. 64-22 MT 124 TON 202 FENCE REMOVED 26 LF 441 1.5" ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG. 64-22 MT 10 TON 203 EXCAVATION 103 CY 441 1.75" ASPHALT CONCRETE INTERMEDIATE COURSE TYPE 2, (448), PG. 64-22 MT 102 TON 203 EMBANKMENT, A.P.P.345 CY 499 10" CONCRETE (COC 6)150 SY 204 SUBGRADE COMPACTION 896 SY 608 4" CONCRETE WALK (INCLUDING NO. 57 AGG. BASE)3667 SF 204 PROOF ROLLING 2 HOUR 608 CURB RAMPS 9 EA 204 EXCAVATION OF SUBGRADE 30 CY 608 DETECTABLE WARNING PANELS, A.P.P. 92 SF 204 GRANULAR EMBANKMENT, NO. 2 STONE 30 CY 609 6" CONCRETE COMBINATION CURB AND GUTTER (INCLUDING NO. 57 AGG. BASE)720 LF 604 RIGHT OF WAY MONUMENTS, A.P.P.11 EA 609 CURB, STRAIGHT 18" (INCLUDING NO. 57 AGG. BASE)402 LF 606 GUARDRAIL, TYPE MGS, A.P.P.97 LF SIGNALS* 606 ANCHOR ASSEMBLY, MGS TYPE E 1 EA 625 CONNECTION, FUSED PULL APART 8 EACH 606 ANCHOR ASSEMBLY, MGS TYPE E, A.P.P.1 EA 625 CONNECTION, UNFUSED PULL APART 4 EACH 606 ANCHOR ASSEMBLY, MGS TYPE T, A.P.P.1 EA 625 NO. 4 AWG 600 VOLT DISTRIBUTION CABLE, AS PER PLAN 1476 FT 606 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1, A.P.P.3 EA 625 NO. 10 AWG POLE AND BRACKET CABLE 618 FT 607*FENCE, TYPE CHAIN LINK 41 LF 625 BRACKET ARM, 6', AS PER PLAN 4 EACH 653 TOPSOIL FURNISHED AND PLACED, A.P.P. (T=4")152 CY 625 CONDUIT, 2", 725.04 235 FT 659 SEEDING AND MULCHING, A.P.P.1366 SY 625 CONDUIT, 3", 725.04 130 FT 659 REPAIR SEEDING AND MULCHING, A.P.P 500 SY 625 CONDUIT, JACKED OR DRILLED, 725.04, 3"868 FT 659 COMMERCIAL FERTILIZER 0.18 TON 625 CONDUIT, JACKED OR DRILLED, 725.051, AS PER PLAN, 6"868 FT 659 WATER 7 MGAL 625 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER PLAN, TYPE III, 110 WATT, AS PER PLAN 4 EACH SPECIAL PROOF SURVEY 1 LUMP 625 TRENCH, AS PER PLAN 136 FT 625 PULL BOX, 725.07, 18", AS PER PLAN 3 EACH STORM SEWER 625 PULL BOX, 725.08, 32", AS PER PLAN 3 EACH 604 CATCH BASIN ADJUSTED TO GRADE, A.P.P.1 EA 625 PULL BOX, MISC.: 725.08, 27", AS PER PLAN 2 EACH 604 CATCH BASIN RECONSTRUCTED TO GRADE, A.P.P.1 EA 625 GROUND ROD, AS PER PLAN 6 EACH 604 CURB INLET MANHOLE ADJUSTED TO GRADE, A.P.P.2 EA 630 SIGN HANGER ASSEMBLY, MAST ARM MOUNTED, AS PER PLAN 4 EACH 605 4" PIPE UNDERDRAIN (INCLUDING NO. 57 AGGREGATE)726 LF 625 UNDERGROUND WARNING/MARKING TAPE 127 FT 901 12" STORM SEWER PIPE, 706.02, WITH TYPE 1 BEDDING 72 LF 630 SIGN ATTACHMENT ASSEMBLY, MAST ARM 4 EACH SPECIAL CONCRETE FLARED END SECTION 1 EA 630 SIGN SUPPORT ASSEMBLY, POLE MOUNTED, AS PER PLAN 8 EACH SPECIAL DRAIN LEADER PIPE 80 FT 630 SIGN, FLAT SHEET (TRAFFIC SIGNALS)47 SF SPECIAL CURB CAN HOLES 4 EA 630 SIGN, STREET NAME, SINGLE FACED, ILLUMINIATED, AS PER PLAN 4 EACH 632 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, 1-WAY, POLYCARBONATE, AS PER PLAN 8 EACH WATER 632 VEHICULAR SIGNAL HEAD, (LED), 4-SECTION, 12" LENS, 1-WAY, POLYCARBONATE, AS PER PLAN 1 EACH 801 6" WATER PIPE AND FITTINGS 7 LF 632 VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 12" LENS, 1-WAY, POLYCARBONATE, AS PER PLAN 3 EACH 801 8" WATER PIPE AND FITTINGS 144 LF 632 PEDESTRIAN SIGNAL HEAD (LED), TYPE D2, COUNTDOWN, AS PER PLAN 6 EACH 801 6-INCH VALVE AND APPURTENANCES 1 EA 632 COVERING OF VEHICULAR SIGNAL HEAD 12 EACH 802 8-INCH VALVE AND APPURTENANCES 2 EA 632 COVERING OF PEDESTRIAN SIGNAL HEAD 6 EACH 808 8" WATER MAIN ABANDONED 1 EA 632 PEDESTRIAN PUSHBUTTON, AS PER PLAN 6 EACH 809 FIRE HYDRANT 1 EA 632 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG, AS PER PLAN 1351 FT SPECIAL SURVEY COORDINATES 1 LS 632 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG, AS PER PLAN 1567 FT 632 SIGNAL CABLE, 9 CONDUCTOR, NO. 14 AWG, AS PER PLAN 502 EACH EROSION CONTROL 632 SIGNAL SUPPORT FOUNDATION, AS PER PLAN 4 EACH 207 WATTLES 350 LF 632 PEDESTAL FOUNDATION, AS PER PLAN 2 EACH 207 INLET PROTECTION 3 EA 632 LOOP DETECTOR LEAD-IN CABLE, 2 CONDUCTOR, NO. 14 AWG 1324 FT 655 TREE PROTECTION DURING CONSTRUCTION 1 LUMP 632 POWER CABLE, 3 CONDUCTOR, NO. 6 AWG, AS PER PLAN 40 FT 632 SIGNALIZATION, MISC.: RELOCATION OF ITS ITEMS 1 LS P:\PR58074\FRA\000000\Design\Roadway\Sheets\GG001.dgn Sheet 5/6/2022 5:10:24 PM jkelley66 NJL 4/7/22 58074 JMK NJL NONE SUMMARY GENERAL 7 7 MSLBRIDGE REPLACEMENTSHAWAN FALLS DRIVE GENERAL SUMMARY SPECIFICATIONS. CITY OF COLUMBUS CONSTRUCTION AND MATERIAL (LATEST EDITION). ALL OTHER ITEMS REFERENCE CONSTRUCTION AND MATERIAL SPECIFICATIONS DENOTES OHIO DEPARTMENT OF TRANSPORTATION* ITEM DESCRIPTION TOTAL UNIT ITEM DESCRIPTION TOTAL UNIT 632 POWER SERVICE, AS PER PLAN 1 EACH 632 POWER METER CABINET, BASE MOUNT, WITH FOUNDATION, AS PER PLAN 1 EACH MAINTENANCE OF TRAFFIC* 632 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 4, AS PER PLAN 2 EACH 614 MAINTAINING TRAFFIC, AS PER PLAN 1 LUMP 632 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 13, AS PER PLAN 1 EACH 614 LAW ENFORCEMENT OFFICER WITH PATROL CAR, A.P.P.100 HOUR 632 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 14, AS PER PLAN 1 EACH 614 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS, (UNIDIRECTIONAL)1 EA 632 PEDESTAL, 11', TRANSFORMER BASE, AS PER PLAN 1 EACH 614 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS, (BIDIRECTIONAL)2 EA 632 PEDESTAL, MISC.: 19', TRANSFORMER BASE, AS PER PLAN 1 EACH 614 BARRIER REFLECTOR, TYPE 1, BIDIRECTIONAL 17 EA 632 REMOVAL OF TRAFFIC SIGNAL INSTALLATION, AS PER PLAN 1 EACH 614 OBJECT MARKER, TWO-WAY 17 EA 633 CABINET FOUNDATION, AS PER PLAN 1 EACH 614 WORK ZONE CENTER LINE, CLASS I, 642 PAINT 0.17 MILE 633 CONTROLLER WORK PAD, AS PER PLAN 1 EACH 614 WORK ZONE EDGE LINE, CLASS I, 642 PAINT 0.37 MILE 633 UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 WATT, AS PER PLAN 1 EACH 614 WORK ZONE CHANNELIZING LINE, CLASS I, 8", 642 PAINT 88 FT 633 CONTROLLER ITEM, MISC.: CONTROLLER UNIT, TYPE TS2/A2 WITH CABINET, TYPE TS1, AS PER PLAN 1 EACH 614 WORK ZONE DOTTED LINE, CLASS I, 642 PAINT 310 FT 633 EMERGENCY VEHICLE PREEMPTION, AS PER PLAN 1 EACH 614 WORK ZONE STOP LINE, CLASS I, 642 PAINT 70 FT 816 VIDEO DETECTION SYSTEM, AS PER PLAN 1 EACH 615 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER PLAN 377 SY 616 WATER 1 MGAL TRAFFIC CONTROL*622 PORTABLE BARRIER, UNANCHORED 529 FT 630 SIGN, FLAT SHEET, AS PER PLAN 15 SF 622 PORTABLE BARRIER, ANCHORED 160 FT 630 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL 7 EA 630 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSAL 6 EA 644 CENTERLINE, 4"0.05 MILE INCIDENTALS 644 EDGE LINE, 4"0.1 MILE 623 CONSTRUCTION LAYOUT STAKES 1 LUMP 644 CHANNELIZING LINE, 8"187 LF 624 MOBILIZATION 1 LUMP 644 STOP LINE, 24"31 LF 644 CROSSWALK LINE, 12"120 LF 644 CHEVRON MARKING, 12"25 LF 644 LANE ARROW, 96"3 EA BRIDGE 202 STRUCTURE REMOVED, AS PER PLAN 1 LUMP 503 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN 1 LUMP 503 UNCLASSIFIED EXCAVATION INCLUDING ROCK 626 CY 509 EPOXY COATED REINFORCING STEEL 26748 LB 510 DOWEL HOLES WITH CEMENT GROUT 192 EA 511 CLASS COC 2 CONCRETE, SUPERSTRUCTURE 68 CY 511 CLASS COC 1 CONCRETE, ABUTMENT NOT INCLUDING FOOTING 106 CY 511 CLASS COC 1 CONCRETE, FOOTING 108 CY 511 CLASS COC 2 CONCRETE, SIDEWALK 11 CY 512 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE)227 SY 512 TYPE 2 WATERPROOFING 21 SY 515 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEMBERS, LEVEL 1, CB17-36 (44'-0" LENGTH)1 EA 515 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEMBERS, LEVEL 1, CB17-48 (44'-0" LENGTH)12 EA 516 1/2" PREFORMED EXPANSION JOINT FILLER 28 SF 516 2" PREFORMED EXPANSION JOINT FILLER 95 SF 516 SEMI-INTEGRAL ABUTMENT EXPANSION JOINT SEAL 131 FT 516 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LOAD PLATE (NEOPRENE) (15/16" THICK)52 EA 517 RAILING, MISC.: MODIFIED TST-1-99 RAILING 196 FT 518 POROUS BACKFILL WITH GEOTEXTILE FABRIC 77 CY 518 SPECIAL - STEEL DRIP STRIP 46 FT 518 6" PERFORATED CORRUGATED PLASTIC PIPE 139 FT 518 6" NON-PERFORATED CORRUGATED PLASTIC PIPE INCLUDING SPECIALS 9 FT 526 REINFORCED CONCRETE APPROACH SLABS (T=13"), AS PER PLAN 230 SY 526 TYPE A INSTALLATION 125 FT 601 ROCK CHANNEL PROTECTION, TYPE C WITH FABRIC FILTER 75 CY 613 LOW STRENGTH MORTAR BACKFILL (TYPE 2)10 CY SPECIAL PROTECTION OF UTILITIES 1 LUMP SPECIAL RELOCATION OF EXISTING STONE WALL 1 LUMP NJL 66 4/7/22 58074 P:\PR58074\FRA\000000\Design\Roadway\Sheets\GY001.dgn Sheet 5/6/2022 5:10:26 PM jkelleyJMK NJL MSL NONE REPLACEMENT BRIDGE SHAWAN FALLS TYPICAL SECTIONS 8 8 BRIDGE REPLACEMENTSHAWAN FALLS DRIVE 1 2 3 4 5 0.016 0.016 7 7 6 PROFILE GRADE MAX2:1 6 1 2 3 4 5 0.016 0.016 PROFILE GRADE A 7 STA.102+98.59 TO STA. 103+41.00 6" 2'2' 9 9 10 12 12 \ CONST. SHAWAN FALLS DRIVE 6MAX2:1 2' STA. 102+38.04 TO STA. 103+41.00 STA. 100+88.60 TO STA. 101+51.94 (SEE INTERSECTION DETAIL) NORMAL CROWN PROPOSED SHAWAN FALLS DRIVE *2' \ CONST. SHAWAN FALLS DRIVE SLAB SEE SHEET ON APPROACH FOR WALK DETAILS 47 D 12 B C E A B C DSTA. 101+33.91 TO STA. 101+52.81 STA. 101+52.81 TO STA. 101+53.41 STA. 102+11.03 TO STA. 102+18.27 STA. 101+62.90 TO STA. 101+70.83 E STA. 101+70.83 TO STA. 101+82.36 STA. 102+28.46 TO STA. 102+48.31 K L M N O P Q R 10.00' 24.00' TO 10.00' 24.00' 10.00' 12.00' TO 10.00' 12.00' K L M N O STA. 102+38.04 TO STA. 102+70.29 STA. 102+70.29 TO STA. 103+20.29 STA. 103+20.29 TO STA. 103+41.00 STA. 102+38.04 TO STA. 102+70.29 STA. 102+70.29 TO STA. 103+20.29 P STA. 103+20.29 TO STA. 103+41.00 Q STA. 102+48.31 TO STA. 102+53.52 R STA. 102+53.52 TO STA. 103+03.46 S 0.00' S STA. 103+03.46 TO STA. 103+41.00 3.50' 3.50' TO 1.50' 7'-3.5" STA. 101+99.51 TO STA. 102+11.03 0.0160.016 11 3:1 MAX 4 :1 MAX 1 LEGEND 2 3 4 5 6 7 8 A B 9 C 10 11 12 EXISTING GUARDRAIL EXISTING CURB AND GUTTER EXISTING BASE EXISTING ASPHALT CONCRETE D 13 14 15 SEE SHEET OF FOR ADDITIONAL INFORMATION MEASURED ALONG \ CONST. SHAWAN FALLS DRIVE STA. 102+18.04 TO STA. 102+38.04 STA. 101+51.94 TO STA. 101+71.94 APPROACH SLAB PROPOSED SHAWAN FALLS DRIVE 47 66 MEASURED ALONG TOE OF CURB MEASURED ALONG BACK OF CURB/FACE OF WINGWALL 0.016 ** 103+08.59 TO 8.33% FROM STA.102+98.59 TO STA. **TRANSITION GUTTER SLOPE FROM 1.6% TRANSITION GUTTER PAN SLOPE FROM 1.6% AT STA. 102+22.15 TO 5.56% AT STA. 102+23.15 * TRANSITION GUTTER PAN WIDTH FROM 3.45' AT STA. 102+22.15 TO 1.50' AT STA. 102+60.74 28.00' TO 29.87' 28.00' 27.24' TO 28.00' 17.83' TO 16.00' 16.00' 8 SURFACE COURSE TYPE 1, (448), PG64-22 MT ITEM 441 - VARIABLE DEPTH (1.25" TO 6") ASPHALT CONCRETE ITEM 254 - 1.25" PAVEMENT PLANING NOT USED ITEM 606 - GUARDRAIL, TYPE MGS, A.P.P. ITEM 608 - 4" CONCRETE WALK (INCLUDING NO. 57 AGG. BASE) ITEM 609 - CURB, STRAIGHT 18" (INCLUDING NO. 57 AGG. BASE) (INCLUDING NO. 57 AGG. BASE) ITEM 609 - 6" CONCRETE COMBINATION CURB AND GUTTER ITEM 407 - TRACKLESS TACK COAT (ODOT) ITEM 605 - 4" PIPE UNDERDRAIN (INCLUDING NO. 57 AGGREGATE) ITEM 659 - SEEDING AND MULCHING, A.P.P. ITEM 204 - SUBGRADE COMPACTION ITEM 304 - 6" AGGREGATE BASE (ROADWAY) 3") ITEM 301 - 6" BITUMINOUS AGGREGATE BASE (TWO COURSES OF TYPE 2, (448), PG. 64-22 MT ITEM 441 - 1.75" ASPHALT CONCRETE INTERMEDIATE COURSE (448), PG64-22 MT ITEM 441 - 1.25" ASPHALT CONCRETE SURFACE COURSE TYPE 1, NJL 66 4/7/22 58074 P:\PR58074\FRA\000000\Design\Roadway\Sheets\GY001.dgn Sheet 5/6/2022 5:10:27 PM jkelleyJMK NJL MSL NONE REPLACEMENT BRIDGE SHAWAN FALLS TYPICAL SECTIONS 9 9 BRIDGE REPLACEMENTSHAWAN FALLS DRIVE 15 A 7 2' 9 C D \ CONST. SHAWAN FALLS DRIVE 2' 10.00'10.00' B STA.103+41.00 TO STA. 103+65.18 RESURFACING PROPOSED SHAWAN FALLS DRIVE 6 0.0160.016 11 3:1 MAX3:1 M AX 14 0.0163:1 M AX 7 9 2' 0.0163:1 M AX C 2' STA. 104+80.00 TO 105+45.76 7 9 2' STA. 106+28.17 TO 106+33.00 A C \ CONST. SHAWAN FALLS DRIVE B 0.016`0.016` 10' (TYP.)10' (TYP.) VAR IES VAR IES STA. 103+65.18 TO 106+33.00 SIDEWALK PROPOSED SHAWAN FALLS DRIVE \ CONST. SIDEWALK \ CONST. SIDEWALK 6 6116 6116 3 :1 MAX 6 0.016 0.016 LEGEND A B C EXISTING GUARDRAIL EXISTING CURB AND GUTTER EXISTING BASE EXISTING ASPHALT CONCRETE D 8 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 114 8 SURFACE COURSE TYPE 1, (448), PG64-22 MT ITEM 441 - VARIABLE DEPTH (1.25" TO 6") ASPHALT CONCRETE ITEM 254 - 1.25" PAVEMENT PLANING NOT USED ITEM 606 - GUARDRAIL, TYPE MGS, A.P.P. ITEM 608 - 4" CONCRETE WALK (INCLUDING NO. 57 AGG. BASE) ITEM 609 - CURB, STRAIGHT 18" (INCLUDING NO. 57 AGG. BASE) (INCLUDING NO. 57 AGG. BASE) ITEM 609 - 6" CONCRETE COMBINATION CURB AND GUTTER ITEM 407 - TRACKLESS TACK COAT (ODOT) ITEM 605 - 4" PIPE UNDERDRAIN (INCLUDING NO. 57 AGGREGATE) ITEM 659 - SEEDING AND MULCHING, A.P.P. ITEM 204 - SUBGRADE COMPACTION ITEM 304 - 6" AGGREGATE BASE (ROADWAY) 3") ITEM 301 - 6" BITUMINOUS AGGREGATE BASE (TWO COURSES OF TYPE 2, (448), PG. 64-22 MT ITEM 441 - 1.75" ASPHALT CONCRETE INTERMEDIATE COURSE (448), PG64-22 MT ITEM 441 - 1.25" ASPHALT CONCRETE SURFACE COURSE TYPE 1, NJL 66 4/7/22 58074 JMK NJL MSL NONE REPLACEMENT BRIDGE SHAWAN FALLS TYPICAL SECTIONS 10 10 P:\PR58074\FRA\000000\Design\Roadway\Sheets\GY001.dgn Sheet 5/6/2022 5:10:28 PM jkelleyBRIDGE REPLACEMENTSHAWAN FALLS DRIVEA B 0.016` A B 0.016`0.016` C CC C 27.9'16.8' 10'10' \ CONST. SHAWAN FALLS DRIVE \ CONST. SHAWAN FALLS DRIVE STA. 100+88.60 TO 101+51.94 EXISTING TYPICAL SECTION SHAWAN FALLS DRIVE STA. 102+38.04 TO 103+41.00 EXISTING TYPICAL SECTION SHAWAN FALLS DRIVE 0.016` LEGEND A B C EXISTING GUARDRAIL EXISTING CURB AND GUTTER EXISTING BASE EXISTING ASPHALT CONCRETE D 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 SURFACE COURSE TYPE 1, (448), PG64-22 MT ITEM 441 - VARIABLE DEPTH (1.25" TO 6") ASPHALT CONCRETE ITEM 254 - 1.25" PAVEMENT PLANING NOT USED ITEM 606 - GUARDRAIL, TYPE MGS, A.P.P. ITEM 608 - 4" CONCRETE WALK (INCLUDING NO. 57 AGG. BASE) ITEM 609 - CURB, STRAIGHT 18" (INCLUDING NO. 57 AGG. BASE) (INCLUDING NO. 57 AGG. BASE) ITEM 609 - 6" CONCRETE COMBINATION CURB AND GUTTER ITEM 407 - TRACKLESS TACK COAT (ODOT) ITEM 605 - 4" PIPE UNDERDRAIN (INCLUDING NO. 57 AGGREGATE) ITEM 659 - SEEDING AND MULCHING, A.P.P. ITEM 204 - SUBGRADE COMPACTION ITEM 304 - 6" AGGREGATE BASE (ROADWAY) 3") ITEM 301 - 6" BITUMINOUS AGGREGATE BASE (TWO COURSES OF TYPE 2, (448), PG. 64-22 MT ITEM 441 - 1.75" ASPHALT CONCRETE INTERMEDIATE COURSE (448), PG64-22 MT ITEM 441 - 1.25" ASPHALT CONCRETE SURFACE COURSE TYPE 1, TPTPTP TPP.I. Sta. 102+68.33 ¬ R = 200.00' T = 17.50' L = 34.91' E = 0.76' C = 34.86'12"12"2IN2IN2IN24IN16IN8IN12IN32IN18IN2IN4IN18IN3IN2IN2IN10IN12IN2IN2IN2IN2IN10IN6IN18IN99 100 PI Sta. 100+76.19101 102 PC St a. 102+50.84PT Sta. 102+85.74103 ¬ = 3°58'37"10 2012021" = 20' NJL 66 4/7/22 58074 JMK 11 11 NJL MSLBRIDGE REPLACEMENTSHAWAN FALLS DRIVEP:\PR58074\FRA\000000\Design\Roadway\Sheets\GP001.dgn Sheet 5/6/2022 5:10:31 PM jkelleySTA. 103+65.18 TO BEGIN PROJECT REPLACEMENT BRIDGE SHAWAN FALLS PLAN VIEW 101 102 103 104 835 840 845 850 855 860 835 840 845 850 855 860 865 865 SAWCUTW BRIDGE STREETSHAWAN FALLS DRIVE CONST. LIMITS STA. 102+48.64, 16.17' RT BEGIN SHOULDER TAPER PROP. RIM = 854.43 EX. RIM = 584.11 ADJUST TO GRADE EX. CURB INLET MANHOLE SEE PROFILE BELOW ADJUST TO GRADE EX. CURB INLET MANHOLE SAWCUT SAWCUT STA. 101+70.77, 15.50' RT BEGIN SHOULDER TAPER STA. 101+82.20, 15.50' RT END SHOULDER TAPER STA. 101+52.81, 28.00' LT END SHOULDER TAPER 97 ° 5 0' 29 " A A DUBLIN, OH 43017 220 W. BRIDGE ST. AN OHIO LIMITED LIABILITY COMPANY 220 W BRIDGE ST, LLC, DUBLIN, OH 43017 250 W. BRIDGE ST. OHIO NOT-FOR-PROFIT CORPORATION OHIOHEALTH CORPORATION, AN (APROXIMATE LOCATION) DB 2809 PAGE 303 20' WIDE SEWER EASEMENT A EX. 3" GAS (TBRR)EX. UG TELECOM (DND)EX. MH (DND) B C C 12.00' RT STA. 103+65.18, END AA, TYPE TD EX. GR (TBR) EX. GR (TBR) MGS TYPE GR, 31.06' LT STA. 102+51.40, RAMP TYPE E EX. GR THEN CONNECT TO 48.04' LT STA. 101+02.75, BEGIN AA, TYPE E STA. 101+14.40, 26.46' LT BEGIN SHOULDER TAPER BEGIN STRAIGHT CURB END CURB & GUTTER 9.1' 8.5' 9.0'10.0'10.0'24.0'12.0' STA. 102+70.29, 12.00' RT BEGIN PAVEMENT TAPER STA. 103+20.29, 12.00' LT END PAVEMENT TAPER STA. 102+70.29, 24.00' LT BEGIN PAVEMENT TAPER STA. 103+20.29, 10.00' RT END PAVEMENT TAPER A DND +43.04STA. 101+51.94 BEGIN APPROACH SLAB STA. 102+38.04 END APPROACH SLAB GAS (DND) EX. 4"MATCH LINE STA. 103+65.18SEE SHEET12STA. 100+88.60 BEGIN PROJECT FALLS DRIVE \ CONST. SHAWAN I NDI AN RUNS OUTH F ORK CURVE DATA - SHAWAN FALLS D TYPE E CURB RAMP | DRIVE 1 BRIDGE STREET \ CONST. W CURB RAMP TYPE C CURB RAMP TYPE C CURB RAMP TYPE C CURB RAMP TYPE C CURB RAMP TYPE C 64.89' RT STA. 99+47.08, BEGIN WALK BEGIN WORK 41.93' LT STA. 200+92.90, BEGIN C&G 39.77' RT STA. 99+59.27, BEGIN C&G 24.50' LT STA. 99+74.85, BEGIN C&G 31.61' LT STA. 100+01.40, END C&G 30.55' LTSTA. 99+69.96, BEGI N WALK4.0' 56.67' RT STA. 202+53.20, END WALK 37.64' RT 202+49.26, END C&G 36.00' RT 202+34.80 BEGIN C&G 44.00' LT 202+39.80 BEGIN WALK(DND)(DU0008_009) WATER EX. 16" SEE SHEET OF PROP. 8" WM 51 66 (TBR) (DU0085_002)EX. 8" WATER THIS SHEET SEE NOTE ON TBR 3 7 . 0'R100 STA. 101+79.28, 12.00' RT END PAVEMENT TAPER (TO REMAIN) EX. UG TELECOM STA. 102+98.64, 12.37' RT BEGIN CURB & GUTTER END STRAIGHT CURB END SHOULDER TAPER G PROP. 12" (N) 851.55 EX 12" (NW) 848.33 (TBR) PROP. RIM = 856.14 EX. RIM = 854.43 RECONSTRUCT TO GRADE STA. 101+13.68, 28.28' RT EX. CB-3A PROP. 12" (S) 850.00 STA. 101+85.77, 21.00' RT CONCRETE FLARED END SECTION DU0085-CIP_002 RECORD PLAN FOUND, SHOWN PER WATER VALVE NOT RESURFACING/OVERLAY PAVEMENT PLANING AND H I J STA. 101+67.87, 18.50' RT BEGIN PROP. CHAIN LINK FENCEH I J STA. 101+78.40, 26.50' RT BEGIN FENCE REMOVED STA. 102+02.16, 40.00' RT END PROPOSED CHAIN LINK FENCE END FENCE REMOVED 62.86' LT STA. 200+46.70 BEGIN CONCRETE WALK (DND)EX. 24" SANITARY EX. ROOF DRAINDRAINEX. ROOF E 29.41' LT STA. 101+09.75, RAMP TYPE D E 32.00' LT STA. 102+20.47, RAMP TYPE E (TBR) EX. SIGN F F G K L K STA. 102+65 OUTFALL TO NEW CURB RECONNECT ROOF DRAINS L STA. 103+31 OUTFALL TO NEW CURB RECONNECT ROOF DRAINS WATERLINE. SPACING AS NECESSARY TO AVOID GUARDRAIL POSTS. ADJUST POST WATERLINE PRIOR TO PLACING VERIFY LOCATION AND DEPTH OF NOTE: BEGIN PAVEMENT PLANING AND RESURFACING END FULL DEPTH PAVEMENT STA. 103+41.00 END PROJECT 1' FULL DEPTH PAVEMENT REPAIR 1' FULL DEPTH PAVEMENT REPAIR 1' FULL DEPTH PAVEMENT REPAIR 15.88' RT +62.45, END C+G PROP. HYDRANT B TP TP PROTECTION LIMITS TP = TREE P.V.I. STA 101+81.00 ELEV = 856.35' 100.00' VC K = 54 SSD = 633' P.V.I. STA 102+91.00 ELEV = 853.88' -2.25 % 100.00' VC K = 40 EX. 12" STM (TBR) EX. 24" SANITARY (DND) EX. FO (DND) EX. 16" WM EX. +0.12 %856.88856.79856.50856.02847.19854.72854.06854.03854.09854.76-0.40 % -2.25 % +0.23 %856.68856.58856.44856.20855.84855.36854.81854.38854.11853.99854.0212 STA. 100+88.60ELEV. = 856.72SHAWAN FALLS DRIVEBEGIN PROFILE SEE SIDEWALK PROFILE, SHEET STA. 103+65.18, ELEV. = 854.05 END PROFILE SHAWAN FALLS DRIVE EX. 12" (W) 850.56 EX. 12" (E) 849.56 PROP. RIM ELEV 854.43 EX. RIM ELEV 854.16 EX CI-MH, AJUST TO GRADE STA 103+40.25, 11.50' LT EXISTING GROUND SHAWAN FALLS DRIVE PROPOSED PROFILE GRADE TPTPTP TP P.I. Sta. 105+51.77 ¬ R = 365.00' T = 105.17' L = 204.79' E = 14.85' C = 202.11' 104 PC Sta. 104+46.60105 106PT Sta. 106+51.3910 7 10 8PC Sta. 10+81.4210 11 121" = 20' NJL 66 4/7/22 58074 JMK NJL MSL END PROJECT TO STA. 103+65.18 REPLACEMENT BRIDGE SHAWAN FALLS PLAN VIEW P:\PR58074\FRA\000000\Design\Roadway\Sheets\GP002.dgn Sheet 5/6/2022 5:10:33 PM jkelley12 12 BRIDGE REPLACEMENTSHAWAN FALLS DRIVE840 845 850 855 860 840 845 850 855 860 865 865 A CURVE DATA - SHAWAN FALLS A MATCH LINE STA. 103+65.1811SEE SHEET10 11 12 | DRIVE 3| DRIVE 2 | DRIVE 489°58'28"9 2 °5 6'10" 90°0'0"10.0'10.0'FALLS DRIVE \ CONST. SHAWAN SIDEWALK \ CONST. \ CONST. SHAWAN FALLS DRIVE STA. 106+28.08 \ CONST. SIDEWALK STA. 12+74.83 = END WALK 8.29'29.81'7.15'2 0'R20'R+77.21+50.06+81.507'10'5'STA. 106+18.00BEGIN C&G75.76' RT +12.88, 75.48' RT +19.19, SEE DETAIL 1 CURB RAMP TYPE C DETAIL 1 ID | STATION | OFFSET 2 106+25.50 1 106+25.50 12.00' LT 12.00' RT TYPE CURB RAMP TYPE C TYPE C | CURB RAMP 5.0'7.0'5.5'5.0'5.0'5.5'5.0' 2 1 2" WT (C) 650 SHAWAN FALLS DR. WITH AT&T TO COORDINATE (ATG), CONTRACTOR AT&T MANHOLE 10 103+65.18 FALLS DRIVE STA. \ CONST. SHAWAN STA. 10+00.00 = \ CONST. SIDEWALK BEGIN WALK PROFILE EX. SIGN (DND) (TO REMAIN) (DU0085_002) EX. 8" WATER EX. ROOF DRAIN EX. ROOF DRAIN BY OTHERS) AND RELOCATED (TO BE REMOVED AT&T PEDESTAL (TO REMAIN) AT&T PEDESTAL STA. 106+33.00, 10' LT, 10' RT END CURB & GUTTER END PAVEMENT PLANING AND RESURFACING END WORK BOX TO PROPOSED GRADE ADJUST WATER VALVE SHOWN FROM PLANS VALVE NOT VISIBLE, A STA. 104+90 OUTFALL TO NEW CURB RECONNECT ROOF DRAINS A B B STA. 105+54 OUTFALL TO NEW CURB RECONNECT ROOF DRAINS RESURFACING/OVERLAY PAVEMENT PLANING AND TP TP PROTECTION LIMITS TP = TREE +1.98 %`+1.97 %`+5.00 %`-0.57 %`-3.00 %` -4 .38 % ` -2.05 %`-0.83 %`P.V.I. STA 10+45.20ELEV = 855.63'P.V.I. STA 10+49.55ELEV = 855.67'P.V.I. STA 11+38.73ELEV = 857.63'P.V.I. STA 11+52.17ELEV = 857.55'P.V.I. STA 11+82.17ELEV = 856.65'P.V.I. STA 10+23.03ELEV = 854.58'P.V.I. STA 10+73.92ELEV = 855.06'P.V.I. STA 10+96.22ELEV = 855.50'P.V.I. STA 12+12.52ELEV = 855.32'P.V.I. STA 12+34.01ELEV = 854.88'22.21' 22.30' 21.49' DRIVE 2 DRIVE 3 DRIVE 4 GRADE EXISTING ELEV = 854.14'BEGIN SIDEWALK PROFILESTA. 10+00.82STA. 12+74.83ELEV = 854.54'END SIDEWALK PROFILEGRADE (BACK OF WALK) PROPOSED SIDEWALK PROFILE +4.74 %`-2.52 %`855.06AT&T COORDINATE WITH CONTRACTOR TO MANHOLE (ATG), +1.03%, AT&T PP007PP008PP016PP017PP018PP019PP020PP021PP022PP041PI105 855.08855.69856.94857.56856.86855.87855.06854.74854.67855.66855.43855.95856.03857.61856.05855.17 TPTPTP TPTPTP TP TPPI Sta. 100+76.19101 102 PC St a. 102+50.84PT Sta. 102+85.74103 104 PC Sta. 104+46.60105 106PT Sta. 106+51.39¬ = 3°58'37"PC Sta. 10+81.4210 11 12200845 84584585085085 0 850 850855855 855855855 855855 855 855855 8558558551" = 20' NJL 66 4/7/22 58074 JMK NJL MSL END PROJECT TO BEGIN PROJECT REPLACEMENT BRIDGE SHAWAN FALLS GRADING PLAN 13 13 BRIDGE REPLACEMENTSHAWAN FALLS DRIVEP:\PR58074\FRA\000000\Design\Roadway\Sheets\XG001.dgn Sheet 5/6/2022 5:10:36 PM jkelleySHAWAN FALLS DRIVEW BRIDGE STREETSTA. 100+82.47 BEGIN PROJECT 846'847'848'849'851'852'853'854' 845' 850' 854'854' 854'854' 854' 856' 857' 855'85 5 '853'854'855'854'856'857'855'856'856'856'856' 855'856'857'854' 856' 855 '855 '856'857' 855' 856' 857' 8 5 6'855' 853' 854'855'WATER EDGE EX. FO 850 ' 852 ' 854 '850'852' MH (ATG) EX. STORM STA. 103+41.00 END PROJECT EX. TELECOM BOX (TBR) EX. TELECOM BOX (TO REMAIN) EX. TELECOM MH (ATG) EX. SANITARY MH \ CONST. SHAWAN FALLS DRIVE EX. STORM MH (ATG) EX. SANITARY EX. FO EX. GAS EX. WATER (TBR)SOUTH FORK INDIAN RUNEX. GAS RELOCATE AS SHOWN) (REMOVE AS NECESSARY, EXISTING STONE WALL /1BRIDGE, SHEET PROPOSED GRADING UNDER NOTE: SEE BRIDGE PLANS FOR 24 1.460 ACRES INST. 201807310102242-1 A.P.N. 273-000786-00 DUBLIN, OH 43017 220 W. BRIDGE ST. AN OHIO LIMITED LIABILITY COMPANY 220 W BRIDGE ST, LLC, 2.1873 ACRES INST. 201803260038938 A.P.N. 273-000797-00 DUBLIN, OH 43017 250 W. BRIDGE ST. OHIO NOT-FOR-PROFIT CORPORATION OHIOHEALTH CORPORATION, AN 0.9616 ACRES INST. 199811170295482 A.P.N. 273-002485-00 DUBLIN, OH 43017 650 SHAWAN FALLS DR. BISCAR PROPERTIES, LLC(APROXIMATE LOCATION)DB 2809 PAGE 30320' WIDE SEWER EASEMENT23. TRAFFIC, SEE MOT SHEETS 18 - GRADING FOR MAINTENANCE OF INFORMATION. FOR TEMPORARY PROJECT GRADING THIS SHEET SHOWS FINAL TREE PROTECTION TREE PROTECTION TREE PROTECTION TREE PROTECTION EX. TELECOM BOX (TBR) STA. 106+33.00 END WORK EX. 6" ROOF DRAIN, QL "D"EX. 3" GAS, CITY OF DUBLIN, QL "C"EX. UNDERGROUND TELECOM, AT&T QL "C"102PC Sta. 102+50.84 12" EX. 6" ROOF DRAIN, QL "D"104EX. 6" ROOF DRAIN, QL "D"104PC Sta. 104+46.60 PP020EX. 6" SANITARY EX. 6" ROOF DRAIN, QL "D" EX . TELECOM , QL "D" EX . 6" ROO F DRA IN , QL "D"P:\PR58074\FRA\000000\Design\Roadway\Sheets\GD001.dgn Sheet 5/6/2022 5:10:38 PM jkelleyNJL 66 4/7/22 58074 JMK NJL MSLBRIDGE REPLACEMENTSHAWAN FALLS DRIVE 1" = 10' 14 14 REPLACEMENT BRIDGE SHAWAN FALLS DRIVE DETAIL106| DRIVE 1 | DRIVE 2 | DRIVE 3 | DRIVE 4 FALLS DRIVE \ CONST. SHAWAN FALLS DRIVE \ CONST. SHAWAN FALLS DRIVE \ CONST. SHAWAN FALLS DRIVE \ CONST. SHAWAN 97°50'29"90°0'0" 92°56'3"90°1'7" 7.35'13.89'17.28'10.00'10.07'11.10'31.68'31.02'5.81'7.77'33.47'30.06'6.63' 6.00'11.00'11.00'3.00'10.30'10.00'10.00'DRIVE 1 STA. 00+00.00 SHAWAN FALLS DRIVE STA. 102+43.04 = DRIVE 3 STA. 00+00.00 SHAWAN FALLS DRIVE STA. 104+50.06 = DRIVE 4 STA. 00+00.00 SHAWAN FALLS DRIVE STA. 105+81.50 = +39.24, 25.00' LT +60.36, 25.00' LT +89.67, 25.00' LT +70.85, 25.00' LT +66.12, 24.88' LT +88.21, 24.85' LT DRIVE 2 STA. 00+00.00 STA. 103+77.21 = SHAWAN FALLS DRIVE SAWCUT SAWCUT SAWCUT SAWCUT BEGIN STRAIGHT CURB BEGIN STRAIGHT CURB +70.73, 34.44' LT BEGIN STRAIGHT CURB +70.73, 34.44' LT BEGIN STRAIGHT CURB BEGIN STRAIGHT CURB BEGIN STRAIGHT CURB BEGIN STRAIGHT CURB BEGIN STRAIGHT CURB S71°13'34.9"W S89°04'04"W S89°36'40.1"W N 72°42'46"W ON SHEET NOTES: SEE DRIVE PROFILES 15 ELEV. 853.76` +04.96, 58.40' LT 853.77` +05.14, 59.38' LT ELEV. 854.35` +65.59, 47.49' LT ELEV. 854.36` +63.69, 48.48' LT A B C D E F G H I J K L A L = 6.95' R = 5.0' ¬ = 79°36'09.5" STA. 102+21.04, 50.34' LT B L = 23.54' R = 15.0' ¬ = 89°54'19.7" STA. 102+11.03, 43.00' LT C D L = 20.77' R = 15.0' ¬ = 79°19'17.7" 40.50' LT STA. 102+60.74, L = 9.45' R = 5.0' ¬ = 108°19'59.9" 44.60' LT STA. 102+51.82, E L = 7.90' R = 5.0' ¬ = 90°30'29.2" STA. 103+61.21, 33.99' LT F G L = 7.81' R = 5.0' ¬ = 89°29'30.8" STA. 103+93.21, 34.27' LT H L = 23.56' R = 15.0' ¬ = 90°00'00" STA. 103+51.21, 26.50' LT L = 23.56' R = 15.0' ¬ = 90°00'00" STA. 104+03.21, 26.50' LT ELEV. 857.01` +43.75, 38.83' LT ELEV. 857.03` +43.74, 39.83' LT ELEV. 856.69` +07.28, 39.40' LT ELEV. 856.71` +07.27, 40.40' LT ELEV. 855.77` +39.37, 32.36' LT ELEV. 855.86` +60.37, 32.15' LT I J K L L = 23.42' R = 15.0' ¬ = 89°27'23.9" STA. 104+24.31, 26.50' LT L = 22.57' R = 15.0' ¬ = 86°11'31.6" STA. 104+76.30, 25.37' LT L = 23.33' R = 15.0' ¬ = 89°05'45.3" STA. 105+56.91, 26.50' LT L = 21.88' R = 15.0' ¬ = 83°34'23.2" STA. 106+03.61, 26.50' LT DRIVE 1 - 250 W. BRIDGE STREET) DRIVE 3 - 650 SHAWAN FALLS DRIVE DRIVE 2 - 250 W. BRIDGE STREET DRIVE 4 - 650 SHAWAN FALLS DRIVE PAVEMENT PLANING AND RESURFACING 7.5' 10' TO TIE INTO APPROACH SLAB TAPER CURB AND GUTTER OVER +29.79, 27.08' LT +19.79, 27.57' LT ITEM 304 - 6" AGGREGATE BASE (DRIVEWAYS) ITEM 499 - 10" CONCRETE (COC 6) (DRIVEWAYS) ITEM 304 - 6" AGGREGATE BASE ITEM 301 - 3" BITUMINOUS AGGREGATE BASE COURSE TYPE 1 (448), PG. 64-22 MT ITEM 441 - 1.5" ASPHALT CONCRETE SURFACE P:\PR58074\FRA\000000\Design\Roadway\Sheets\GD002.dgn Sheet 5/6/2022 5:10:40 PM jkelleyNJL 66 4/7/22 58074 JMK NJL MSLBRIDGE REPLACEMENTSHAWAN FALLS DRIVE 1" = 10' 15 15 REPLACEMENT BRIDGE SHAWAN FALLS DRIVE PROFILES 845 850 855 854.88854.03854.62P.V.I. STA 0+27.37ELEV = 854.61'P.V.I. STA 0+36.88 ELEV = 854.71' +1.00 %-5 .50 % 10.00' VC K = 2 P.V.I. STA 0+49.21 ELEV = 854.03' -0.25 %` 5.00' VC K = 1854.04845 850 855 860 854.06856.80P.V.I. STA 0+12.00ELEV = 853.84'P.V.I. STA 0+19.00ELEV = 854.29'+6.41 %P.V.I. STA 0+24.00ELEV = 854.36'856.47854.50+1.56 % +13.05 % ` 845 850 855 860 854.77856.26P.V.I. STA 0+12.00ELEV = 854.75'P.V.I. STA 0+19.00ELEV = 855.20'P.V.I. STA 0+24.00ELEV = 855.28'855.73855.33+6.41 %+1.56 % +5.50 % ` 845 850 855 860 854.61P.V.I. STA 0+12.01ELEV = 854.63'P.V.I. STA 0+19.01ELEV = 855.01'P.V.I. STA 0+24.01ELEV = 855.09'855.42855.12+5.48 %+1.56 % +3.06 % ` DRIVE 1 DRIVE 3 DRIVE 2 DRIVE 4 0 +50 +500 +500+500 PROPOSED GRADE PROPOSED GRADE PROPOSED GRADE PROPOSED GRADE EXISTING GRADE EXISTING GRADE EXISTING GRADE EXISTING GRADE FALLS DRIVE \ CONST. SHAWAN DRIVE SHAWAN FALLS \ CONST. DRIVE SHAWAN FALLS \ CONST. DRIVE SHAWAN FALLS \ CONST. 8.35' SIDEWALK PROP. GRADE SHAWAN FALLS 99 100 PI Sta. 100+76.19101 102 202NJL 66 4/7/22 58074 XXX NJL XXXBRIDGE REPLACEMENTSHAWAN FALLS DRIVE W BRIDGE STREET DRIVE AND SHAWAN FALLS REPLACEMENT BRIDGE SHAWAN FALLS DETAIL INTERSECTION 16 16 1" = 10'P:\PR58074\FRA\000000\Design\Roadway\Sheets\GI001.dgn Sheet 5/6/2022 5:10:42 PM jkelley5.2'37. 0'R4.0' 6.1' 5.0' 8.5' 25. 0'R6.0' 6.0'8.0'8.5'5.0'5.5'15.1' 5.5' 5. 5' 5.6'4.5'4.2'5.0'R3.0'R3.9'4.1'5.5' 8.0'5.0'5.0'5.0'5.0'5.0'EDGE LINE EDGE LINE ¬ = 102° 58' 53" R = 20.00' L = 35.95'856.24856.50856.87857.51 ID | STATION | OFFSET 2 100+98.00 1 101+09.75 29.41' LT 33.04' RT TYPE CURB RAMP TYPE D TYPE C 1 SHAWAN FALLS DRIVE 856.19 855.98 856.58 856.19 EX. WALK 5.9' 856.14 L.P.24.00'12.00' +88.60 856.68 +0 1. 8 1 +94.13 +14.4026.46' LT24.00' LT 857.19` 856.72` 2 9 . 8 4' RT+79.2912.00' RT856.43+51.94+52.8128.00' LT\ CONST. SHAWAN FALLS DRIVE \ CONST. W BRIDGE STREET ¬ = 33° 59' 53" R = 47.00' L = 27.89' ¬ = 66° 12' 30" R = 45.00' L = 52.00' ¬ = 65° 04' 34" R = 40.00' L = 45.43' 2 3 4 5 6 +05.60 36.00' LT +20.2924.00' LT2.00' 7.88' 855.75`855.76` EX. WALK EX. WALK EX. WALK (TBR) EX. CURB RAMP EX. CURB RAMP (TBR) 3 202+16.42 38.00' LTTYPE C 4 202+35.25 46.22' RTTYPE C 5 53.63' RTTYPE C 6 28.61' LTTYPE C | CURB RAMP 99+73.44 99+90.21 Sta. 99+76.50, 71.47' Lt. = \ CONST. SHAWAN FALLS DRIVE Sta. 201+04.07, 87.58' Rt. \ CONST. E BRIDGE STREET Sta. 202+60.11, 81.31' Rt. \ CONST. E BRIDGE STREET Sta. 202+05.60, 76' Lt. \ CONST. E BRIDGE STREET STA. 200+93.26, 61.93' LT \ CONST. E BRIDGE STREET Sta. 101+20.29, 44' Lt. \ CONST. SHAWAN FALLS DRIVE Sta. 101+10.79, 68.82' Rt. \ CONST. SHAWAN FALLS DRIVE Sta. 99+39.70, 80.3' Rt. \ CONST. SHAWAN FALLS DRIVE 5.0' 6.0'R4.0'+24.39 35.50' LT 6.8'5.4'RAMP 1 856.81 856.67 856.82 856.68 857.38 857.24 857.18 857.28 7.0%1.56% 857.13` 857.05` 856.46` 856.50` +09.97 13.05' LT +62.45 15.88' RT +10.00 +10.00 26.93' RT +36.05 24.00' LT 856.15 856.64 856.46 856.14 856.0119.5' EDGE OF PAVEMENT ELEVATION/SAWCUT ELEVATION* ` = MATCH EXISTING5. H.P. = HIGH POINT; L.P. = LOW POINT4. FOR TOP OF CURB ELEVATION ADD 0.5' TO FACE OF CURB ELEVATION.3. OTHERWISE NOTED IN DETAILS. FOR FACE OF CURB ELEVATIONS, SUBTRACT 0.13' FROM EOP ELEVATION UNLESS 2. ALL CURB RETURN ELEVATIONS AT 10' INTERVALS UNLESS OTHERWISE MARKED. ALL BASELINE AND EOP ELEVATIONS AT 25' INTERVALS UNLESS OTHERWISE MARKED. 1. NOTES: +34.80, 36.00' LT *856.25`/856.26` *856.41`/856.41` *856.50`/856.50` H.P. 856.47` *856.46`/ *856 .42 `/856 .43 `*856.26`/856.27`*856.22`/856.23`+79.37, 44.07' RT*8 5 6.20/85 6.22 *8 56.18/8 5 6.20 8 5 6 . 1 8 * 8 5 6 . 1 6 / * 8 5 6. 9 4 `/ 8 5 6. 9 3 ` * 8 5 7.0 0`/8 57.0 0`856.88`*856.89` / 85 6.89`*857.07`/856.44`*856.43`/856.36`*856.36`/*856.50`/856.52`H.P.*856.61`/856.61`*856.59`/856.59` *856.52`/856.54` *856.38`/856.39` *857.66`/857.68` 856.62 856.75 856.85 856.79 856.89 856.99 857.42 856.99 857.13 857.12 857.27 RESURFACING PAVEMENT PLANING AND STA. 101+62.45 101+52.71 TO 1.6% FROM STA. FROM 8.33% TO GUTTER SLOPE TRANSITION 1.56% 1.56%EX. STONE WALL PROP. STONE WALL STA. 101+13.92 101+01.67 TO 1.6% FROM STA. FROM 8.33% TO GUTTER SLOPE TRANSITION 1' FULL DEPTH PAVEMENT REPAIR 1' FULL DEPTH PAVEMENT REPAIR PAVEMENT REPAIR 1' FULL DEPTH 100 PI Sta. 100+76.19101 102 PC St a. 102+50.84PT Sta. 102+85.74103 104 PC Sta. 104+46.60105 ¬ = 3°58'37"PC Sta. 10+81.4210 11 12200201202EX. 24" SANITARY, CITY OF DUBLIN, QL "B"12"12"E X. 6" S A NI T A R YEX. 6" ROOF DRAIN, QL "D"EX. 6" ROOF DRAIN, QL "D"EX. 6" ROOF DRAIN, QL "D"EX. 6" ROOF DRAIN, QL "D"PEDESTRI ANSUSI NGROADWAYPEDESTRIANSUSINGROADWAYONLYEMERGENCYVEHI CLEWEI GHT LI MI TSI NGLE AXLE 29TTANDEM 37TEMERGENCYVEHICLEWEIGHT LIMITSINGLE AXLE 29TTANDEM 37TPARKI NGNOTHI SSI DEOF STREETPARKINGNOTHISSIDEOF STREET1" = 20' STB 66 4/7/22 58074 EMW STB EMW 17 17 END PROJECT TO BEGIN PROJECT REPLACEMENT BRIDGE SHAWAN FALLS TRAFFIC CONTROLBRIDGE REPLACEMENTSHAWAN FALLS DRIVEONLYONLYSTA. 103+25R3-H8bh-36STA. 101+29R3-H8bh-36PAVEMENT MARKING LEGEND ITEM 644, CENTER LINE, 4", DOUBLE YELLOWCL CH ITEM 644, CHANNELIZING LINE, 8", WHITE CWL SL CV A ITEM 644, STOP LINE, 24", WHITE SL CV A A A CL CH CWL +51+86+75+71+45+39+29CH ITEM 644, CHEVRON MARKING, 12", WHITE, 12' SPACING ITEM 644, CROSSWALK LINE, 12", WHITE SHAW AN FALLS DR US33/SR161/BRIDGE ST9'+1810'10'+65ELW ITEM 644, EDGE LINE, 4", WHITE ELW12'12'12'+04 +61+86+53+07+51+18ELW 100'R300'RPAYMENT SHALL BE PER ITEM 630. TYPE XI, INCLUDING, SUPPLEMENTAL REQUIREMENTS S1. REFLECTIVE SHEETING SHALL BE IN ACCORDANCE WITH ODOT SUPPLEMENT 1049 AND ACCORDING TO ASTM D 4956, SHALL BE SUBMITTED FOR REVIEW AND APPROVAL PRIOR TO ORDERING MATERIAL. APPROVED BY THE CITY OF DUBLIN. NUTS AND BOLTS NEED NOT BE PAINTED. SHOP DRAWINGS AND COLOR SAMPLES THOSE ITEMS IS MADE UNDER THIS ITEM OF WORK. SIGN BACKING SHALL BE COATED WITH 3M VINYL MATERIAL AS ALL SIGNS ETC., SHALL BE COATED TO MATCH FEDERAL STANDARD 595-B COLOR #27038, BLACK. PAYMENT FOR ALL VISIBLE ELEMENTS OF SIGN MOUNTING SYSTEMS, E.G. SIGN BACKING ASSEMBLIES, SUPPORT POSTS, BACK OF (RD-10). SIGNS SHALL FOLLOW BLACK ALUMINUM BACKER FRAME PANEL AND REFLECTIVE SHEETING PER SHEETS 3 AND 4 OF 6 PER CITY OF DUBLIN STANDARD CONSTRUCTION DRAWING RD-10, BRIDGE STREET DISTRICT TYPICAL STREET SIGNS, TEMPORARY SIGNS. ON POSTS OR POLE SUPPORTS, OR OVERHEAD MOUNTED ON MAST ARMS. THIS SPECIFICATION SHALL NOT APPLY TO THIS SPECIFICATION INCLUDING PAINTING, APPLY TO ALL PERMANENT SIGNS WHETHER THEY ARE GROUND MOUNTED DEVICES FOR STREETS AND HIGHWAYS, STATE REQUIREMENTS AND LOCAL REQUIREMENTS. THE REQUIREMENTS OF ALL REGULATORY AND TRAFFIC CONTROL SIGNS SHALL COMPLY WITH OHIO MANUAL OF UNIFORM TRAFFIC CONTROL ITEM 630 SIGN, FLAT SHEET, AS PER PLAN ITEM 644, LANE ARROW, 96", WHITE STB 66 4/7/22 58074 EMW STB EMW NONE 18 P:\PR58074\FRA\000000\Design\MOT\Sheets\MN001.dgn Sheet 6/29/2022 8:03:54 AM worley18 MAINTENANCE OF TRAFFIC NOTESBRIDGE REPLACEMENTSHAWAN FALLS DRIVE& W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ 16/29/22NOTE MODIFICATIONAND MATERIALS NECESSARY TO CONSTRUCT AND MAINTAIN A COMPLETE AND FUNCTIONAL IMPACT ATTENUATOR SYSTEM, INCLUDING ALL RELATED BACKUPS, TRANSITIONS, LEVELING PRICE BID AND SHALL INCLUDE ALL LABOR, TOOLS, EQUIPMENT GATING IMPACT ATTENUATOR SHALL BE INCLUDED IN THE COST OF THE GATING IMPACT ATTENUATOR. PAYMENT FOR THE ABOVE WORK SHALL BE MADE AT THE UNIT PADS, HARDWARE AND GRADING, NOT SEPARATELY SPECIFIED, AS REQUIRED BY THE MANUFACTURER. THE COST FOR THE ADDITIONAL BARRIER REQUIRED FOR A THE ROADWAY STANDARDS APPROVED PRODUCTS WEB PAGE. INSTALLATION SHALL BE AT THE LOCATIONS SPECIFIED IN THE PLANS IN ACCORDANCE WITH THE MANUFACTURER'S APPROVED LIST FOR WORK ZONE IMPACT ATTENUATORS, FROM THIS ITEM SHALL CONSIST OF FURNISHING AND INSTALLING A NON-GATING IMPACT ATTENUATOR. FURNISH AN IMPACT ATTENUATOR FROM THE OFFICE OF ROADWAY ENGINEERING'S SPECIFICATIONS. WHEN GATING IMPACT ATTENUATORS ARE DESIRED, THE CONTRACTOR SHALL SUBMIT DOCUMENTATION TO THE ENGINEER FOR ACCEPTANCE. CONTRACTOR SHALL SUPPLY APPROPRIATE TRANSITIONS. THE CONTRACTOR SHALL REPAIR OR REPLACE A DAMAGED UNIT WITHIN 24 HOURS OF A DAMAGING IMPACT. WHEN BIDIRECTIONAL DESIGNS ARE SPECIFIED, THE EXCAVATION FOR MAINTAINING TRAFFIC 250 CU. YD. ITEM 614, MAINTAINING TRAFFIC, AS PER PLAN DELINEATION OF PORTABLE BARRIER CONTROL. ITEM 616, WATER 1 M. GAL. THE SPECIFICATIONS FOR PROTECTION OF COMPLETED ASPHALT CONCRETE COURSES. BARRIER REFLECTORS AND OBJECT MARKERS SHALL BE PERIODS OF TIME CONSISTENT WITH THE REQUIREMENTS OF PLACEMENT OF ASPHALT CONCRETE TWO-WAY TRAFFIC SHALL BE MAINTAINED AT ALL TIMES EXCEPT THAT ONE-WAY TRAFFIC WILL BE PERMITTED FOR MINIMUM INSTALLED ON ALL PORTABLE BARRIER (PB) USED FOR TRAFFIC THE PB CONTAINS GLARE SCREEN, ONE SET OF THREE VERTICAL STRIPES OF SHEETING SHALL BE CONSIDERED EQUIVALENT TO AN OBJECT MARKER, ONE-WAY. SHALL CONFORM TO C&MS 614.03 AND SCD MT-101.70. WHEN BARRIER REFLECTORS SHALL CONFORM TO C&MS 626, EXCEPT THAT THE SPACING SHALL BE AS PER TRAFFIC SCD MT-101.70. OBJECT MARKERS AND THEIR INSTALLATION PLAN. IN WHICH NO WORK IS ANTICIPATED WITHIN A REASONABLE TIME FRAME, AS DETERMINED BY THE ENGINEER, SHALL NOT BE PERMITTED. THE LEVEL OF UTILIZATION OF MAINTENANCE OF CLOSURES OR RESTRICTIONS OVER SEGMENTS OF THE PROJECT LENGTH AND DURATION OF LANE CLOSURES AND RESTRICTIONS SHALL BE AT THE APPROVAL OF THE ENGINEER. IT IS THE INTENT TO MINIMIZE THE IMPACT TO THE TRAVELING PUBLIC. LANE TRAFFIC DEVICES SHALL BE COMMENSURATE WITH THE WORK IN MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES. PAYMENT FOR ALL LABOR, EQUIPMENT AND MATERIALS SHALL BE INCLUDED IN THE LUMP SUM CONTRACT PRICE FOR ITEM 614, PORTIONS OF THE SPECIFICATIONS, AS WELL AS THE OHIO PROGRESS. ALL WORK AND TRAFFIC CONTROL DEVICES SHALL BE IN ACCORDANCE WITH C&MS 614 AND OTHER APPLICABLE ROAD. ADDITIONAL SOIL BORINGS ALONG THE TEMPORARY ROAD ARE NOT NORMALLY REQUIRED. ITEM 614, OBJECT MARKER, TWO-WAY 17 EACH CONDITIONS ARE ADEQUATE TO SUPPORT THE TEMPORARY TEMPORARY ROAD UNDERCUTS IF WITHIN A CLOSE PROXIMITY TO THE MAINLINE UNDERCUTS. A GEOTECHNICAL EVALUATION SHOULD BE CONSIDERED TO DETERMINE IF THE EXISTING SOIL ITEM 614, BARRIER REFLECTOR, TYPE 1, BI-DIRECTIONAL 17 EACH DUST CONTROL THE CONTRACTOR SHALL FURNISH AND APPLY WATER FOR DUST OR EMBANKMENT CONSTRUCTION, EVALUATE THE NEED FOR FURNISHING, INSTALLING, MAINTAINING AND REMOVING EACH OF THE ABOVE ITEMS. MAINTAINING TRAFFIC, UNLESS SEPARATELY ITEMIZED IN THE LABOR, INCIDENTALS AND EQUIPMENT NECESSARY FOR THE FOLLOWING ESTIMATED QUANTITIES HAVE BEEN INCLUDED IN THE PLANS AND CARRIED TO THE GENERAL SUMMARY: PAYMENT SHALL BE FULL COMPENSATION FOR ALL MATERIAL, CONSTRUCTION INITIATION THE FOLLOWING QUANTITIES HAVE BEEN INCLUDED IN THE PLAN FOR INFORMATION ONLY. WHEN UNDERCUTS ARE NECESSARY FOR MAINLINE PAVEMENT EARTHWORK FOR MAINTAINING TRAFFIC CONFLICTING MARKINGS COVERING SIGNS TEMPORARY PAVEMENT MARKINGS FOR ITEM 614-MAINTAINING TRAFFIC, AS PER PLAN. SHALL BE INCLUDED IN THE LUMP SUM CONTRACT PRICE TION AND REMOVAL OF TEMPORARY PAVEMENT MARKINGS ALL MATERIALS AND LABOR ASSOCIATED WITH THE INSTALLA- CONTRACT PRICE FOR ITEM 614 - MAINTAINING TRAFFIC, AS PER PLAN. MARKINGS SHALL BE INCLUDED IN THE LUMP SUM WITH THE MAINTENANCE OF THE TEMPORARY PAVEMENT TEMPORARY PAVEMENT MARKINGS. ALL COSTS ASSOCIATED TO INSPECT AND REQUIRE REPLACEMENT OF DAMAGED UNSERVICEABLE. THE CITY ENGINEER SHALL HAVE THE RIGHT TEMPORARY PAVEMENT MARKINGS THAT BECOME PAVEMENT MARKINGS AND TO REPAIR AND/OR REPLACE ALL REQUIRED TO INSPECT AND MAINTAIN ALL TEMPORARY SHALL BE ITEM 642 - PAINT. THE CONTRACTOR SHALL BE MARKINGS REQUIRED FOR THE MAINTENANCE OF TRAFFIC BEYOND THE PROJECT LIMITS. ALL TEMPORARY PAVEMENT THE CONTRACTOR SHALL NOT DAMAGE THE ROADWAY SURFACE 614-MAINTAINING TRAFFIC. COSTS FOR COVERING SIGNS SHALL BE INCLUDED IN ITEM COVERING OF SIGNS SHALL BE IN ACCORDANCE WITH 614.07. CONFLICT WITH THE MAINTENANCE OF TRAFFIC SIGNING. THE CONTRACTOR SHALL COVER ALL EXISTING SIGNS THAT CONSTRUCTION PROJECT. OF ANY AND ALL DELAYS AND/OR CHANGES REGARDING THE CONTRACTOR WILL IMMEDIATELY INFORM THE CITY ENGINEER PRIOR TO THE START OF CONSTRUCTION ACTIVITIES. THE THE CONTRACTOR WILL NOTIFY THE CITY ENGINEEER 14 DAYS CLASS B, APP ITEM 615 - PAVEMENT FOR MAINTAINING TRAFFIC, LOCAL ACCESS INCLUDED. PERSONS THAT WERE GIVEN NOTICES WITH THE DATE OF THE NOTICE REMAINING OPEN. THE ENGINEER SHALL BE GIVEN A LIST OF THE COMMERCIAL ENTRANCE WITH THE OTHER COMMERCIAL ENTRANCE 48 HOURS BUT NOT MORE THAN 72 HOURS PRIOR TO CLOSURE OF ONE OWNERS, RESIDENTS, OR BUSINESS OPERATORS IN WRITING AT LEAST THE PLANS. THE CONTRACTOR WILL BE RESPONSIBLE FOR NOTIFYING COMMERCIAL PROPERTIES AT ALL TIMES UNLESS SHOWN OTHERWISE ON INGRESS AND EGRESS SHALL BE MAINTAINED TO ALL PUBLIC AND ITEM 614, LAW ENFORCEMENT OFFICER WITH PATROL CAR, AS PER PLAN CONTROL AS DIRECTED BY THE ENGINEER. CALCIUM CHLORIDE SHALL NOT BE USED. THE FOLLOWING ESTIMATED QUANTITIES HAVE BEEN INCLUDED FOR DUST CONTROL PURPOSES: 347 SY CLASS B, APP PAVEMENT FOR MAINTAINING TRAFFIC, FOR THIS PURPOSE: QUANTITIES HAVE BEEN CARRIED TO THE GENERAL SUMMARY AT THE DETAILED CROSS-SLOPE. THE FOLLOWING EARTHWORK REQUIRED TO PROVIDE TEMPORARY PAVEMENT PAVEMENT FOR MAINTAINING TRAFFIC. THIS INCLUDES ANY THE CONTRACTOR SHALL FURNISH AND INSTALL TEMPORARY PEDESTRIAN ACCOMMODATIONS BRIDGE STREET. USERS OF THE SHARED USE PATH AND SIDEWALK ADJACENT TO W THE CONTRACTOR SHALL FOLLOW ODOT SCD MT-110.10 TO DETOUR PER PLAN. PRICE FOR ITEM 614, LAW ENFORCEMENT OFFICER WITH PATROL CAR, AS OBTAIN THE SERVICES OF A LEO ARE INCLUDED WITH THE BID UNIT (ADMINISTRATIVE OR OTHERWISE) INCURRED BY THE CONTRACTOR TO BY THE LAW ENFORCEMENT AGENCY INVOLVED. ANY ADDITIONAL COSTS THE HOURS PAID SHALL INCLUDE ANY MINIMUM SHOW-UP TIME REQUIRED 100 HOURS ITEM 614, LAW ENFORCEMENT OFFICER WITH PATROL CAR, AS PER PLAN THE GENERAL SUMMARY. PLAN. THE FOLLOWING ESTIMATED QUANTITIES HAVE BEEN CARRIED TO UNDER ITEM 614, LAW ENFORCEMENT OFFICER WITH PATROL CAR, AS PER TASKS ABOVE SHALL BE PAID FOR ON A UNIT PRICE (HOURLY) BASIS LEOS (WITH PATROL CAR) REQUIRED BY THE TRAFFIC MAINTENANCE COUNTY SHERIFF'S OFFICE, OR OHIO STATE HIGHWAY PATROL. ENFORCEMENT AGENCY'S: CITY OF DUBLIN (614-410-4800), FRANKLIN PARTIES. THE CONTRACTOR SHALL UTILIZE ANY OF THE FOLLOWING LAW WILL RESOLVE ANY ISSUES THAT MAY ARISE BETWEEN THE TWO HAVE FINAL CONTROL OVER THE LEOS' DUTIES AND PLACEMENT, AND PLANS WITH RESPECT TO DUTIES OF THE LEOS. THE ENGINEER SHALL APPROPRIATE AGENCIES AND COMMUNICATING THE INTENTIONS OF THE RESPONSIBLE FOR SECURING THE SERVICES OF THE LEOS WITH THE AT THE DIRECTION OF THE CONTRACTOR. THE CONTRACTOR IS WHERE COMPLETE BLOCKAGE OF TRAFFIC IS REQUIRED. THE LEOS WORK B. DURING THE ENTIRE ADVANCE PREPARATION AND CLOSURE SEQUENCE INTERSECTIONS IN WORK ZONES. CLOSURE TO MANUALLY CONTROL TRAFFIC MOVEMENTS THROUGH SHOULD BE POSITIONED AT THE POINT OF LANE RESTRICTION OR ROAD LANE CLOSURE ARRANGEMENTS ARE INITIATED. IN GENERAL, LEOS PERIODS, SUBSTANTIAL SHIFTS OF A CLOSURE POINT OR WHEN NEW A. FOR LANE CLOSURES: DURING INITIAL SET-UP PERIODS, TEAR DOWN FOR THE FOLLOWING TRAFFIC CONTROL TASKS: OF THE APPROPRIATE LAW ENFORCEMENT AGENCY) SHALL BE PROVIDED TOP-MOUNTED EMERGENCY FLASHING LIGHTS AND COMPLETE MARKINGS A UNIFORMED LEO WITH AN OFFICIAL PATROL CAR (CAR WITH ADDITION TO THE REQUIREMENTS OF ODOT C&MS 614 AND THE OMUTCD, NOT BE USED WHERE THE OMUTCD INTENDS THAT FLAGGERS BE USED. IN PERMITTED AT PROJECT COST UNLESS PRIOR APPROVAL. LEOS SHOULD THAN THE USES SPECIFIED BELOW IN THIS NOTE WILL NOT BE USE OF LAW ENFORCEMENT OFFICERS (LEOS) BY CONTRACTORS OTHER ITEM 614, WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS, UNIDIRECTIONAL ITEM 614, WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS, BIDIRECTIONAL PLAN. CONTRACT PRICE FOR ITEM 614-MAINTAINING TRAFFIC, AS PER CONFLICTING MARKINGS SHALL BE INCLUDED IN THE LUMP SUM ACCORDANCE WITH 614.11 AND 641.10. THE COST FOR REMOVAL OF TRAVELING PUBIC DURING DAYLIGHT OR NIGHTTIME HOURS IN REMOVE ALL EXISTING CONFLICTING MARKINGS VISIBLE TO THE THE CONTRACTOR SHALL, PRIOR TO PLACING TEMPORARY MARKINGS, 1 P:\PR58074\FRA\000000\Design\MOT\Sheets\MN001.dgn Sheet 5/6/2022 5:10:47 PM jkelleySTB 66 4/7/22 58074 EMW STB EMW NONE 19 19 & W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ MAINTENANCE OF TRAFFIC NOTESBRIDGE REPLACEMENTSHAWAN FALLS DRIVESEQUENCE OF CONSTRUCTION - NO MOT PLAN VIEW SHEET PROVIDED FOR PHASE 5. OTHER REMAINING ITEMS. A. CONSTRUCT FINAL SURFACE COURSE, PAVEMENT MARKINGS, AND ANY PHASE 5: - NO MOT PLAN VIEW SHEET PROVIDED FOR PHASE 4. CONTROL PER SCD MT-97.10. THE EAST SIDE OF SHAWAN FALLS DRIVE VIA 1-LANE, 2-WAY FLAGGER A. CONSTRUCT THE CURB RAMP AND SIDEWALK AT STATION 106+26 ON PHASE 4: - NO MOT PLAN VIEW SHEET PROVIDED FOR PHASE 3. 1-LANE, 2-WAY FLAGGER CONTROL PER SCD MT-97.10. SHAWAN FALLS DRIVE INCLUDING THE CURB AND ADA CURB RAMP VIA B. CONSTRUCT THE NORTHWEST CORNER OF W BRIDGE STREET AND FLAGGER CONTROL PER SCD MT-97.10. SIDEWALK, DRIVEWAYS, CURB, AND ADA CURB RAMPS VIA 1-LANE, 2-WAY A. CONSTRUCT THE WEST SIDE OF SHAWAN FALLS DRIVE INCLUDING THE PHASE 3: OPERATIONAL). SHAWAN FALLS DRIVE, INCLUDING THE SIGNAL (FULLY INSTALLED AND B. CONSTRUCT THE NORTHEAST CORNER OF W BRIDGE STREET AND ROADWAY (INTERMEDIATE COURSE) AND BRIDGE. A. CONSTRUCT THE EAST SIDE OF SHAWAN FALLS DRIVE INCLUDING THE PHASE 2: C. CONSTRUCT THE TEMPORARY PAVEMENT. EXCLUDING THE CURB, DRIVEWAYS, SIGNAL, AND SIDEWALK. WIDENING OF THE ROADWAY (INTERMEDIATE COURSE) AND BRIDGE; B. CONSTRUCT THE WEST SIDE OF SHAWAN FALLS DRIVE INCLUDING THE A. CONSTRUCT THE 8" WATER LINE. PHASE 1: PI Sta. 95+86.4696 97 98PC Sta. 98+00.98PT Sta. 98+83.7799 100 PI Sta. 100+76.19101¬ = 3°58'37"2002012022031" = 20' STB 66 4/7/22 58074 EMW STB EMW 20 20 STA. 101+50 TO BEGIN PROJECT REPLACEMENT BRIDGE SHAWAN FALLS MAINTENANCE OF TRAFFIC - PHASE 1BRIDGE REPLACEMENTSHAWAN FALLS DRIVEENDROAD WORKEND ROAD WORK WORKROADAHEADWORK ROAD AHEAD ENDROAD WORKSTA. 98+47W20-1-36STA. 98+51G20-2-36W20-1-36G20-2-36 W20-1-36G20-2-36WORKROADAHEADMATCHLI NE STA. 101+50SL CL+07+0210' EL EL +91 LEGEND D DRUMS (20' SPACING) PORTABLE BARRIER IMPACT ATTENUATOR TEMPORARY PAVEMENT EL SL CL DL CH A ITEM 614, LANE ARROW, CLASS I ITEM 614, CHANNELIZING LINE, 8", CLASS I ITEM 614, CENTER LINE, CLASS I ITEM 614, STOP LINE, CLASS I 1 7 3'R20'R19'R26.46' LT 101+14.40 27.24' LT 101+33.91 35.50' LT 101+28.6148.49' LT 101+00.80 25.04' LT 101+13.92 PB IA WORK AREA CORBINS MILL DR PB PB US 33/SR 161/BRIDGE STITEM 614, EDGE LINE, WHITE, 4", CLASS I ITEM 614, DOTTED LINE, YELLOW, 4", CLASS I DIRECTION OF TRAFFIC FALLS DRSHAWAN 30'R+03 ITEM 614, DOTTED LINE, WHITE, 4", CLASS IDLW PER ODOT SCD MT-110.10. 1. CONTRACTOR SHALL PROVIDE PEDESTRIAN DETOUR NOTE: 102 PC St a. 102+50.84PT Sta. 102+85.74103 104 PC Sta. 104+46.60105 106PT Sta. 106+51.39PC Sta. 10+81.4210 1" = 20' 66 4/7/22 58074 EMW STB EMW 21 21 END PROJECT TO STA. 101+50 REPLACEMENT BRIDGE SHAWAN FALLS MAINTENANCE OF TRAFFIC - PHASE 1BRIDGE REPLACEMENTSHAWAN FALLS DRIVEWORKROADAHEADENDROAD WORKSTA. 106+15G20-2-36STA. 106+15W20-1-36STBMATCHLINE STA. 101+50CL 10'10'10'10'+70+58+23EL EL 38.78' LT 103+34.42 698'R36.29' LT 102+23.88 28.63' LT 102+24.09 24.00' LT 102+27.15 24.00' LT 102+70.29 13.07' LT 103+09.48 36.73' LT 103+43.55 12.00' LT 104+03.88 11.81' LT 103+88.47 522'R+65D 14.19' LT 103+88.28 29.66' LT 103+62.30 13.70' LT 103+61.66 D D SHAWAN FALLS DR PB IA 20*FOR LEGEND, SEE MAINTENANCE OF TRAFFIC SHEET A A 10'10'4'VARIESVARIES 0.016 PAVEMENT TEMPORARY1:1 SLOPE TERRAIN EXISTING SECTION A-A ROADWAY EXISTINGWORKZONE78'R38.62' LT 103+43.55 39.19' LT 103+17.07 +0854'R2' 10' SPACING 10' SPACING 10' SPACING 78'R29.67' LT 103+61.33 30.04' LT 103+88.63 DRIVEWAY CLOSED SHAWAN FALLS DR. | CONST. EXISTING #250 BUILDING #650 BUILDING #700 RUN FALLS INDIAN IS PART OF MOT LUMP SUM. REPLACED WITH ORIGINAL. OF WORK IN AREA, FRAME AND CASTING SHALL BE WITH PAVEMENT. UPON COMPLETION 24" DIAMETER CATCH BASINS (AA-S113). ENSURE FLUSH MANHOLE FRAME GROUND RIM (AA-S138) AND GRATING FOR REMOVED AND STORED. REPLACED WITH MODIFIED HEIGHT EX. CURB INLET MANHOLE FRAM AND CASTING SHALL BE TO TEMPORARY PAVEMENT. EXISTING ROOF DRAIN TEMPORARILY DIVERT 250 W. BRIDGE STREET. REMAIN OPEN AT ALL TIMES TO AT LEAST ONE DRIVEWAY SHALL WITHIN DRIVEWAY LIMITS. CONSTRUCT TEMPORARY PAVEMENT 21'R PI Sta. 95+86.4696 97 98PC Sta. 98+00.98PT Sta. 98+83.7799 100 PI Sta. 100+76.19101¬ = 3°58'37"200201202203ONLYONLYONLY1" = 20' STB 66 4/7/22 58074 EMW STB EMW 22 22 STA. 101+50 TO BEGIN PROJECT REPLACEMENT BRIDGE SHAWAN FALLS MAINTENANCE OF TRAFFIC - PHASE 2BRIDGE REPLACEMENTSHAWAN FALLS DRIVEWORKROADAHEADENDROAD WORKWORKROADAHEADEND ROAD WORK WORK ROAD AHEAD ENDROAD WORKONLYW20-1-36G20-2-36 G20-2-36W20-1-36STA. 96+14G20-2-36STA. 96+28W20-1-36STA. 99+25R3-H8bj -36MATCHLI NE STA. 101+50A A CL CH SL EL DL EL EL SL+93 +19+87+75 +11+54243'R+31+79+69+91+13+1641'R44'R+91+22+55+51+49+73+88+99+10D 12'12'10'10' CL A A PB IA12'US33/SR161/ BRIDGE STFALLS DRSHAWAN CORBINS MILL DR 20*FOR LEGEND, SEE MAINTENANCE OF TRAFFIC SHEET +35 +55 +65 43'R 26'R +24+33555'RDLW PB +43+13DURING MOT PHASE 2. COVER EXISTING LANE USE SIGN SIGNAL HEADS SHALL BE SHIFTED 34' WEST. SHALL BE SHIFTED 17' WEST. THE NORTHBOUND CORBIN MILL DR ALIGNMENT. THE SOUTHBOUND SHAWAN FALLS DR SIGNAL HEADS 2. CONTRACTOR SHALL ADJUST THE EXISTING SIGNAL HEAD PER ODOT SCD MT-110.10. 1. CONTRACTOR SHALL PROVIDE PEDESTRIAN DETOUR NOTE: 1 17/12/22ADDED NOTE 102 PC St a. 102+50.84103 104 PC Sta. 104+46.60105 106PT Sta. 106+51.3910 7PC Sta. 10+81.4212"1" = 20' STB 66 4/7/22 58074 EMW STB EMW 23 23 END PROJECT TO STA. 101+50 REPLACEMENT BRIDGE SHAWAN FALLS MAINTENANCE OF TRAFFIC - PHASE 2BRIDGE REPLACEMENTSHAWAN FALLS DRIVEWORKROADAHEADENDROAD WORK10MPH10MPHSTA. 107+07G20-2-36STA. 107+07W20-1-36STA. 102+18W13-1P-18W1-4R-30STA. 105+04W13-1P-18W1-4R-30MATCHLI NE STA. 101+50EL CL D +04+3810'10' D D D EL SHAW AN FALLS DR 20 PB IA *FOR LEGEND, SEE MAINTENANCE OF TRAFFIC SHEET+64+18+12+2210' SPACING 5' SPACING 5' SPACING DRIVEWAY CLOSED #250 BUILDING #650 BUILDING #700 RUN FALLS INDIAN JED MSL 66 4/7/22 58074 MSL NONE P:\PR58074\FRA\000000\Design\Drainage\Sheets\DE001.dgn Sheet 5/6/2022 5:10:56 PM jkelley24 24 REPLACEMENT BRIDGE SHAWAN FALLS NOTES EROSION CONTROL SEDIMENT & JEDBRIDGE REPLACEMENTSHAWAN FALLS DRIVEWITHIN 24 HOURS AFTER A RAIN EVENT OF GREATER THAN 0.5 INCHES IN A 24-HOUR PERIOD. ONCE EVERY 7 CALENDAR DAYS AND/OR THE PROJECT. IDENTIFYING ANY INCIDENTS OF NONCOMPLIANCE. KEEP RECORDS 3 YEARS AFTER COMPLETION OF PLAN, A CERTIFICATION THAT THE FACILITY IS IN COMPLIANCE WITH THE PLAN, AND RELATING TO THE IMPLEMENTATION OF THE TEMPORARY EROSION AND SEDIMENT CONTROL NAME(S) AND QUALIFICATIONS OF PERSONNEL MAKING THE INSPECTION, MAJOR OBSERVATIONS INSPECTION COMPLETION. THE REPORT SHALL CONTAIN THE RESULTS OF THE INSPECTION, PREPARED BY THE CONTRACTOR AND SUBMITTED TO THE CITY ENGINEER WITHIN 48 HOURS OF WHETHER ADDITIONAL MEASURES ARE REQUIRED. ACCEPTABLE INSPECTION REPORTS SHALL BE MAINTENANCE OF EXISTING AND PROPOSED EROSION/SEDIMENTATION MEASURES; AND DETERMINE ASSOCIATED WITH THE PROJECT; EVALUATE THE ADEQUACY, IMPLEMENTATION, AND THESE INSPECTIONS SHALL IDENTIFY AREAS CONTRIBUTING TO STORMWATER DISCHARGES WITHIN 24 HOURS AFTER A RAIN EVENT OF GREATER THAN 0.5 INCHES IN A 24-HOUR PERIOD. CONTRACTOR IN THE PRESENCE OF THE CITY ENGINEER, RESPONSIBILITY OF THE CONTRACTOR. INSPECTIONS SHALL BE PERFORMED BY THE EROSION/SEDIMENT CONTROL DEVICES REQUIRED BY THE CITY ENGINEER SHALL BE THE SOLE PERFORMANCE OF THEIR INTENDED FUNCTION. MAINTENANCE AND INSPECTION OF ALL REQUIREMENTS. THEY SHALL BE MAINTAINED AND REPAIRED AS NEEDED TO ENSURE CONTINUED CONTROL PRACTICES SHALL BE DESIGNED AND CONSTRUCTED TO MINIMIZE MAINTENANCE MAINTENANCE AND INSPECTION - ALL TEMPORARY AND PERMANENT EROSION AND SEDIMENT15. PROBLEMS. ENGINEER'S RECOMMENDATIONS TO CORRECT, ELIMINATE, OR ADEQUATELY ADDRESS THE THEM UNLESS THE WORK IS DONE IN ACCORDANCE WITH A QUALIFIED PROFESSIONAL LANDSLIDING SHALL NOT BE GRADED, EXCAVATED, FILLED, OR HAVE LOADS IMPOSED UPON PLACING IS AUTHORIZED BY THE CITY ENGINEER. UNSTABLE SOILS PRONE TO SLIPPING OR READILY SLOUGH, SLIP, OR ERODE INTO A WATER RESOURCE UNLESS SUCH DUMPING OR DUMPED OR PLACED INTO A WATER RESOURCE OR INTO SUCH PROXIMITY THAT IT MAY SLOUGHING AND DUMPING - NO SOIL, ROCK, DEBRIS, OR ANY OTHER MATERIAL SHALL BE14. TRACKING OF SEDIMENTS BY VEHICLES AND EQUIPMENT IS ELIMINATED. ONTO PUBLIC ROADS. THE CONTRACTOR SHALL BE RESPONSIBLE TO ENSURE THAT OFF-SITE TRANSPORT ONTO SURFACES WHERE RUNOFF IS NOT CHECKED BY SEDIMENT CONTROLS, OR CONSTRUCTION ACCESS ROUTES - MEASURES SHALL BE TAKEN TO PREVENT SOIL13. TEMPORARY CULVERT SHALL BE PROVIDED. MUST BE CROSSED BY CONSTRUCTION VEHICLES REGULARLY DURING CONSTRUCTION, A STABILIZE THE WORK AREA DURING CONSTRUCTION TO MINIMIZE EROSION. WHERE A STREAM OF STREAMS. WHERE IN-CHANNEL WORK IS NECESSARY, PRECAUTIONS SHALL BE TAKEN TO STOPPED. TO THE EXTENT PRACTICABLE, CONSTRUCTION VEHICLES SHALL BE KEPT OUT RESTABILIZED IMMEDIATELY AFTER IN-CHANNEL WORK IS COMPLETED, INTERRUPTED, OR WORKING IN OR CROSSING STREAMS - STREAMS INCLUDING BED AND BANKS SHALL BE12. AND AS DIRECTED BY THE CITY ENGINEER. FACILITY. THESE CONTROLS SHALL BE SELECTED AND LOCATED AS INDICATED IN THE PLANS TREATED TO REMOVE SEDIMENT, UNLESS THE STORM SEWER SYSTEM DRAINS TO A SETTLING WILL NOT ENTER THE STORM SEWER SYSTEM WITHOUT FIRST BEING FILTERED OR OTHERWISE RUNOFF FROM THE PROJECT AREA SHALL BE PROTECTED SO THAT SEDIMENT-LADEN WATER STORM SEWER INLET PROTECTION - ALL STORM SEWER INLETS WHICH ACCEPT WATER11. TO FUNCTION UNTIL THE UPSLOPE DEVELOPMENT AREA IS STABILIZED. CONSTRUCTION AND WITHIN 7 DAYS FROM THE START OF GRUBBING. THEY SHALL CONTINUE INTENDED TO TRAP SEDIMENT SHALL BE IMPLEMENTED AS THE FIRST STEP OF GRADING OR SETTLING FACILITIES, SEDIMENT FILTERS, PERIMETER CONTROLS, AND OTHER PRACTICES10. 7 DAYS AFTER AREA OR SECTION HAS BEEN OPENED. BACKFILL TRENCHES IMMEDIATELY AFTER USE. SEED AND MULCH TRENCH AREA WITHIN9. EROSION CONTROL VALUE. ACTUAL CONSTRUCTION. PROTECT THE REMAINING TO PRESERVE THEIR AESTHETIC AND REMOVE ONLY THE TREES, SHRUBS, AND GRASSES THAT MUST BE REMOVED TO PERMIT8. MAINTAIN DRAINAGE AND AESTHETICS. FINAL GRADING WILL BE CONSISTENT WITH PRECONSTRUCTION TOPOGRAPHY TO7. ANCHORED STRAW MULCH. ARE TO BE PROTECTED THROUGH THE USE OF TEMPORARY SEEDING, OR COVERED WITH ALL DENUDED AREAS, INCLUDING STOCKPILED TOPSOIL AND EXCAVATED MATERIAL,6. BEFORE GROWTH OF PERMANENT GROUND COVER. TEMPORARY SEDIMENT DEVICES AT THE CONCLUSION OF CONSTRUCTION BUT NOT ESTABLISHED. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REMOVAL OF ALL THAT ARE INSTALLED SHALL BE MAINTAINED UNTIL VEGETATIVE GROWTH HAS BEEN SEEDED WITHIN 7 CALENDAR DAYS OF THE DISTURBANCE. OTHER SEDIMENT CONTROLS DISTURBED AREAS THAT WILL REMAIN UNWORKED FOR 14 DAYS OR MORE SHALL BE5. TIMES CONSISTENT WITH EROSION CONTROL PRACTICES. THE CONTRACTOR SHALL PROVIDE ADEQUATE DRAINAGE OF THE WORK AREA AT ALL4. TEMPORARY GROUND COVER. THE USE OF STRAW BALES IS PROHIBITED. NOT LIMITED TO: SEDIMENT FILTERS, WATTLES, INLET PROTECTION, AND ACCEPTED METHODS OF PROVIDING EROSION/SEDIMENT CONTROL INCLUDE BUT ARE3. SEWERS, WHETHER SPECIFICALLY SHOWN ON THE PLANS OR NOT. LEAVES THE PROJECT, INCLUDING WATERWAYS, OVERLAND SHEET FLOW, AND STORM THE CONTRACTOR SHALL PROVIDE SEDIMENT CONTROL AT ALL POINTS WHERE WATER2. THE DEVELOPER OF THE STORMWATER DISCHARGE. SPECIFICATIONS AND THE CITY ENGINEER. THE CONTRACTOR SHALL BE CONSIDERED OHIO EPA, ITEM 207 OF OHIO DEPARTMENT OF TRANSPORTATION (ODOT) STANDARD THE DESIGN OF EROSION CONTROL SYSTEMS SHALL FOLLOW THE REQUIREMENTS OF1. CONTROL MEASURES4.0 PROHIBITED CONSTRUCTION ACTIVITIES5.0 CONTROL MEASURES4.0 POST-CONSTRUCTION STORM WATER TREATMENT. THE PROJECT AREA IS LESS THAN ONE ACRE AND WILL NOT REQUIRE POST-CONSTRUCTION STORM WATER CONTROL6.0 SPECIFIED BY THE CITY ENGINEER FOR SAID PURPOSES. CONSTRUCTION MATERIALS ON PROPERTY (PUBLIC OR PRIVATE) NOT PREVIOUSLY STORING CONSTRUCTION EQUIPMENT AND VEHICLES AND/OR STOCKPILING9. OPEN BURNING OF PROJECT DEBRIS WITHOUT A PERMIT.8. WETLANDS, OR SURFACE WATERS. DISPOSAL OF TREES, BRUSH, AND OTHER DEBRIS IN ANY STREAM CORRIDORS,7. DAMAGING VEGETATION OUTSIDE OF THE CONSTRUCTION AREA.6. PERMANENT OR UNSPECIFIED ALTERATION OF THE FLOWLINE OF A STREAM.5. THERETO. RIVERS, STREAMS, IMPOUNDMENTS, OR INTO NATURAL OR MAN-MADE CHANNELS LEADING MATERIALS, RAW SEWAGE, AND/OR ANY OTHER HARMFUL WASTE, INTO OR ALONGSIDE OF DISCHARGING POLLUTANTS SUCH AS CHEMICALS, FUELS, LUBRICANTS, BITUMINOUS4. DRAINS. INTO ANY SURFACE WATERS, ANY STREAM CORRIDORS, ANY WETLANDS, OR STORM PUMPING OF SEDIMENT LADEN WATER FROM TRENCHES OR OTHER EXCAVATIONS3. LIMITS. STREAM CORRIDORS, ANY WETLANDS, ANY SURFACE WATERS, OR OUTSIDE THE EASEMENT INDISCRIMINATE, ARBITRARY, OR CAPRICIOUS OPERATION OF EQUIPMENT IN ANY2. FLOOD PLAINS, EVEN WITH THE PERMISSION OF THE PROPERTY OWNER. DISPOSING OF EXCESS OR UNSUITABLE EXCAVATED MATERIAL IN WETLANDS OR1. ACTIVITIES, OR OPERATIONS INCLUDE, BUT ARE NOT LIMITED TO, THE FOLLOWING: THE PUBLIC HEALTH AND SAFETY. PROHIBITED CONSTRUCTION PROCEDURES, OPERATIONS THAT MAY UNNECESSARILY IMPACT THE NATURAL ENVIRONMENTAL OR THE CONTRACTOR SHALL NOT USE CONSTRUCTION PROCEDURES, ACTIVITIES, OR INSPECTION REPORTS· A COPY OF THE CONSTRUCTION GENERAL PERMIT· CORRECTIVE ACTION AND SWP3 AMENDMENT LOGS· DATES OF GRADING, CONSTRUCTION ACTIVITY, AND STABILIZATION· KEPT AT THE PROJECT SITE AND MADE AVAILABLE FOR INSPECTORS TO REVIEW: RECORD KEEPING - THE FOLLOWING IS A LIST OF RECORDS THAT WILL NEED TO BE22. MATERIALS USED TO CONSTRUCT THE AREA WILL BE REMOVED AND DISPOSED OF OFF-SITE. LONGER NEEDED FOR THE CONSTRUCTION PROJECT, THE HARDENED CONCRETE AND WILL BE PROPERLY DISPOSED OF OFF-SITE. WHEN THE TEMPORARY WASHOUT AREA IS NO TRUCKS AND CHUTES WILL BE WASHED IN THE DESIGNATED AREA OR CONCRETE WASTES NOT BE CONDUCTED DURING OR BEFORE AN ANTICIPATED STORM EVENT. CONCRETE MIXER CONCRETE EQUIPMENT OPERATORS USE THE PROPER FACILITY. CONCRETE POURS WILL SHALL BE POSTED MARKING THE LOCATION OF THE WASHOUT AREA TO ENSURE THAT TEMPORARY ABOVE-GRADE CONCRETE WASHOUT AREA SHALL BE CONSTRUCTED. SIGNS CONCRETE WASHOUT - IF CONCRETE IS NEEDED AT THE SITE, A DESIGNATED21. TO SURVIVE ADVERSE WEATHER CONDITIONS. ADEQUATE COVER AND IS MATURE ENOUGH TO CONTROL SOIL EROSION SATISFACTORILY & COVER IS ACHIEVED WHICH, IN THE OPINION OF THE APPROVING AGENCY, PROVIDES PERMANENT VEGETATION SHALL NOT BE CONSIDERED ESTABLISHED UNTIL GROUND20. ADJUSTMENTS TO THE SWP3. CONTRACTOR SHALL ALSO BE SOLELY RESPONSIBLE TO PERFORM ALL UPDATES AND RESPONSIBLE TO ENSURE THE IMMEDIATE AVAILABILITY OF THE SWP3 ON-SITE. THE SWP3 AVAILABILITY AND UPDATES - THE CONTRACTOR SHALL BE SOLELY19. AND SWP3. UPDATES AND ADJUSTMENTS TO THE TEMPORARY EROSION AND SEDIMENT CONTROL PLAN ON-SITE. THE CONTRACTOR SHALL ALSO BE SOLELY RESPONSIBLE TO PERFORM ALL AVAILABILITY OF THE TEMPORARY EROSION AND SEDIMENT CONTROL PLAN AND SWP3 THE CONTRACTOR SHALL BE SOLELY RESPONSIBLE TO ENSURE THE IMMEDIATE TEMPORARY EROSION AND SEDIMENT CONTROL PLAN AVAILABILITY AND UPDATES -18. ANY STORMWATER FLOW. CONTRACTOR SHALL ALSO ENSURE THAT NO SOLID OR LIQUID WASTE IS DISCHARGED INTO TRACKED OFF-SITE BY CONSTRUCTION EQUIPMENT, VEHICLES, AND WORKERS. THE ADDITIONAL CONTROLS - THE CONTRACTOR SHALL ENSURE THAT NO SEDIMENTS ARE17. IN SUCH A MANNER AS TO ELIMINATE EROSION FROM SUCH DISCHARGE. OPERATIONS OR FROM MORE EXTENSIVE DEWATERING OPERATIONS, SHALL BE DISCHARGED AND DEWATERING OPERATIONS, WHETHER SPECIFICALLY FROM TRENCH DEWATERING OUTFLOWS FROM DEWATERING OPERATIONS - ALL WATER PRODUCED FROM CLEANING16. AND REVISE THIS SCHEDULE TO REFLECT THE ACTUAL SCHEDULE. ACTIVITIES IS ATTACHED IN THE ADDENDUM SECTION E. CONTRACTOR SHALL UPDATE 1/2 INCH. THE TENTATIVE SCHEDULE FOR THE EROSION AND SEDIMENT CONTROL STABILIZATION METHODS WHEN A 24-HOUR RAINFALL EVENT IS EXPECTED TO EXCEED WEATHER FORECASTS AND DIRECT INSTALLATION OF COVERINGS OR OTHER DISTURBING ACTIVITIES. THE CONSTRUCTION MANAGER WILL MONITOR REGIONAL EROSION AND SEDIMENT CONTROL MEASURES WILL BE INSTALLED PRIOR TO SOIL IMPLEMENTATION SCHEDULE3.4 USES WERE PRIMARILY COMMERCIAL. RIGHTS-OF-WAY AND/OR PRIVATELY OWNED COMMERCIAL PROPERTY. PRIOR LAND THE MAJORITY OF AREAS WHERE SOIL WILL BE DISTURBED ARE CURRENTLY MOWED PRIOR LAND USES3.3 THE SWP3 ADDENDUM SECTION D. 6 PERCENT SLOPES. SOIL SURVEY INFORMATION IS PROVIDED IN THE PRINCIPAL SOIL TYPE MAPPED IN THE PROJECT AREA IS RITCHEY SILT LOAM, 2 TO SOIL DATA3.2 ADDENDUM SECTION C. AFTER CONSTRUCTION ACTIVITIES COMMENCE. A BLANK LOG IS PROVIDED IN THE MAINTAINED TO DOCUMENT THE GRADING AND STABILIZATION ACTIVITIES WHICH OCCUR COMPLETION OF THE PROJECT. A "GRADING AND STABILIZATION LOG" WILL BE WILL ALSO BE NECESSARY. DISTURBED SURFACE AREAS WILL BE STABILIZED AT THE GRADING FOR THE CONSTRUCTION OF THE ROAD. STOCKPILES AND STAGING AREAS RIGHT-OF-WAY. THE SOIL DISTURBING ACTIVITIES WILL INCLUDE EXCAVATION AND RIGHTS-OF-WAY AND/OR LANDSCAPED PRIVATE PROPERTY ADJACENT TO THE THE MAJORITY OF AREAS WHERE SOIL WILL BE DISTURBED ARE CURRENTLY MOWED SOUTH FORK INDIAN RUN. W BRIDGE STREET IN DUBLIN, OHIO. THE PROJECT WILL REPLACE THE BRIDGE OVER THE PROJECT IS LOCATED AT THE INTERSECTION OF SHAWAN FALLS DRIVE WITH SITE DESCRIPTION/CONSTRUCTION ACTIVITY3.1 SITE DESCRIPTION3.0 OF THE SWP3 ADDENDUM. WITH CONSTRUCTION ACTIVITY. A PLAN AMENDMENT LOG IS PROVIDED IN SECTION G OBJECTIVES OF CONTROLLING POLLUTANTS IN STORM WATER DISCHARGES ASSOCIATED OF THE STATE OR IF THE SWP3 PROVES TO BE INEFFECTIVE IN ACHIEVING THE GENERAL EFFECT ON THE POTENTIAL FOR THE DISCHARGE OF POLLUTANTS TO SURFACE WATERS DESIGN, CONSTRUCTION, OPERATION OR MAINTENANCE, WHICH HAS A SIGNIFICANT THE SWP3 WILL BE AMENDED BY THE CONTRACTOR WHENEVER THERE IS A CHANGE IN PLAN AMENDMENT2.2 SUBMITTED TO THE OHIO EPA. WRITTEN CERTIFICATION THAT THE REQUESTED CHANGES HAVE BEEN MADE WILL BE REQUIREMENTS OF THE GENERAL PERMIT. IF REQUESTED, THE REVISED SWP3 OR A FROM THE OHIO EPA THAT THE SWP3 DOES NOT MEET ONE OR MORE OF THE MINIMUM THE SWP3 WILL BE AMENDED BY THE CONTRACTOR WITHIN 10 DAYS AFTER NOTIFICATION PLAN REVISION2.1 PLAN REVISION AND AMENDMENT2.0 UNDERSTAND THE CONDITIONS AND RESPONSIBILITIES OF THE SWP3. CONTRACTORS AND SUBCONTRACTORS, ACKNOWLEDGING THAT THEY HAVE REVIEWED AND SWP3 AND THE ACKNOWLEDGMENT FORM FOR RECORDING THE SIGNATURES OF ALL SECTION B OF THE SWP3 ADDENDUM CONTAINS THE CERTIFICATION STATEMENT FOR THE UTILIZED THROUGHOUT THE PROJECT. PROVIDE EROSION AND SEDIMENT CONTROL AND STORM WATER MANAGEMENT WILL BE LESS THAN ONE ACRE OF LAND AREA. ALL REQUIRED PREVENTATIVE MEASURES TO GRUBBING, AND/OR FILLING ACTIVITIES WHICH WILL RESULT IN THE DISTURBANCE OF ACTIVITIES DURING THE PROJECT WILL INCLUDE CLEARING, GRADING, EXCAVATING, STORM WATER POLLUTION. FROM THE PROJECT AND TO ESTABLISH MEASURES AND PROCEDURES FOR PREVENTING THIS SWP3 IS TO IDENTIFY THE POTENTIAL SOURCES OF STORM WATER POLLUTION GENERAL STORM WATER PERMIT NO. OHC000004 (GENERAL PERMIT). THE PURPOSE OF PREPARED BY BURGESS & NIPLE TO COMPLY WITH THE OHIO EPA CONSTRUCTION THIS PRELIMINARY STORM WATER POLLUTION PREVENTION PLAN (SWP3) HAS BEEN INTRODUCTION1.0 P:\PR58074\FRA\000000\Design\Drainage\Sheets\DE001.dgn Sheet 5/6/2022 5:10:57 PM jkelleyNET WRAP. 100% NATURAL STRAW ROLLS WITH 0.03-INCH THICK NOTE: STRAW WATTLES SHALL BE 9-INCH DIAMETER, 12" MIN. 3" TYP. 12" MIN. WATTLE 9" DIA. STRAW 1"x1" STAKE @ 4'-0" O/C WATTLE 9" DIA. STRAW 25 REPLACEMENT BRIDGE SHAWAN FALLS NOTES EROSION CONTROL SEDIMENT & BRIDGE REPLACEMENTSHAWAN FALLS DRIVEJED MSL 66 4/7/22 58074 NONE MSL DAM GRATE OVERFLOW GAP CURB & GUTTER INLET FINGER LOOPS APPEAL SAFETY AND CURB GUTTER FOR LAYS FLUSH WITH UNIT. NO NEED TO REINSTALL. INSPECT CATCH BASIN AND REPLACE REMOVE UNIT WITH GRATE INSIDE, TO INSPECT CATCH BASIN: CUSTOM SIZES. IN 3", 4" OR DAM AVAILABLE MONOFILAMENT WOVEN MEETS FEDERAL REQUIREMENTS 30 SIEVE SIZE LESS THAN 7LBS WEIGHT OF UNIT IS UNIT WITH GRATE EASY MOVEMENT OF LIFTING STRAPS ALLOW CONCRETE CURBS ALL SHAPES OF CONFORMS TO SPECIAL DESIGN MATERIAL FROM INSIDE ENVELOPE AS NEEDED. BROOM OR SQUARE POINT SHOVEL. REMOVE FINE FROM SURFACE OF UNIT AS NEEDED WITH STIFF MAINTENANCE: REMOVE DRIED SEDIMENT SCALE: NONE STRAW WATTLE DETAIL SCALE: NONE ADJACENT WATTLE DETAIL TO SLOPE FACE. 2-3" OF STAKE EXTENDING ABOVE THE WATTLE. STAKES SHOULD BE DRIVEN PERPENDICULAR END. STAKES SHOULD BE DRIVEN THROUGH THE MIDDLE OF THE WATTLE LEAVING AT LEAST 3. SECURE THE WATTLE WITH 18"-24" STAKES EVERY 3'-4' AND WITH A STAKE ON EACH ADJACENT WATTLES SHOULD TIGHTLY ABUT. COMPACT SOIL FROM THE EXCAVATED TRENCH AGAINST THE WATTLE ON THE UPHILL SIDE. 2. PLACE THE WATTLE IN THE TRENCH SO THAT IT CONTOURS TO THE SOIL SURFACE. SOIL SHOULD BE PLACED UP-SLOPE FROM THE ANCHOR TRENCH. A 3" DEEP X 9" WIDE ANCHOR TRENCH ALONG THE CONTOUR OF THE SLOPE. EXCAVATED 1. BEGIN AT THE LOCATION WHERE THE WATTLE IS TO BE INSTALLED BY EXCAVATING NOTES: ITEM 207-WATTLES 25 JED ITEM 655 - TREE PROTECTION DETAIL ITEM 207-INLET PROTECTION STABILIZATION OF EARTH DISTURBED AREAS. 2. CONTRACTOR SHALL REMOVE WITHIN TWO (2) WEEKS OF FINAL PROTECTION RECOMMENDATIONS. PAYMENT WILL BE PER EACH FOR ITEM 207 - INLET IN ACCORDANCE WITH THE DETAILS AND THE MANUFACTURER'S 1. INSTALLATION AND MAINTENANCE OF INLET SEDIMENT FILTERS SHALL BE NOTES: 9. ROOTS SHALL BE KEPT MOIST WHILE TRENCHES ARE OPEN AND REFILLED IMMEDIATELY AFTER UTILITIES ARE INSTALLED OR REPAIRED. 8. SOIL EXCAVATION DURING TRENCHING SHALL BE PILED ON THE SIDE AWAY FROM THE TREE. DISCOURAGE DECAY. 7. ROOTS 2 INCHES OR LARGER THAT ARE SEVERED BY TRENCHING SHOULD BE SAWN OFF NEATLY IN ORDER TO ENCOURAGE NEW GROWTH AND BY ENGINEER. 6. MINIMIZE EXCAVATION OR TRENCHING WITHIN THE DRIP LINE OF THE TREE. ROUTE TRENCHES AROUND THE DRIP LINE OF TREES AS DIRECTED 5. NO FILLING OR STOCKPILING OF MATERIALS SHALL OCCUR WITHIN THE TREE PROTECTION AREA, INCLUDING DEPOSITION OF SEDIMENT. NOT BE GRUBBED OR PULLED OUT. NO CLEARING SHALL BE DONE IN BUFFER STRIPS OR OTHER PRESERVED FORESTED AREAS. 4. IF ANY CLEARING IS DONE AROUND SPECIMEN TREES IT SHALL BE DONE BY CUTTING AT GROUND LEVEL WITH HAND HELD TOOLS AND SHALL ENGINEER. 3. FENCE SHALL BE PLACED AS SHOWN IN THE DETAIL AND BEYOND THE DRIP LINE OR CANOPY OF TREES TO BE PROTECTED OR AS DIRECTED BY 2. TREE AND NATURAL PRESERVATION AREA SHALL BE FENCED PRIOR TO BEGINNING CLEARING OPERATIONS. PROTECT TREES AND VEGETATION TO BE LEFT STANDING. WITHIN DRIP LINE, EXCESS FOOT OR VEHICULAR TRAFFIC, OR PARKING OF VEHICLES WITHIN DRIP LINE. PROVIDE TEMPORARY GUARDS TO OF ROOTS, SKINNING OR BRUISING OF BARK, SMOTHERING OF TREES BY STOCKPILING CONSTRUCTION MATERIALS OR EXCAVATED MATERIALS 1. PROTECT EXISTING TREES AND OTHER VEGETATION INDICATED TO REMAIN IN PLACE AGAINST UNNECESSARY CUTTING, BREAKING, OR SKINNING NOTES: 845 8458 5 0 850 85 0 8 5 5 85585 5 855PI Sta. 100+76.19101 102 PC Sta. 102+50.84PT Sta. 102+85.74103N DATEREVIEWEDREVISEDDRAWNCHECKEDDESIGNEDP:\PR58074\FRA\000000\Design\Structure\Sheets\SP001.dgn Design 5/6/2022 4:53:15 PM jkelleySTA.STA. FT/S FT/S BORING LOCATION DESIGN TRAFFIC: BENCHMARK DATA NOTES LEGEND HYDRAULIC DATA SQ. MILES TYPE: SPANS: LOADING: SKEW: APPROACH SLABS: ALIGNMENT: CROWN: DATE BUILT: DISPOSITION: ROADWAY: PROPOSED STRUCTURE TYPE: SPANS: SKEW: APPROACH SLABS: ALIGNMENT: CROWN: ROADWAY: COORDINATES: LATITUDE LONGITUDE FT/FT EngineersArchitectsPlanners5085 REED RO AD, COLUMBUS, O HIO 43220SIMPLE SPAN PRESTRESSED CONCRETE BOX BEAMS WITH COMPOSITE CONCRETE DECK ON SEMI-INTEGRAL ABUTMENTS ON SPREAD FOOTINGS 42'-6" c/c BEARINGS LOADING: HL-93 33°30'00" RF TANGENT SIMPLE SPAN PRESTRESSED CONCRETE BOX BEAMS WITH ASPHALT WEARING SURFACE ON WALL TYPE ABUTMENTS ON SPREAD FOOTINGS 28'-0"` o/o DECK HS20-44 33°30'` RF 20'-0"` TANGENT 3/16"/FT. 1977 TO BE REPLACED EXISTING STRUCTURE STRUCTURAL FILE NUMBER: 2568772 1 24DRIVESHAWAN FALLS SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUNQ (10) = 863 Q (100) = 1660 V (100) = 9.0 DRAINAGE AREA = 6.4 SITE PLANJMKJMKBDESTRUCTURE CLEARS THE 25 YEAR DESIGN HW BY 0.14 FEET. N 40° 05' 58" W 83° 07' 16" R.A. = REAR ABUTMENT F.A. = FORWARD ABUTMENT BRGS. = BEARINGS A.S. = APPROACH SLAB 26 66 40'-0"` f/f ABUTMENTS 0.016 44'-0" CURB TO RAILING WITH 7'-3"(+) SIDEWALK V (10) = 8.9 CFS, FROM STREAMSTATS CFS, FROM STREAMSTATS STRUCTURE FILE NUMBER2568773FRANKLIN COUNTY101+71.94102+18.04IPINS W/ BLUE CAP BM #1 STA. 101+12.77, OFFSET 23.07' LT., ELEV. 857.016 IPINS W/ RED CAP BM #2 STA. 102+08.00, OFFSET 33.69' LT., ELEV. 853.366 IPINS W/ YELLOW CAP BM #3 STA. 101+82.90, OFFSET 32.63' LT., ELEV. 848.319 13 66 2. 1. DIRECTIONAL DISTRIBUTION = 0.5 2042 ADT = 12,100 2042 ADTT = 1,800 2022 ADT = 10,100 2022 ADTT = 1,500 ** = VARIES DEPENDING ON WALL PLACEMENT, 2:1 MAX. ¬ = 33°30'00" SKEW (TYP.) 20'-0" LONG (AS-1-15)JCS3/8/22NOTE ON SHEET FOR ADDITION INFORMATION. LOCATED BY THE CONTRACTOR, SEE PROTECTION OF UTILTIES EXISTING BRIDGE FOUNDATIONS. THESE LINES ARE TO BE APPROXIMATELY SHOWN. COPPER LINES MAY BE UNDER THE BE IN THE VICINITY OF THE FIBER OPTIC LINE BUT ARE ONLY TWO ADDITIONAL AT&T COPPER LINES TO REMAIN ARE KNOWN TO SEE ROADWAY SHEET FOR GRADING PLAN. B-001-0-19 PARK ING LOT GROU P SOUTH PHYS IC IANS OH IOHEALTH B-002-0-19 S.R. 161/W. BRIDGE ST.GROUND EXISTING GRADE PROFILE PROPOSED ELEVATION ALONG PROFILE GRADE (TO REMAIN) EX. FIBER OPTIC LINE (TO BE RELOCATED) EX. 12" STORM DRAIN INDIAN RUNSOUTH FORK101+00 102+00 (TO REMAIN) (CITY OF DUBLIN) EX. 24" SANITARY LINE -0.40 %-2.25 % 100.00' VC P.V.I. STA 102+91.00 ELEV = 853.88' 850.00 840.00 830.00 860.00 870.00 880.00 ELEV. = 856.35' P.V.I. STA 101+81.00 100.00' VC 46.10' BRIDGE LIMITS EXP.EXP. EL. 843.50 EL. 843.30 EL. 852.71 HW 25 N 10°55'56" W PC Sta. 102+50.84PT Sta. 102+85.74STA. 101+73.74 | BRGS. R.A. STA. 102+16.24 | BRGS. F.A. SHORING (TYP.) PILE AND LAGGING TEMPORARY SOLDIER STA. 101+71.94 END A.S. STA. 102+18.04 BEGIN A.S. ¬ PLAN 856.48855.99855.92856.07855.85855.26854.72854.35856.68856.58856.44856.20855.84855.36854.81854.38FALLS DRIVE | CONSTR. SHAWAN 51'-3•" PLUS FIT-UP o/o DECK7'-3•"SIDEWALKPLUS FIT-UPPHASE 227'-3•"PHASE 124'-0" PLUS FIT-UP8" WATER LINE PROPOSED (TO BE RELOCATED) (DU0085_002) EX. 8" WM (TO BE REMAIN) (CITY OF DUBLIN) (DU0085_002) EX. 8" WATER LINE (TO REMAIN) (CITY OF DUBLIN) (DU0008_009) EX. 16" WATER LINE 3 LANES @ 12'-0" = 36'-0"10 EL. 851.80 HW EL. 847.70 ORDINARY HIGH WATER 3 24 -2.25 %` 1.7:11.5:1 1.5:1M.E.2:1 M.E.M.E.2.25:12:1 M.E.3'-0"WITH FABRIC FILTER (TYP.) PR0TECTION, TYPE C LIMITS OF ROCK CHANNEL 856.72T/R = 847.7 APPROX. B-001-0-19 T/R = 843.6 APPROX. B-002-0-19 (TO REMAIN, SEE NOTE 2) EX. FIBER OPTIC LINE (TO REMAIN, SEE NOTE 2) EX. COPPER LINES 8:1 8:1 ** ** +0.23%` GROU P PHYS IC IANS OH IOHEALTH 250 W . BR IDGE ST .SHEET ) (SEE NOTE ON EXISTING STONE WALL 3 24 EDGE LINE EDGE LINE (TO BE RELOCATED) EX. 3" GAS LINE (TO REMAIN) EX. 4" GAS LINE 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SN001.dgn Sheet 5/6/2022 4:53:17 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220JMKJMKBDE-27 2GENERAL NOTES - 1THE ELEVATION SHOWN, WHICHEVER IS LOWER. FOOTINGS AT THE ABUTMENTS SHALL EXTEND A MINIMUM OF 3" INTO BEDROCK OR TO FACTORED BEARING RESISTANCE IS 16.3 KIPS PER SQUARE FOOT. STATE BEARING PRESSURE OF 16.1 KIPS PER SQUARE FOOT AT THE ABUTMENTS. THE BEARING PRESSURE OF 13.7 KIPS PER SQUARE FOOT AND A MAXIMUM STRENGTH LIMIT ABUTMENT FOOTINGS, AS DESIGNED, PRODUCE A MAXIMUM SERVICE LIMIT STATE FOUNDATION BEARING RESISTANCE: SHIMS WILL BECOME THE PROPERTY OF THE CITY OF DUBLIN. THE CONTRACT PRICE FOR ITEM 516 - „" PREFORMED BEARING PADS. ANY UNUSED TOTAL NUMBER SUPPLIED. THE DEPARTMENT WILL PAY FOR ACCEPTED QUANTITIES AT FURNISH TWO SHIMS PER BEAM. THE DEPARTMENT WILL MEASURE THIS ITEM BY THE UNDER THE ELASTOMERIC BEARING PADS WHERE REQUIRED FOR PROPER BEARING. PLACE „" THICK PREFORMED BEARING PAD SHIMS, PLAN AREA 11 INCHES BY 8 INCHES, BEARING PAD SHIMS: 5 24 SHIER-RINGS ROAD, DUBLIN, OH, 43016 (PHONE: (614) 410-4600). BIDDERS/CONTRACTORS AT THE CITY OF DUBLIN ENGINEER'S OFFICE, 5800 PLANS OF THE EXISTING BRIDGE AND ROADWAY MAY BE EXAMINED BY PROSPECTIVE BEEN VERIFIED IN THE FIELD. FOR ALL PROJECT WORK BASED UPON ACTUAL DETAILS AND DIMENSIONS THAT HAVE EXAMINATION OF THE EXISTING STRUCTURE. HOWEVER, THE DEPARTMENT WILL PAY RECOGNITION OF THE UNCERTAINTIES DESCRIBED ABOVE AND UPON A PREBID C&MS SECTIONS 102.05 AND 105.02. BASE CONTRACT BID PRICES UPON A BE CONSIDERED TENTATIVE AND APPROXIMATE. THE CONTRACTOR IS REFERRED TO INDICATIVE OF THE EXISTING STRUCTURE AND THE PROPOSED WORK BUT THEY SHALL FROM FIELD OBSERVATIONS AND MEASUREMENTS. CONSEQUENTLY, THEY ARE STRUCTURE HAVE BEEN OBTAINED FROM PLANS OF THE EXISTING STRUCTURE AND DETAILS AND DIMENSIONS SHOWN ON THESE PLANS PERTAINING TO THE EXISTING EXISTING STRUCTURE VERIFICATION: SHEETS . STAGED CONSTRUCTION SEQUENCE FOR THE PROPOSED BRIDGE WORK IS GIVEN ON COORDINATED WITH OVERALL PROJECT MAINTENANCE OF TRAFFIC PLANS. THE THE PROPOSED BRIDGE WORK (INCLUDING THE APPROACH SLABS) SHALL BE STAGE CONSTRUCTION AND MAINTENANCE OF TRAFFIC: 6 24 FOR PROVIDING AN ALTERNATE DESIGN. ASSOCIATED WITH TEMPORARY SHORING. NO ADDITIONAL PAYMENT WILL BE MADE LONGER NECESSARY FOR SPECIFIC CONSTRUCTION PHASE AND ALL OTHER ITEMS WELDING, TEMPORARY SHEET PILING, REMOVAL OF ALL COMPONENTS AFTER NO REQUIRED TO INSTALL LAGGING, PLATES, ANGLES, CONCRETE ANCHORS, FIELD SHAFTS), CONCRETE, LOW STRENGTH MORTAR, LOW STRENGTH MORTAR REMOVAL AS PLAN AND SHALL INCLUDE SOLDIER PILES, LAGGING, PREBORED HOLES (DRILLED CONTRACT LUMP SUM PRICE FOR COFFERDAMS AND EXCAVATION BRACING, AS PER DEPARTMENT WILL PAY FOR THE TEMPORARY SUPPORT OF THE EXCAVATION AT THE EXCAVATION, PREPARE AND PROVIDE PLANS IN ACCORDANCE WITH C&MS 501.05. THE CONSTRUCTING AN ALTERNATE DESIGN FOR THE TEMPORARY SUPPORT OF THE AN ALTERNATE DESIGN TO SUPPORT THE SIDES OF THE EXCAVATIONS. IF THE CONTRACTOR MAY CONSTRUCT THE DESIGN SHOWN ON THE PLANS OR PREPARE IS ONE REPRESENTATIVE DESIGN THAT MAY BE USED TO CONSTRUCT THE PROJECT. THE DESIGN SHOWN ON THE PLANS FOR TEMPORARY SUPPORT OF THE EXCAVATION ITEM 503, COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN: FUNCTIONAL RAILING SYSTEM. TOOLS, EQUIPMENT, AND MATERIALS NECESSARY TO CONSTRUCT A COMPLETE AND 517 RAILING, MISC.: MODIFIED TST-1-99 RAILING AND SHALL INCLUDE ALL LABOR, PAYMENT FOR THE ABOVE WORK SHALL BE MADE AT THE UNIT PRICE BID FOR ITEM PAINTING. FOR APPROVAL TO THE CITY ENGINEER IF POWDER COATING IS USED IN LIEU OF POWDER COATING COMPANY. SPECIFICATIONS AND PAINT CHIP SHALL BE SUBMITTED OR EXCEED THE PAINTING REQUIREMENTS. THOMARIOS IN AKRON IS AN APPROVED IN LIEU OF PAINTING WILL BE ACCEPTABLE IF PROCESSES AND MATERIALS EQUAL POWDER COATING: POWDER COATING OF ALL GALVANIZED GUARDRAIL COMPONENTS PAINTED. SUITABLE FOR USE ON GALVANIZED METAL. THE WOOD POSTS SHALL NOT BE THICKNESS FOR EACH COAT. PAINT SHALL BE HIGH QUALITY, ALL WEATHER PAINT PAINT SHALL BE APPLIED IN TWO COATS, EACH WITH A MINIMUM 2.0 MILL DRY FILM UNIFORM, CONSISTENT, AND EVEN APPLICATION ON THE SURFACE. SHER-CRYL THE STEEL GUARDRAIL AND STEEL HARDWARE. EACH COAT TO BE APPLIED IN A AFTER PRIMER, APPLY TWO COATS OF SHER-CRYL PAINT BY SHERWIN-WILLIAMS ON WITH PRO-CRYL PRIMER IN A UNIFORM, CONSISTENT, AND EVEN APPLICATION. SHERWIN-WILLIAMS ON ALL GALVANIZED SURFACES. PAINT ALL METAL SURFACES COMMERCIAL STORE 614-299-2116. FIRST, USE PRIMER PAINT COAT PRO-CRYL BY PAINTED WOLF GREY AS SUPPLIED BY SHERWIN-WILLIAMS PAINT - KING AVENUE PAINTING: ALL STEEL GUARDRAIL SURFACES AND STEEL HARDWARE SHALL BE RAILINGS ARE MODIFIED TST-1-99 RAILING. ITEM 517 RAILING, MISC,: MODIFIED TST-1-99 RAILING: CITY OF DUBLIN FOR SEALER COLOR PREFERENCES. SEALED WITH EPOXY-URETHANE SEALER PER ITEM 512. CONTRACTOR SHALL CONTACT BRIDGE ABUTMENT AND WINGWALL SURFACES AS SHOWN IN THE PLANS SHALL BE ITEM 512 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE): THICK. MONOLITHIC WEARING SURFACE IS ASSUMED, FOR DESIGN PURPOSES, TO BE 1 INCH STEEL DRIP STRIP 2• IN CONCRETE COVER EPOXY COATED REINFORCING STEEL DECK PROTECTION METHOD: INITIAL STRESS = 202.5 KSI (LOW RELAXATION STRANDS) ULTIMATE STRENGTH = 270 KSI AREA = .153 SQ. IN. PRESTRESSING STRAND: COMPRESSIVE STRENGTH (RELEASE) - 5.0 KSI COMPRESSIVE STRENGTH (FINAL) - 7.0 KSI CONCRETE FOR PRESTRESSED BEAMS: STEEL H-PILES - ASTM A572 - YIELD STRENGTH 50 KSI REINFORCING STEEL - MINIMUM YIELD STRENGTH 60 KSI CONCRETE CLASS COC 1- COMPRESSIVE STRENGTH 4.0 KSI (SUBSTRUCTURE) CONCRETE CLASS COC 2 - COMPRESSIVE STRENGTH 4.5 KSI (SUPERSTRUCTURE) DESIGN DATA: FUTURE WEARING SURFACE (FWS) OF 60 PSF (5" OF ASPHALT) HL-93 DESIGN LOADING: 1.3.5 AND THE ODOT BRIDGE DESIGN MANUAL, 2020 IN ACCORDANCE WITH THE AASHTO LRFD BRIDGE DESIGN SPECIFICATIONS, ARTICLE A LOAD MODIFIER OF 1.0 HAS BEEN ASSUMED FOR THE DESIGN OF THIS STRUCTURE OPERATIONAL IMPORTANCE: TRANSPORTATION OFFICIALS, 2020 AND THE ODOT BRIDGE DESIGN MANUAL, 2020. SPECIFICATIONS" ADOPTED BY THE AMERICAN ASSOCIATION OF STATE HIGHWAY AND THIS STRUCTURE CONFORMS TO THE 9TH EDITION OF THE "LRFD BRIDGE DESIGN DESIGN SPECIFICATIONS: NONE AND TO THE FOLLOWING SUPPLEMENTAL SPECIFICATIONS: TST-1-99 REVISED 1-15-21 PSBD-2-07 REVISED 7-20-18 PCB-91 REVISED 7-17-20 DS-1-92 REVISED 7-18-03 BD-1-11 REVISED 07-20-18 AS-2-15 REVISED 1-18-19 AS-1-15 REVISED 7-17-15 REFER TO THE FOLLOWING ODOT STANDARD BRIDGE DRAWINGS: REMOVE ABUTMENTS TO LIMITS SHOWN ON SHEET . EXISTING BRIDGE. STEEL SUPPORTS SHALL REMAIN IN PLACE WHILE TRAFFIC IS PRESENT ON THE ABUTMENT IN SUCH A MANNER AS TO NOT DISTURB THE STEEL SUPPORTS. EXISTING THE CONTRACTOR SHALL TAKE CARE TO REMOVE PORTIONS OF THE EXISTING REAR EXTERNAL STEEL SUPPORTS HAVE BEEN ADDED AT THE EXISTING REAR ABUTMENT. C&MS 501.05. RETAINED IN THE REBUILT STRUCTURE. SUBMIT CONSTRUCTION PLANS ACCORDING TO SHALL NOT BE PLACED IN DIRECT CONTACT WITH REINFORCING STEEL THAT IS TO BE SHALL NOT BE HEAVIER THAN THE NOMINAL 90-POUND CLASS. PNEUMATIC HAMMERS DAMAGE THE EXISTING REINFORCING STEEL TO BE PRESERVED. CHIPPING HAMMERS ENGINEER. PERFORM ALL WORK IN A MANNER THAT WILL NOT CUT, ELONGATE OR THE METHOD OF REMOVAL AND THE WEIGHT OF HAMMER SHALL BE APPROVED BY THE USE OF EXPLOSIVES, HEADACHE BALLS AND/OR HOE-RAMS WILL NOT BE PERMITTED. FINAL CONSTRUCTION AND ARE DIRECTED TO BE REMOVED BY THE ENGINEER. THE AND MISCELLANEOUS ITEMS THAT ARE NOT SHOWN TO BE INCORPORATED INTO THE REMOVED INCLUDE ALL EXISTING MATERIALS BEING REPLACED BY NEW CONSTRUCTION NOTES AND THAT ARE NOT SEPARATELY LISTED FOR PAYMENT. ITEMS TO BE THIS ITEM SHALL INCLUDE THE ELEMENTS INDICATED IN THE PLANS AND GENERAL ITEM 202, STRUCTURE REMOVED, AS PER PLAN: BOTTOM OF THE DIAPHRAGMS. THE ABUTMENTS, AND THE EXPANDED POLYSTYRENE FILLER USED TO FORM THE THIS ITEM SHALL INCLUDE THE BRIDGE DECK, SIDEWALK, THE END DIAPHRAGMS AT ITEM 511 CLASS COC 2 CONCRETE, SUPERSTRUCTURE: GENERAL NOTES: 2 66 ITEMS. CMS), 2018 EDITION, AND ANY SUPPLEMENTS THERETO, SHALL GOVERN ALL BRIDGE THE CITY OF COLUMBUS CONSTRUCTION AND MATERIAL SPECIFICATIONS (C.O.C. ADDITIONAL TO THE BRIDGE GENERAL NOTES LISTED HERE. THE CONTRACTOR IS REFERRED TO SHEET FOR GENERAL NOTES IN 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SN002.dgn Sheet 5/6/2022 4:53:17 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220JMKJMKBDE-28 3GENERAL NOTES - 2CONNECTORS SHALL CONFORM WITH ITEM 509. MATERIAL THAT MEET THE SPECIFICATIONS. MAY BE REPAIRED AS DIRECTED BY THE ENGINEER OR THEY SHALL BE REPLACED WITH NOT MEET SPECIFICATIONS WITH RESPECT TO COLOR, CONTINUITY AND UNIFORMITY SPECIFICATIONS. COATINGS WHICH HAVE BEEN DAMAGED OR WHICH OTHERWISE DO COATED. COATING FOR BOTH CONNECTORS AND BARS SHALL CONFORM TO THE SAME CONNECTOR AND DOWEL BARS USED WITH EPOXY COATED BARS SHALL BE EPOXY RECOMMENDED PROCEDURE. PROVIDED. INSTALLATION OF CONNECTOR SHALL CONFORM WITH MANUFACTURER'S AN APPROVED TYPE OF MECHANICAL CONNECTOR FOR REINFORCING BARS SHALL BE MECHANICAL CONNECTORS: WP = WORK POINT U.N.O. = UNLESS NOTED OTHERWISE TYP. = TYPICAL T.O.R. = TOP OF ROCK T/R = TOP OF ROCK T&B = TOP & BOTTOM STD. = STANDARD STA. = STATION SPA. = SPACES SHLDR. = SHOULDER S.O. = SERIES OF RT. = RIGHT RF = RIGHT FORWARD RAD. = RADIUS R.A. = REAR ABUTMENT P.V.I. = POINT OF VERTICAL CURVE INTERSECTION PEJF = PREFORMED EXPANSION JOINT FILLER PCPP = PERFORATED CORRUGATED PLASTIC PIPE PCB = PORTABLE CONCRETE BARRIER O.C. = ON-CENTER o/o = OUT-TO-OUT N.F. = NEAR FACE NPCPP = NON-PERFORATED CORRUGATED PLASTIC PIPE MOT = MAINTENANCE OF TRAFFIC MIN. = MINIMUM MAX. = MAXIMUM M.E. = MATCH EXISTING M.C. = MECHANICAL CONNECTOR LT. = LEFT F.F. = FAR FACE F.A. = FORWARD ABUTMENT f/f = FACE-TO-FACE EQ. = EQUAL EL. = ELEVATION E.F. = EACH FACE DWG. = DRAWING DIA. = DIAMETER CONST. = CONSTRUCTION CMS = CONSTRUCTION AND MATERIAL SPECIFICATIONS CLR. = CLEAR C.J. = CONSTRUCTION JOINT c/c = CENTER-TO-CENTER BRGS. = BEARINGS BOT. = BOTTOM A.S. = APPROACH SLAB ABUT. = ABUTMENT 5 66 COORDINATING THEIR WORK WITH THE RESPECTIVE UTILITY OWNERS. RESPONSIBLE FOR LOCATING AND CONFIRMING ALL UTILITIES ON THIS PROJECT, AND INTEREST IN UTILITIES IN THE AREA OF THIS PROJECT. THE CONTRACTOR IS SEE SHEET FOR A LIST OF THE KNOWN CONTACTS THAT HAVE AN TO THE PROJECT OR CITY OF DUBLIN. EXECUTING) THE NECESSARY REPAIRS AS SOON AS POSSIBLE AT NO ADDITIONAL COST CONTRACTOR SHALL COORDINATE, FUND, AND EXECUTE (OR ASSIST THE UTILITY IN UTILITY COMPANY. UNDER THE GUIDANCE OF THE AFFECTED UTILITY, THE IMMEDIATELY STOP WORK, NOTIFY THE ENGINEER, AND CONTACT THE AFFECTED IN THE EVENT THAT EXISTING UTILITIES BECOME DAMAGED, THE CONTRACTOR SHALL INCLUDING UTILITIES THAT MAY NOT HAVE ALREADY BEEN IDENTIFIED. IDENTIFY, AND AVOID INTERFERENCE WITH ANY AND ALL EXISTING UTILITIES UTILITY PROTECTION. IT IS THE CONTRACTOR'S RESPONSIBILITY TO LOCATE, EXERCISE ADDITIONAL CARE, AND SHALL ESTABLISH AND EXECUTE A MEANS OF DURATION OF THE PROJECT. THE CONTRACTOR IS TO BE AWARE OF THIS, SHALL PLANS. SOME OF THE UTILITIES ARE TO REMAIN IN SERVICE THROUGHOUT THE NUMEROUS UTILITIES EXIST WITHIN THE PROJECT LIMITS AND ARE SHOWN ON THE UTILITIES ENGINEER. COMPLETE THIS ITEM OF WORK AS DESCRIBED AND TO THE SATISFACTION OF THE SHALL INCLUDE ALL TOOLS, LABOR, EQUIPMENT AND MATERIALS NECESSARY TO CONTRACT PRICE BID LUMP SUM FOR ITEM SPECIAL - PROTECTION OF UTILITIES. THIS PAYMENT FOR ACCEPTED QUANTITIES, COMPLETE IN PLACE, SHALL BE MADE AT THE ONLY SMALL HAND OPERATED EQUIPMENT. COMPACTION OF MATERIAL WITHIN 5 FEET OF THE UTILITIES SHALL BE DONE USING LATERALLY AND VERTICALLY TO PROVIDE 6" CLEARANCE BETWEEN ADJACENT DUCTS. ADJUST REINFORCING STEEL AS NECESSARY TO AVOID DUCTS. SPACE DUCTS WEIGHT OF THE CONCRETE DOES NOT BEAR ON THE UTILITY CONDUIT OR CABLE. MOVEMENT OF THE CONDUIT OR CABLE WITHIN THE DUCTS AND TO ENSURE THAT THE SUBSTRUCTURE CONCRETE. SPLIT DUCTS SHALL BE SIZED TO ALLOW FOR FREE UTILITY CONDUITS ARE TO BE ENCASED USING SPLIT DUCTS AND CAST INTO THE BID ITEM. PROVIDED AS DIRECTED BY THE ENGINEER AND ARE INCLUDED IN THE COST OF THIS TEMPORARY SUPPORT AND/OR PROTECTION OF EXPOSED UTILITIES SHALL BE SUPERVISION OF AN AUTHORIZED UTILITY REPRESENTATIVE. THEIR PRECISE LOCATION IS CONFIRMED AND SHALL BE PERFORMED ONLY UNDER CLOSER THAN 3 FEET FROM THE UTILITIES SHALL BE PERFORMED BY HAND UNTIL AND APPROVED BY THE ENGINEER PRIOR TO COMMENCING ANY WORK. EXCAVATING PLANS FOR EXCAVATION NEAR UTILITIES MUST BE SUBMITTED BY THE CONTRACTOR LOCATIONS. HORIZONTAL AND VERTICAL POSITION OF THE UTILITIES AT SUBSTRUCTURE DEPICTION OF EXISTING SUBSURFACE UTILITY DATA, TO DETERMINE THE PRECISE IN ACCORDANCE WITH ASCE 38-02, STANDARD GUIDELINES FOR THE COLLECTION AND EQUIPMENT SUCH AS SMALL TEST HOLE VACUUM EXCAVATION USING THE AIR METHOD QUALITY LEVEL "A" UTILITY INFORMATION. USE MINIMALLY INVASIVE EXCAVATION USE A PREQUALIFIED SUBSURFACE UTILITY ENGINEERING (SUE) COMPANY TO OBTAIN OF THE PROJECT. RESPONSIBILITY TO PROTECT THESE UTILITIES AND COMPONENTS FOR THE DURATION AFTER THE PROJECT REMOVALS AND CONSTRUCTION. IT IS THE CONTRACTOR'S THE AT&T FIBER OPTIC AND TWO COPPER LINES ARE TO REMAIN IN USE DURING AND HEREIN AND AS DIRECTED BY THE ENGINEER. EQUIPMENT TO PROTECT EXISTING UTILITIES DURING CONSTRUCTION AS DESCRIBED THIS ITEM SHALL CONSIST OF FURNISHING ALL NECESSARY LABOR, MATERIALS, AND ITEM SPECIAL - PROTECTION OF UTILITIES: 1 24 LEGEND: SATISFACTION OF THE ENGINEER. NECESSARY TO COMPLETE THIS ITEM OF WORK AS DESCRIBED AND TO THE STONE WALL. THIS SHALL INCLUDE ALL TOOLS, LABOR, EQUIPMENT AND MATERIALS CONTRACT PRICE BID LUMP SUM FOR ITEM SPECIAL - RELOCATION OF EXISTING PAYMENT FOR ACCEPTED QUANTITIES, COMPLETE IN PLACE, SHALL BE MADE AT THE EXISTING WALL AS DIRECTED BY THE ENGINEER. ENGINEER OR CITY OF DUBLIN. THE WALL SHALL BE RECONSTRUCTED SIMILAR TO THE BOULDERS AT THE EXISTING REAR ABUTMENT UNLESS DIRECTED TO DO SO BY THE THE CONTRACTOR SHALL NOT DISPOSE OF ANY SANDSTONE BLOCKS OR OTHER LARGE AESTHETICALLY PLEASING TERMINATION. EXTEND UNDER THE BRIDGE BEYOND THE LENGTH NECESSARY TO PROVIDE AN ABUTMENT. BOTH COURSES SHALL END IN FRONT OF THE ABUTMENT BUT SHALL NOT PLEASING TRANSITION TOWARDS THE WEST CORNER OF THE PROPOSED REAR SHALL TIE INTO THE EXISTING WALL SUCH AS TO PROVIDE AN AESTHETICALLY DETERMINE THE EXACT LOCATION OF THE RELOCATED WALL. THE RELOCATED WALL THE CONTRACTOR SHALL WORK WITH THE ENGINEER AND THE CITY OF DUBLIN TO WALL SHALL BE RELOCATED AS SHOWN ON SHEET . RELOCATION OF ANY UTILITIES UNDER THE WALL, THE REMOVED PORTION OF THE ABUTMENT. AFTER CONSTRUCTION OF THE PROPOSED REAR ABUTMENT AND EXISTING BRIDGE REAR ABUTMENT PRIOR TO CONSTRUCTION OF THE PROPOSED REAR BLOCKS. THE STONE WALL SHALL BE REMOVED FOR APPROXIMATELY 35' FROM THE THE WALL CONSISTS OF TWO COURSES OF APPROXIMATELY 22"H x 36"D x 60"L STONE A SANDSTONE WALL EXISTS AT THE SOUTHWEST CORNER OF THE EXISTING BRIDGE. DESCRIBED HEREIN AND AS DIRECTED BY THE ENGINEER. OF THE REAR ABUTMENT AND RELOCATION OF ANY UTILITIES UNDER THE WALL AS THE BRIDGE DURING CONSTRUCTION AND CONSTRUCT THE WALL AFTER CONSTRUCTION EQUIPMENT TO REMOVE THE EXISTING STONE WALL AT THE SOUTHWEST CORNER OF THIS ITEM SHALL CONSIST OF FURNISHING ALL NECESSARY LABOR, MATERIALS, AND ITEM SPECIAL - RELOCATION OF EXISTING STONE WALL: 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SQ001.dgn Sheet 5/6/2022 4:53:18 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220ESTIMATED QUANTITIES29BDEKK JMK4 ITEM DESCRIPTION TOTAL UNIT ESTIMATED QUANTITES SPECIAL SPECIAL 613 601 526 526 518 518 518 518 517 516 516 516 516 515 515 512 512 511 511 511 511 510 509 503 503 202 LUMP LUMP CU YD CU YD FT SQ YD FT FT FT CU YD FT EACH FT SQ FT SQ FT EACH EACH SQ YD SQ YD CU YD CU YD CU YD CU YD EACH POUND CU YD LUMP LUMP RELOCATION OF EXISTING STONE WALL PROTECTION OF UTILITIES LOW STRENGTH MORTAR BACKFILL (TYPE 2) ROCK CHANNEL PROTECTION, TYPE C WITH FABRIC FILTER TYPE A INSTALLATION REINFORCED CONCRETE APPROACH SLABS (T=13"), AS PER PLAN 6" NON-PERFORATED CORRUGATED PLASTIC PIPE INCLUDING SPECIALS 6" PERFORATED CORRUGATED PLASTIC PIPE SPECIAL - STEEL DRIP STRIP POROUS BACKFILL WITH GEOTEXTILE FABRIC RAILING, MISC.: MODIFIED TST-1-99 RAILING ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LOAD PLATE (NEOPRENE) (•" THICK) SEMI-INTEGRAL ABUTMENT EXPANSION JOINT SEAL 2" PREFORMED EXPANSION JOINT FILLER •" PREFORMED EXPANSION JOINT FILLER PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEMBERS, LEVEL 1, CB17-48 (44'-0" LENGTH) PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEMBERS, LEVEL 1, CB17-36 (44'-0" LENGTH) TYPE 2 WATERPROOFING SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) CLASS COC 2 CONCRETE, SIDEWALK CLASS COC 1 CONCRETE, FOOTING CLASS COC 1 CONCRETE, ABUTMENT NOT INCLUDING FOOTING CLASS COC 2 CONCRETE, SUPERSTRUCTURE DOWEL HOLES WITH CEMENT GROUT EPOXY COATED REINFORCING STEEL UNCLASSIFIED EXCAVATION INCLUDING ROCK COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN STRUCTURE REMOVED, AS PER PLAN 1 1 10 75 125 230 9 139 46 77 196 52 131 95 28 12 1 21 227 11 108 106 68 192 26,748 626 1 1 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SC001.dgn Sheet 5/6/2022 4:53:19 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220JMKBDE-30 5 KKPHASED CONSTRUCTION DETAILSLEGEND: PHASE 1 REMOVAL PHASE 1 CONSTRUCTION PHASE 2 REMOVAL PHASE 2 CONSTRUCTION PHASE 3 CONSTRUCTION SHLDR. 1'-0" SHLDR. 1'-0" (TYP. OF 6) B17-48 BOX BEAM (TYP. OF 12) B17-48 BOX BEAM B17-36 BOX BEAM 4'-0"` PER SEGMENT) 2' PCB (2 ANCHORS SHLDR. 9" PER SEGMENT) 2' PCB (2 ANCHORS PER SEGMENT) 2' PCB (2 ANCHORS C.J. 2' PCB (UNANCHORED) = LIMITS OF REMOVAL SHLDR. 9"` SHLDR. 9"` PHASE 2 CONSTRUCTION 27'-3•" SHAWAN FALLS DR. \ CONSTRUCTION SHAWAN FALLS DR. \ CONSTRUCTION SHAWAN FALLS DR. \ CONSTRUCTION MOT LANE 11'-0" MOT LANE 11'-0" SEE NOTE 2 3•" (MINUS FIT-UP) (SEE NOTE 3) PER SEGMENT) 2' PCB (2 ANCHORS SEE NOTE 2 NOTES: SEE NOTE 1 SHAWAN FALLS DR. \ CONSTRUCTION SHOULDER 1'-0" PLUS FIT-UP 24'-0" PLUS FIT-UP SHOULDER 1'-0" PLUS FIT-UP 51'-3•" PLUS FIT-UP 7'-3•" SIDEWALK PLUS FIT-UP 16'-0" 35'-3•" PLUS FIT-UP SEE NOTE 4 20 24 4. 3. 2. 1. SEE NOTE 4 MOT LANE 10'-0" MOT LANE 10'-0" MOT LANE 10'-0" MOT LANE 10'-0" SHLDR. 9" SHAWAN FALLS DR. \ CONSTRUCTION INSTALL RAILING ANCHOR PLATE IN DECK DURING PHASE 1 DECK PRIOR TO PHASE 3 CONSTRUCTION. PORTABLE CONCRETE BARRIER AND REPAIR ANCHOR HOLES IN AFTER PHASE 2 CONSTRUCTION IS COMPLETE, REMOVE WITH BEAMS ADJACENT TO B6 AND WORKING OUTWARDS. ACCURATELY PLACE B6 FIRST. SET OTHER BEAMS STARTING PROVIDE MOT LANES AND SHOULDERS AS SHOWN. ALSO REMOVE PORTIONS OF WINGWALLS AS NECESSARY TO REMOVE EXISTING CURB PRIOR TO ESTABLISHING PHASE 1 MOT. LAGGING WALL TEMPORARY SOLDIER PILE AND LAGGING WALL TEMPORARY SOLDIER PILE AND TEMPORARY RAILING TEMPORARY RAILING TEMPORARY RAILING AND SIDEWALK TO ANCHORS IN BEAMS, DECK INSTALL PERMANENT RAILING FROM ANCHORS IN BEAMS AND REMOVE TEMPORARY RAILING THAT THE REMAINING BEAMS ARE TIED TOGETHER. DO NOT CUT ANY OTHER TIE RODS TO ENSURE CUT TIE RODS AT THIS JOINT AS NECESSARY. EXISTING BRIDGE 28'-0"` 16'-0"` 12'-0"` PHASE 1 CONSTRUCTION 24'-0" PLUS FIT-UP 3'-0"` 24'-0"` 16'-0"` 35'-3•" PLUS FIT-UP MOT LANE 10'-0" MOT LANE 10'-0" PHASE 2 REMOVAL 24'-0"` 3'-0"` 24'-0" PLUS FIT-UP SHLDR. 1'-0" MOT LANE 10'-0" MOT LANE 10'-0" SHLDR. 1'-0" AND FINAL COURSE ON BRIDGE. SEE MOT PLANS FOR PLACEMENT OF INTERMEDIATE COURSE SEE ODOT STD. DWG PCB-91 FOR ADDITIONAL DETAILS. POURED AND THE RAILING ATTACHED. WELDED STUDS AND SLEEVE NUTS THE SIDEWALK CAN BE TO THE ANCHOR PLATE. AFTER THE INSTALLATION OF THE END TOP END WELDED STUDS AND SLEEVE NUTS SHALL BE WELDED MOT TRAFFIC IS SHIFTED FOR PHASE 3 CONSTRUCTION, THE CONSTRUCTION AS SHOWN ON SHEET . AFTER THE 6. 5. 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SV001.dgn Sheet 5/6/2022 4:53:20 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220NN JMKBDE-31 6 KKREMOVAL DETAILS2'-2"` 1'-2"` 10'-0"`1'-0"`1'-0"` ABUTMENT SECTION - REMOVALS SEE NOTE 21'-0"`9"`VARIESVARIES, 9'-0"` MAX.FORWARD ABUTMENT PLAN - REMOVALSAFTER PHASE 1 BEAM REMOVAL OF SUPERSTRUCTURE SLAB SAWCUT AND EDGE EXISTING APPROACH SHORING PILE AND LAGGING TEMPORARY SOLDIER TO INSTALL LAGGING A.S. SEAT AS NECESSARY REMOVE PORTIONS OF LINE SAWCUT REAR ABUTMENT PLAN - REMOVALS 6'-11"`6' -11"`17' -11"` 35'-6"` 1'-2"` 1'-4" 10"REMOVALS P HAS E 1REMOVALS P HAS E 2 13'-0"` SEE NOTE 2 8'-0"`SHAWAN FALLS DR. \ CONSTRUCTION **1' -2"` 6'-11"`6'-11"`16' -11"` 34'-4"` 18'-1"` 1'-2"`1'-2"`AFTER PHASE 1 BEAM REMOVAL OF SUPERSTRUCTURE SLAB SAWCUT AND EDGE EXISTING APPROACH SHORING PILE AND LAGGING TEMPORARY SOLDIER 10" 1'-4" TO INSTALL LAGGING A.S. SEAT AS NECESSARY REMOVE PORTIONS OF LINE SAWCUT FORWARD ABUTMENT ELEVATION- REMOVALS FORWARD ABUTMENT PLAN - REMOVALSREMOVALS P HAS E 2REMOVALS P HAS E 1 SEE NOTE 2 8'-0"` SHAWAN FALLS DR. \ CONSTRUCTION ** LINE SAWCUT VARIES11'-0"`PHASE 1 REMOVALSPHASE 2 REMOVALS REAR ABUTMENT ELEVATION- REMOVALS9'-0"`(SEE NOTE 4) OF SUPERSTRUCTURE AFTER PHASE 1 BEAM REMOVAL EXISTING APPROACH SLAB SAWCUT AND EDGE 1'-0"` SHEAR KEY SEE NOTE 3 EXISTING STEEL SUPPORTS PHASE 2 REMOVALSPHASE 1 REMOVALS 9'-0"`FORWARD ABUTMENT ELEVATION- REMOVALS (SEE NOTE 4) OF SUPERSTRUCTURE AFTER PHASE 1 BEAM REMOVAL EXISTING APPROACH SLAB SAWCUT AND EDGE VARIES 11'-0"`1'-0"` SHEAR KEY LINE SAWCUT LEGEND: NOTES: = LIMITS OF REMOVAL 5 244. 3. 2. 1. 3 24SHEET FOR ADDITIONAL INFORMATION. REMAIN, SEE PROTECTION OF UTILITIES NOTE ON APPROXIMATE LOCATION OF AT&T UTILITY LINES TO ** = REUSE EXISTING TIE RODS AS SHOWN ON SHEET . REAR ABUTMENT TO NOT DAMAGE THE STEEL SUPPORTS. CONTRACTOR SHALL TAKE CARE DURING PHASE 1 REMOVAL OF THE PLACE UNTIL TRAFFIC IS SHIFTED TO THE NEW STRUCTURE. THE EXISTING STEEL SUPPORTS AT THE REAR ABUTMENT ARE TO REMAIN IN EXISTING FOOTING PORTIONS WITH TYPE 2 LOW STRENGTH MORTAR. VOIDS BETWEEN THE PROPOSED FOOTING AND ADJACENT ROCK OR NOT EXTEND ABOVE THE TOP OF THE PROPOSED FOOTING. FILL ANY FOOTINGS. ANY REMAINING PORTIONS OF THE EXISTING FOOTING SHALL REMOVE ONLY THE PORTIONS REQUIRED TO CONSTRUCT THE PROPOSED THE CONTRACTOR MAY REMOVE THE ENTIRE EXISTING FOOTING OR ABUTMENT AND TO EXCAVATE FOR NEW SLOPES. REMOVED AS NECESSARY TO ALLOW FOR CONSTRUCTION OF PROPOSED ALL DIMENSIONS ARE APPROXIMATE. EXISTING ABUTMENTS SHALL BE 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SH001.dgn Sheet 5/6/2022 4:53:21 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220NNJMKJMKBDE-32 7 NOTES: PROCEDURE:TEMPORARY SHORING REPRESENTATIVE DESIGN DETAILS - 1 APPROACH SLAB SUPERSTRUCTURE AND CONSTRUCTION EDGE OF PHASE 1 PHASE 1 LAGGING LAGGING PHASE 2 REAR ABUTMENT TEMPORARY SHORING PLAN SHAWAN FALLS DR. \ CONSTRUCTION 101+50 B B A A HOLE (TYP.) 2'-0" DIA. PREBORED VIEW A-A AFTER PHASE 1 REMOVALS, PRIOR TO PHASE 1 CONSTRUCTION VIEW B-B AFTER PHASE 1 CONSTRUCTION, PRIOR TO PHASE 2 REMOVALS PHASE 1 LAGGING 10'-0"` PHASE 1 LAGGING 10'-0" PHASE 2 LAGGING 7'-6"` PHASE 1 LAGGING 10'-0" LEFT IN PLACE SEE NOTE 3) LAGGING (TYP., BY ENGINEER APPROVED METHOD ANCHOR LAGGING IN THIS AREA OF A.S.) ABOVE BOTTOM PLATE (EXTEND L6x6x… LAGGING TO A.S. ABOVE ANGLE, ATTACH(TYP.)9'-8"SEE DETAIL F SEE DETAIL E SEE DETAIL G P1 P2 PHASE 1 BEAM REMOVAL SUPERSTRUCTURE AFTER SAWCUT AND EDGE OF EXISTING APPROACH SLAB FOOTINGPROPOSED AND A.S. SEAT PROPOSED STEM PHASE 2 CONSTRUCTIONPHASE 1 MOTPHASE 2 MOTPHASE 1 CONSTRUCTIONEXISTING FOOTING AND A.S. SEAT EXISTING STEM 10'-0"(TYP.)10'-0"(TYP.)AND PLATE TO INSTALL LAGGING A.S. SEAT AS NECESSARY REMOVE PORTIONS OF EL. 847.7` OF ROCK ASSUMED TOP CONTRACTOR) (TO BE DETERMINED BY BEHIND LAGGING EXCAVATION LINE APPROXIMATE (TYP., SEE NOTE 2) SOILDER PILE CONTRACTOR) (TO BE DETERMINED BY BEHIND LAGGING EXCAVATION LINE APPROXIMATE (TYP., SEE NOTE 2) SOILDER PILE EL. 847.7` OF ROCK ASSUMED TOP HOLE (TYP.) 2'-0" DIA. PREBORED SLAB CONSTRUCTION) TO COMPLETE APPROACH (REMOVE AS NECESSARY TEMPORARY SHORING SEE NOTE 3) LAGGING (TYP., PLACE) (LEFT IN LAGGING PHASE 1 SHORING TEMPORARY (INSTALL AS NECESSARY) TEMPORARY SHORING FORWARD ABUTMENT TEMPORARY SHORING PLAN D C D C PLACE) (LEFT IN LAGGING PHASE 1 LAGGING PHASE 2 PHASE 1 LAGGING APPROACH SLAB SUPERSTRUCTURE AND CONSTRUCTION EDGE OF PHASE 1 102+00 SHAWAN FALLS DR. \ CONSTRUCTION VIEW D-D AFTER PHASE 1 CONSTRUCTION, PRIOR TO PHASE 2 REMOVALS VIEW C-C AFTER PHASE 1 REMOVALS, PRIOR TO PHASE 1 CONSTRUCTION PHASE 1 LAGGING 12'-0" PHASE 1 LAGGING 8'-0"` PHASE 1 LAGGING 12'-0" PHASE 1 LAGGING 9'-0"` LEFT IN PLACE HOLE (TYP.) 2'-0" DIA. PREBORED OF A.S.) ABOVE BOTTOM PLATE (EXTEND (TYP., SEE NOTE 2) SOLDIER PILE HOLE (TYP.) 2'-0" DIA. PREBORED L6x6x… LAGGING TO A.S. ABOVE ANGLE, ATTACH (TYP.)9'-8"SEE DETAIL G SEE DETAIL F SEE DETAIL E P3 P4 REMOVAL AFTER PHASE 1 BEAM OF SUPERSTRUCTURE SLAB SAWCUT AND EDGE EXISTING APPROACH PHASE 2 CONSTRUCTIONPHASE 1 MOTPHASE 2 MOTPHASE 1 CONSTRUCTIONEXISTING FOOTING AND A.S. SEAT EXISTING STEM AND A.S. SEAT PROPOSED STEMFOOTINGPROPOSED 10'-0"(TYP.)10'-0"(TYP.)EL. 843.6` OF ROCK ASSUMED TOP SLAB CONSTRUCTION) TO COMPLETE APPROACH (REMOVE AS NECESSARY TEMPORARY SHORING (TYP., SEE NOTE 2) SOLDIER PILE EL. 843.6` OF ROCK ASSUMED TOP LAGGING (TYP., SEE NOTE 3) AND PLATE TO INSTALL LAGGING A.S. SEAT AS NECESSARY REMOVE PORTIONS OF LAGGING (TYP., SEE NOTE 3) CONTRACTOR) DETERMINED BY (TO BE BEHIND LAGGING EXCAVATION LINE APPROXIMATE CONTRACTOR) DETERMINED BY (TO BE BEHIND LAGGING EXCAVATION LINE APPROXIMATE TEMPORARY SHORING NECESSARY) (INSTALL AS TEMPORARY SHORING 11. 10. 9. 8. 7. 6. 5. 4. 3. 2. 1. STATION OFFSET P4 P3 P2 P1 102+31.00 102+19.00 101+58.00 101+48.00 DRILLED SHAFT LOCATIONS 9.67' L 9.67' L 9.67' L 9.67' L SHAFT 2 24 8 245. 4. 3. 2. 1. SEE SHEET FOR DETAILS E, F, & G. TO PLACE THE LAGGING. AROUND THE SOLDIER PILES SHALL BE REMOVED AS NECESSARY LOW STRENGTH MORTAR IS WORKABLE. LOW STRENGTH MORTAR REQUIREMENTS OF C&MS 524.04.C WHILE THE CONCRETE AND OF THE PILES. TEMPORARY CASING SHALL BE REMOVED PER THE OF THE PREBORED HOLE (DRILLED SHAFTS) AND INSTALLATION CASING IN ACCORDANCE WITH C&MS 524.06 FOR CONSTRUCTION STRENGTH MORTAR PER C&MS ITEM 613. PROVIDE TEMPORARY REMAINDER OF THE HOLE SHALL BE FILLED WITH TYPE 2 LOW SHALL BE …" INCH NOMINAL MAXIMUM SIZE. IF NECESSARY, THE AND 524.11 EXCEPT THAT THE AGGREGATE IN THE CONCRETE MIX LAGGING, AND SHALL MEET THE REQUIREMENTS OF C&MS 524.10 PRIOR TO EXCAVATION AND THE INSTALLATION OF THE TIMBER 499, SHALL HAVE A MINIMUM CYLINDER STRENGTH OF 4.5 KSI TOP OF ROCK. CONCRETE SHALL BE CLASS COC 5 PER C&MS (DRILLED SHAFT) IT SHALL BE FILLED WITH CONCRETE TO THE AFTER THE PILE IS SET IN THE CENTER OF THE PREBORED HOLE WILL BE ACCEPTABLE WITH APPROVAL FROM THE ENGINEER. HARDWARE ATTACHING THE LAGGING TO THE SOLDIER PILE FACE LAGGING TO THE SOLDIER PILES. METHODS WITH APPROPRIATE CONTRACTOR CAN CHOOSE THE METHOD OF ATTACHING THE INCHES AND A MINIMUM BENDING STRENGTH (Fb) OF 1000 PSI. THE LAGGING SHALL BE HARDWOOD WITH A MINIMUM DIMENSION OF 3 MINIMUM SECTION MODULUS OF 79 CUBIC INCHES. STRENGTH = 50 KSI) OR AN ENGINEER APPROVED EQUAL WITH A SOLDIER PILES SHALL BE W12x65 ASTM A572 GRADE 50 (YIELD SHEET . MAY PREPARE AN ALTERNATE DESIGN. SEE ITEM 503 NOTE ON MAY BE USED TO CONSTRUCT THE PROJECT OR THE CONTRACTOR THE TEMPORARY SHORING DESIGN SHOWN IS REPRESENTATIVE AND NEW ABUTMENTS. REMOVE TEMPORARY SHORING AS NECESSARY. REMOVE TOP PORTION OF SOLDIER PILES AND LAGGING BEHIND PHASE 2 PORTIONS OF NEW BRIDGE AND APPROACH SLABS. BACKFILL PHASE 2 PROPOSED ABUTMENTS AND CONSTRUCT PROPOSED ABUTMENTS. EXCAVATE AS REQUIRED AND CONSTRUCT PHASE 2 PORTIONS OF SHEET. REMOVE THE PHASE 1 LAGGING, EXCEPT AS NOTED ON THIS REMOVE REMAINING PORTIONS OF THE EXISTING BRIDGE AND ROADWAY AND BRIDGE ONTO NEW PHASE 1 CONSTRUCTION. INSTALL PHASE 2 MOT AND TRANSFER TRAFFIC FROM EXISTING 1 PORTIONS OF NEW BRIDGE AND APPROACH SLABS. BACKFILL PHASE 1 PROPOSED ABUTMENTS AND CONSTRUCT PHASE DETAIL F. LAGGING CONNECTION TO PROPOSED ABUTMENTS AS SHOWN IN SOLDIER PILES AS NECESSARY TO INSTALL LAGGING. ATTACH ATTACHMENT METHOD. REMOVE LOW STRENGTH MORTAR FROM INSTALL PHASE 2 LAGGING WITH ENGINEER APPROVED CONSTRUCT PHASE 1 PORTIONS OF PROPOSED ABUTMENTS. REMOVE PHASE 1 PORTIONS OF EXISTING BRIDGE. REMOVAL AND PROPOSED APPROACH SLAB CONSTRUCTION. BY CONTRACTOR) TO ALLOW FOR EXISTING APPROACH SLAB SHOWN IN DETAIL E. INSTALL TEMPORARY SHORING (DESIGNED TO EXISTING ABUTMENTS AS LAGGING PROGRESSES DOWNWARD AS NECESSARY TO INSTALL LAGGING. ATTACH LAGGING CONNECTION DOWN. REMOVE LOW STRENGTH MORTAR FROM SOLDIER PILES AS ATTACHMENT METHOD AS EXCAVATION PROGRESSES FROM TOP INSTALL PHASE 1 LAGGING WITH ENGINEER APPROVED CONCRETE AND LOW STRENGTH MORTAR IS BEING PLACED. LOW STRENGTH MORTAR TO TOP OF HOLE. REMOVE CASING AS COC 5 CONCRETE UP TO LEVEL OF TOP OF ROCK AND TYPE 2 AND CONCRETE PLACEMENT. INSTALL PILES AND PLACE CLASS PROVIDE TEMPORARY CASINGS TO KEEP HOLE OPEN FOR PILE AT BOTH ABUTMENTS, PREBORE HOLES FOR SOLDIER PILES. INSTALL MOT AND CLOSE LEFT SIDE OF BRIDGE. 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SH002.dgn Sheet 5/6/2022 4:53:22 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220JMKJMKBDE-33 8TEMPORARY SHORING REPRESENTATIVE DESIGN DETAILS - 23@24 ‚ SOLDIER PILE(TYP.) LAGGING DETAIL G PERMITTED BUT NOT SHOWN) PILE FLANGES, OTHER CONFIGURATIONS (LAGGING SHOWN INSIDE SOLDIER L3x3x‚ 1'-0"` O.C. ANCHOR AT •" DIA. CONCRETE ABUTMENT PROPOSED BACK FACE OF LAGGING REQUIRED OR WEDGES AS HARDWOOD BLOCKING REQUIRED (TYP.) OR WEDGES AS HARDWOOD BLOCKING DETAIL F ABUTMENT PHASE C.J. IN L6x6x… DETAIL E1'-0"` O.C. ANCHOR AT •" DIA. CONCRETE LAGGING ABUTMENT EXISTING BACK FACE OF AFTER SAWCUT ABUTMENT END OF EXISTING DIMENSIONS) DETERMINE NECESSARY ƒ" THICK PLATE (FIELD 4"4"8…" 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SR003.dgn Sheet 5/6/2022 4:53:22 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220NN BDEBDEJMK-34 9ABUTMENT FOOTING PLAN1'-6"REAR ABUTMENT FOOTING PLAN12'-0"8'-1„" 2'-2•"1'-5•"1'-9"4'-0"11'-6†"6"5'-6"2'-1"4…" 1'-9" T Y P. PHASE 1 34'-0†" PHASE 2 31'-9"(T&B)8-A501 @ 1'-0" MAX(LAP W/ A501)7-A509 (T&B)MAX (T&B)5-A511 @ 1'-0"MAX (T&B) 7-A50 4 @ 1'-0" B (T&B)8-A512 @ 1'-0" MAX(LAP W/ A512)7-A513 (T&B)A A 28-A506 @ 1'-0" (T&B)1'-0" @ 1'-0" 2 SPA. STA. 101+73.74 | BRGS. R.A. PHASED C.J. (LAP W/ A501) A510 (T&B) A515 (T&B) A516 (T&B) A514 (T&B) OF FOOTING 1'-9" FROM FRONT FACE 3" STEP IN FOOTING, SHAWAN FALLS DR. \ CONSTRUCTION SEE NOTE 1 1'-0" WIDE CUTOFF WALL M.C. (TYP.)33°30'00"PHASE 1 CONSTRUCTIONCONSTRUCTION PHASE 2 1'-0"30-A506 @ 1'-0" (T&B) 3 24SHEET FOR ADDITIONAL INFORMATION. REMAIN, SEE PROTECTION OF UTILITIES NOTE ON APPROXIMATE LOCATION OF AT&T UTILITY LINES TO FORWARD ABUTMENT FOOTING PLAN 56°30'00"PHASE 2 34'-0" PHASE 1 30'-4…"2'-2•"1'-5•"15'-1†"5'-6"1'-6"6" TY P. 13'-2•"(T&B)8-A501 @ 1'-0" MAX(LAP W/ A501)7-A504 (T&B)(LAP W/ A501)7-A502 (T&B) A A 1'-0"29-A506 @ 1'-0" (T&B)30-A506 @ 1'-0" (T&B)1'-0" 1'-0"B (T&B) 8-A50 8 @ 1'-0" MAX 13-A506 @ 1'-0" (T&B) 7'-0" 3'-8"5'-6•"33°30'00"PHASED C.J. STA. 102+16.24 | BRGS. F.A. (LAP W/ A501) A503 (T&B) OF FOOTING 1'-9" FROM FRONT FACE 3" STEP IN FOOTING, SEE NOTE 1 SHAWAN FALLS DR. \ CONSTRUCTION (T&B)8-A501 @ 1'-0" MAXM.C. (TYP.) (LAP W/ A501 & A508) A558 (T&B) PHASE 2 CONSTRUCTIONCONSTRUCTION PHASE 1 243SHEET FOR ADDITIONAL INFORMATION. REMAIN, SEE PROTECTION OF UTILITIES NOTE ON APPROXIMATE LOCATION OF AT&T UTILITY LINES TO 1'-0" WIDE CUTOFF WALL LEGEND:NOTES: B = 1 S.O. 3-A507 @ 1'-0" (T&B) A = 1 S.O. 4-A505 @ 1'-0" (T&B) #5 BARS = 3'-1" LAP REINFORCING STEEL THE FOLLOWING MINIMUM LENGTHS: ON SHEET FOR CUTOFF WALL ELEVATIONS. TOTAL AT REAR ABUTMENT, 87 STIRRUPS TOTAL AT FORWARD ABUTMENT. SEE SECTIONS SITRRUPS ALONG ENTIRE LENGTH OF CUTOFF WALL AT 1'-0" MAX SPACING, 82 STIRRUPS 1'-0" WIDE CUTOFF WALL ALONG FRONT AND SIDE FACES OF ABUTMENT. PROVIDE A401 2. 1. 13 24 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SR001.dgn Sheet 5/6/2022 4:53:23 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220NBDEBDEJMK-35 10REAR ABUTMENT PLAN AND ELEVATIONPHASE 1 CONSTRUCTIONCONSTRUCTION PHASE 2 PHASE 1 31'-6•" PHASE 2 32'-5•" 1'-5•"14'-7•"1'-6"12'-4•"STA. 101+73.74 | BRGS. R.A.6'-10†" 5ƒ"33°30'00"TY P. 56°30'00"33°30'00" 1'-6" 3'-4"9‚" A A 1'-0"EL. 842.00 EL. 843.50 SHAWAN FALLS DR. \ CONSTRUCTION 2'-6„"SHAWAN FALLS DR. \ CONSTRUCTION 2•" THICK POLYSTYRENE EL. 853.79 LEVEL SEAT10'-6"EX. 24" SANITARY LINE REAR ABUTMENT PLAN REAR ABUTMENT ELEVATION WINGWALLS NOT SHOWN FOR CLARITY (SKEW A518 BARS AS NECESSARY AT WINGWALL AND PHASED C.J.) 33 SETS OF 1-A517 (E.F.), 1-A506 (E.F.) AND 1-A518 @ 1'-0" MAX (SKEW A518 BARS AS NECESSARY AT WINGWALL AND PHASED C.J.) 31 SETS OF 1-A517 (E.F.), 1-A506 (E.F.) AND 1-A518 @ 1'-0" MAX7-A520 (N.F.)(LAP W/ A501)7-A519 (E.F.)(LAP W/ A519)(LAP W/ A501)7-A521 (N.F.)ACOPING1'-0"BC2-D601 (E.F.) D503NECESSARY) (FIELD BEND AS (E.F.)D503 (TYP.) 2" PEJF 2-D602 NECESSARY) BEND AS 2-D601 (FIELD (E.F.) 2-D504 RELOCATED STONE WALL LEVEL C.J.LEVEL C.J. 3" CHAMFER FABRIC AND 6" DIA. PCPP (SEE NOTE 3) 2'-0" POROUS BACKFILL W/ GEOTECH 17-D801 @ 1'-6" MAX (MEASURED PERPENDICULAR TO \) 31 SETS OF 1-D501 & 1-D502 @ 1'-0" MAX 18-D801 @ 1'-6" MAX (MEASURED PERPENDICULAR TO \) 33 SETS OF 1-D501 & 1-D502 @ 1'-0" MAX 7"C.J. EL. 847.70 APPROX T.O.R. PHASED C.J. 1'-7‡" M.C. (TYP.) TYPE 2 WATERPROOFING PHASED C.J. W/ 1LWP 2LWP1'-0"1RWP 2RWP 3RWP EL. 855.63* EL. 855.57* EL. 856.69** EL. 855.69** EL. 853.30** EL. 855.90** EL. 853.17** OVERLAY TOP OF ASHPALT EL. 855.96* 4RWP (E.F.)7-A501 @ 1'-0"(E.F.)7-A501 @ 1'-0"LEVEL SEAT 4'-9•" (TYP. EACH SIDE) RAIL ANCHORAGE ON BOX BEAM FACE OF CONCRETE AND ADJACENT PROVIDE A 2" MIN. GAP BETWEEN PEJF ON FASCIA SIDE OF BEAM. CONCRETE DIRECTLY AGAINST 2" THICKNESS AS NECESSARY TO CAST AT BOX BEAMS, INCREASE WINGWALL 3 24SHEET FOR ADDITIONAL INFORMATION. REMAIN, SEE PROTECTION OF UTILITIES NOTE ON APPROXIMATE LOCATION OF AT&T UTILITY LINES TO FOOTING STEP, CUTOFF WALL, AND SUPERSTRUCTURE NOT SHOWN FOR CLARITY ALL DIMENSIONS ARE GIVEN TO THE FACE OF WALL AS SHOWN IN THE SECTIONS 1'-0" FILLET 1'-1"2'-0"END CAP END CAP END CAP3'-2‡"13 24 LEGEND:NOTES: 13 24 12 24 STA. 101+83.13, 16.60' RT. STA. 101+78.72, 16.60' RT. STA. 101+74.30, 16.60' RT. STA. 101+68.47, 17.16' RT. STA. 101+48.47, 36.27' LT. STA. 101+44.30, 36.27' LT. 4R 3R 2R 1R 2L 1L ** = ELEVATION AT CORNER OF WALL * = ELEVATION AT | BEARINGS AT TOP OF CONCRETE FOR BAR PLACEMENT. ¬ = BARS ARE IN COPING. SEE SECTION A-A ON SHEET C = 6-A519 ¬ (LAP W/ A501) B = 6-A501 ¬ (FIELD BEND AS NECESSARY) A = 2-A522 ¬ (N.F.), 4-A501 ¬ (TOP & F.F.) 5. 4. 3. 2. 1.SEE NOTE 5MATCHES THE BRIDGE FACE OF RAILING. OFFSETS AS NECESSARY BASED ON ACUTAL FIT-UP SO THAT FACE OF RAILING RIGHT RAILING OFFSETS SHOWN ARE BASED ON 0" FIT-UP. ADJUST #6 BAR = 4'-0" #5 BAR = 2'-5" MIN. LAP LENGTHS SHALL BE: FOR OUTLETS. SET PIPE OUTLETS 6" ABOVE GROUNDLINE. SLOPE PIPE „" PER FOOT TOWARDS OUTLET. USE NON-PERFORATED PIPES SEE SHEET FOR WINGWALL ELEVATIONS. SEE SHEET FOR SECTION A-A. 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SF001.dgn Sheet 5/6/2022 4:53:24 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220N BDEBDEJMK-36 11FORWARD ABUTMENT PLAN AND ELEVATIONEL. 842.00 1'-6†"12'-6"21'-11•"PHASE 2 34'-0†" PHASE 1 30'-0" 33°30'00" 56°30'00" SHAWAN FALLS DR. \ CONSTRUCTION PHASE 2 CONSTRUCTIONCONSTRUCTION PHASE 1 1'-0" 2'-2„"33°30'00"T Y P. 13'-5ƒ" 1'-6" EL. 843.306 '-6•"1'-0"(SKEW A518 BARS AS NECESSARY AT WINGWALL AND PHASED C.J.) 30 SETS OF 1-A517 (E.F.), 1-A506 (E.F.) AND 1-A518 @ 1'-0" MAX (SKEW A518 BARS AS NECESSARY AT WINGWALL AND PHASED C.J.) 33 SETS OF 1-A517 (E.F.), 1-A506 (E.F.) AND 1-A518 @ 1'-0" MAX A A EL. 853.12 LEVEL SEAT (LAP W/ A501)6-A520 (N.F.)6-A521 (N.F.)(LAP W/ A501)6-A519 (E.F.)(LAP W/ A519)ABC13'-10‡"2•" THICK POLYSTYRENE FORWARD ABUTMENT PLAN FORWARD ABUTMENT ELEVATION LEVEL C.J.LEVEL C.J. C.J. SHAWAN FALLS DR. \ CONSTRUCTION COPING1'-0"EL. 843.60 APPROX. T.O.R. 2-D602 (E.F.) 2-D504 NECESSARY) BEND AS 2-D601 (FIELD NECESSARY) (FIELD BEND AS (E.F.)D503 2-D601 (E.F.) D503 FABRIC AND 6" DIA. PCPP (SEE NOTE 3) 2'-0" POROUS BACKFILL W/ GEOTECH 17-D801 @ 1'-6" MAX (MEASURED PERPENDICULAR TO \) 30 SETS OF 1-D501 & 1-D502 @ 1'-0" MAX 18-D801 @ 1'-6" MAX (MEASURED PERPENDICULAR TO \) 33 SETS OF 1-D501 & 1-D502 @ 1'-0" MAX6"1'-9„" PHASED C.J. M.C. (TYP.) TYPE 2 WATERPROOFING PHASED C.J. W/ (TYP.) 2" PEJF 3LWP 4LWP 5LWP 9RWP 1'-6" STA. 102+16.24 | BRGS. F.A. EL. 855.15* EL. 856.21** EL. 855.21** EL. 854.82* EL. 855.15** EL. 852.51** EL. 855.29* 8RWP 7RWP 6RWP 5RWP (MIN.) 3" CHAMFER ON BOX BEAM (TYP. EACH SIDE) CONCRETE AND ADJACENT RAIL ANCHORAGE PROVIDE A 2" MIN. GAP BETWEEN FACE OF AGAINST 2" PEJF ON FASCIA SIDE OF BEAM. AS NECESSARY TO CAST CONCRETE DIRECTLY AT BOX BEAMS, INCREASE WINGWALL THICKNESS LEVEL SEAT 4'-9•"(E.F.)6-A501 @ 1'-0"(E.F.)6-A501 @ 1'-0"WINGWALLS NOT SHOWN FOR CLARITY EL. 852.62** 324SHEET FOR ADDITIONAL INFORMATION. REMAIN, SEE PROTECTION OF UTILITIES NOTE ON APPROXIMATE LOCATION OF AT&T UTILITY LINES TO FOOTING STEP, CUTOFF WALL, AND SUPERSTRUCTURE NOT SHOWN FOR CLARITY ALL DIMENSIONS ARE GIVEN TO THE FACE OF WALL AS SHOWN IN THE SECTIONS1'-1"2'-0"END CAP END CAP END CAP 1'-0" FILLET 13 24 NOTES: 13 24 12 24 LEGEND: OVERLAY TOP OF ASPHALT 5. 4. 3. 2. 1. 7R 6R 5R 5L 4L 3L STA. 102+38.30, 16.60' RT. STA. 102+33.88, 16.60' RT. STA. 102+29.47, 16.60' RT. STA. 102+02.63, 36.27' LT. STA. 101+98.47, 36.27' LT. STA. 101+94.30, 36.27' LT. ** = ELEVATION AT CORNER OF WALL * = ELEVATION AT | BEARINGS AT TOP OF CONCRETE FOR BAR PLACEMENT. ¬ = BARS ARE IN COPING. SEE SECTION A-A ON SHEET C = 6-A519 ¬ (LAP W/ A501) B = 6-A501 ¬ (FIELD BEND AS NECESSARY) A = 2-A522 ¬ (N.F.), 4-A501 ¬ (TOP & F.F.) 9R STA. 102+47.13, 16.60' RT. 8R STA. 102+42.72, 16.60' RT.SEE NOTE 5SEE NOTE 5MATCHES THE BRIDGE FACE OF RAILING. OFFSETS AS NECESSARY BASED ON ACUTAL FIT-UP SO THAT FACE OF RAILING RIGHT RAILING OFFSETS SHOWN ARE BASED ON 0" FIT-UP. ADJUST #6 BAR = 4'-0" #5 BAR = 2'-5" MIN. LAP LENGTHS SHALL BE: USE NON-PERFORATED PIPES FOR OUTLETS. SLOPE PIPE „" PER FOOT TOWARDS OUTLET. OUTLETS SHALL BE AT EL. 848.0`. SEE SHEET FOR WINGWALL ELEVATIONS. SEE SHEET FOR SECTION A-A. 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SF002.dgn Sheet 5/6/2022 4:53:25 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220BDEBDEJMK-37 12WINGWALL ELEVATIONSRIGHT FORWARD WINGWALL ELEVATION EL. 855.20 EL. 852.51 1'-0"4'-0"@ 1'-0" MAX 15 SETS OF 1-A517 (N.F.) & 1-A601 (F.F.)COPING1'-0"A539 (E.F.) (SPACE & LAP W/ A521) 5-A540 (E.F.) (LAP BOTTOM BAR W/ A521) 4-A541 (N.F.) & 4-A542 (F.F) @ 1'-0" MAX A544 (F.F.) A543 (N.F.) SEE NOTE 1 23-A530 (LAP W/ A537, A538, & A539) B C C B D TYPE 2 WATERPROOFING LEVEL C.J. * W/ EL. 854.67 15-A537 (LAP W/ A517 & A601) RIGHT REAR WINGWALL ELEVATION EL. 853.17 2'-0"3'-3"EL. 856.00 & 1-A601 (F.F.) @ 1'-0" MAX 11 SETS OF 1-A517 (N.F.) (SPACE & LAP W/ A520) 4-A547 (E.F.) LAP AND SPACE BARS W/ A520A548 (E.F.) A549 (E.F.) A551 (F.F.) A550 (N.F.) A555 (F.F.) A554 (N.F.)COPING1'-0"SEE NOTE 1 18-A530 (LAP W/ A545 & A546) 3-A553 (F.F.) @ 1'-0" MAX 3-A552 (N.F.) & B B C C E A515 (E.F.) TYPE 2 WATERPROOFING LEVEL C.J. * W/ A552 (N.F.), A553 (F.F.) EL. 856.11 11-A545 (LAP W/ A517 & A601) (LAP W/ EACH F.F. BAR) 7-A557 IN FILLET EL. 853.30 EL. 856.69 EL. 855.69 2'-6"3'-0"@ 1'-0" MAX 3-A517 (N.F.) B C (E.F.) A533 (SPACE & LAP W/ A521) 3-A534 (N.F.) (SPACE & LAP W/ A521) 1 S.O. 3-A535 (E.F.) A536 (E.F.) (LAP W/ A521) SEE NOTE 1 LEFT REAR WINGWALL ELEVATION @ 1'-0" MAX 8-A529 ® & A530 @ 1'-0" MAX 3-A536 (N.F.) & 3-A509 (F.F.) A556 (F.F.) A506 (N.F.) D D E E3 CONSTRUCTIONCOPING - PHASETYPE 2 WATERPROOFING LEVEL C.J. * W/ C.J.EL. 856.75 EL. 855.75 1'-0" EL. 852.62 LEFT FORWARD WINGWALL ELEVATION EL. 856.21 EL. 855.21 2'-6"2'-6"1-A601 (F.F.) 1-A517 (N.F) & 7 SETS OF @ 1'-0" MAX (SPACE & LAP W/ A520) 3-A502 (E.F.) (E.F.) A528 @ 1'-0" MAX (E.F.) 1 S.O. 6-A524 1'-0"A526 (E.F.) C.J. A (SPACE & LAP W/ A520) 1 S.O. 3-A525 (E.F.) @ 1'-0" MAX 3-A526 (E.F.) SEE NOTE 1 14-A529 ® AND A530 @ 1'-0" MAX D D E E (E.F.) A527 3 CONSTRUCTIONCOPING - PHASETYPE 2 WATERPROOFING LEVEL C.J. * W/ EL. 856.02 EL. 855.02 1'-0" (LAP W/ EACH F.F. BAR) 7-A557 IN FILLET NOTES: 2. 1. LEGEND: #5 BAR = 2'-5" MIN. LAP LENGTHS SHALL BE: COPING TO AVOID THE RAILING ANCHORAGE. ADJUST THE LOCATION OF THE REINFORCING STEEL IN THE E = 1 SET OF 1 S.O. 7-A546 & 7-A529 @ 1'-0" MAX D = 1 SET OF 1 S.O. 7-A538 & 7-A529 @ 1'-0" MAX C = 1 S.O. 4-A532 @ 1'-0" MAX (E.F.) B = 3-A531 (E.F.) (LAP & SPACE W/ A517) A = 7-A523 (E.F.) (LAP W/ A517 & A601) UNTIL THE BOX BEAMS AND DIAPHRAGM HAVE BEEN CONSTRUCTED. * = DO NOT PLACE THE WINGWALL CONCRETE ABOVE THE CONSTRUCTION JOINT ® = A529 BARS TO BE DOWELED INTO WINGWALL DURING PHASE 3 CONSTRUCTION 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SR002.dgn Sheet 5/6/2022 4:53:26 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220BDEBDEJMK-13ABUTMENT SECTIONS AND DETAILS38 C.J. 6" DIA. PCPP BOX BEAM 2•" THICK POLYSTYRENE SECTION A-A SECTION B-B 6" DIA. PCPP APPROACH SLAB A506 A506 A401 A517 A601 A518 D501 D801 A517 A601 A530 OPTIONAL CJ 7'-0"2'-6"2'-0" W/ GEOTEXTILE FABRIC 2'-0" POROUS BACKFILL A506 1'-0"1'-0"1'-0"1'-0"1'-0" 1'-9"2'-9"1" EL. 842.00 EL. 843.50 (R.A.) EL. 843.30 (F.A.) CUTOFF WALL 1'-0" W/ GEOTEXTILE FABRIC 2'-0" POROUS BACKFILL C.J.1'-9" 1" PEJF 2" C.J. 1'-6"1'-0" SECTION C-C GROUND LINE PROPOSED APPROACH SLABA530 1'-6" 1"PEJF 2" C.J. A529 A546 A538 OR SECTION D-D 6" DIA. PCPP GROUND LINE PROPOSED A517 A601 A530 W/ GEOTEXTILE FABRIC 2'-0" POROUS BACKFILL C.J.1'-9" 1" C.J. 1'-6"1'-0" A531 A523 OR APPROACH SLAB SIDEWALK PEJF 2" A530 1'-6" 1" C.J. APPROACH SLAB SIDEWALK PEJF 2" A532 A524 OR GROUND LINE PROPOSED SECTION E-E GROUND LINE PROPOSED 6" AS-1-15 FOR ADDITIONAL DETAILS SEE STANDARD DRAWING APPROACH SLAB DECK SLAB DECK REINFORCING BEAM REINFORCING D503 OR D504 (TYP. OF 4) COPING COPING COPING COPING COPING A529 ® A529 ® EL. 842.00 CUTOFF WALL 1'-0" EL. 842.00 CUTOFF WALL 1'-0" EL. 843.50 (R.A.) EL. 843.30 (F.A.) EL. 843.50 (R.A.) EL. 843.30 (F.A.) 9 24 9 24 (SEE NOTE 2) TYPE 2 WATERPROOFING (SEE NOTE 4) EXPANSION JOINT SEAL SEMI-INTEGRAL ABUTMENT (SEE NOTE 2) TYPE 2 WATERPROOFING (SEE NOTE 2) TYPE 2 WATERPROOFING (SEE NOTE 2) TYPE 2 WATERPROOFING (SEE NOTE 2) TYPE 2 WATERPROOFING A545 A537 OR SEE SHEET FOR FOOTING REINFORCING STEELSEE SHEET FOR FOOTING REINFORCING STEEL 3" ASPHALT OVERLAY (SEE NOTE 5) PROPOSED GROUND LINE 1'-0" NPCPP 6" DIA.¬1'-0"1'-0" ¬¬ ¬¬ 1'-0"1'-0" 3'-1" ¬ WALL FACE OF WALL FACE OF WALL FACE OF WALL FACE OF WALL FACE OF 1'-7"1'-7" 1'-7"1'-7" | ABUTMENT BEARINGS BRIDGE LIMITS 1'-1" D601 OR D602 D502 (SEE NOTE 3) OPTIONAL C.J. VARIES LEGEND: NOTES: ¬ = LIMITS OF SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) DOWEL BARS 10" INTO CONCRETE AND FILL WITH CEMENT GROUT PER 510. ® = A529 BARS TO BE DOWELED INTO WINGWALL DURING PHASE 3 CONSTRUCTION. DRILLING OF ANCHOR BAR HOLES. STEEL IN THE VICINITY OF THE BRIDGE SEAT TO AVOID INTERFERENCE WITH THE BRIDGE SEAT REINFORCING, SETTING ANCHORS: ACCURATELY PLACE REINFORCING FROM THE FACE OF THE ABUTMENT. PROPOSED FOOTING. SLOPE ANY EXPOSED TOP SURFACES OF THE MORTAR AWAY PROPOSED FOOTING AND ANY GAPS BETWEEN EXISTING FOOTING LEFT IN PLACE AND USE TYPE 2 LOW STRENGTH MORTAR BACKFILL TO FILL ANY GAPS BETWEEN ROCK AND FROM THE BEARING SEAT TO THE BOTTOM OF THE APPROACH SLAB. FOR VERTICAL JOINTS, PLACE JOINT SEAL CENTERED ON 2" PEJF AND EXTENDING PLACE JOINT SEAL, 2'-0" WIDE, CENTERED ON HORIZONTAL AND VERTICAL JOINTS. PLACED SEPARATELY, LOCATE A HORIZONTAL CONSTRUCTION JOINT AS SHOWN. CONCRETE OR AT LEAST 48 HOURS BEFORE PLACEMENT OF THE DECK CONCRETE. IF PLACE THE DIAPHRAGM CONCRETE AT THE ENDS OF THE BOX BEAMS WITH THE DECK FROM THE BACK OF THE DIAPHRAGM TO THE END OF WALL. APPROACH SLAB. PLACE WATERPROOFING HORIZONTALLY, CENTERED ON THE C.J., FOOTING TO TOP OF BREASTWALL AND FROM BOTTOM OF DIAPHRAGM TO BOTTOM OF PLACE WATERPROOFING VERTICALLY, CENTERED ON THE PHASED C.J., FROM TOP OF BARS NOT CALLED OUT ARE A5 BARS. 6. 5. 4. 3. 2. 1. 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SS001.dgn Sheet 5/6/2022 4:53:27 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220BDEBDEJMK-BEAM LAYOUT PLAN39 14 BEAM LAYOUT PLAN (TYP.) 1'-0" LEGEND: B13 * B1 * B2 * B3 * B4 * B5 * B6 * B7 * B8 * B9 * B10 * B11 * | DIAPHRAGM 44'-0" BEAM LENGTH (MEASURED ALONG | BEAM) 33 °30'0 "(TYP .)BEAM END DETAILS (TYP.) SEE SHEET FOR TIE RODS (TYP.) HOLES FOR 1" DIA. SHAWAN FALLS DR. \ CONSTRUCTIONNNOTES: 2. 1. (TYP.) 2'-7ƒ" (TYP.) 9" 15 24 102 SUPERSTRUCTURE PHASE C.J. IN OUTWARDS IN ORDER TO MINIMIZE DECK OVERHANGS. STARTING WITH BEAMS ADJACENT TO BEAM 6 AND WORKING ACCURATELY PLACE BEAM 6 FIRST. SET OTHER BEAMS SEE ODOT STD. DWG PSBD-2-07 FOR ADDITIONAL DETAILS.PHASE 1 CONSTRUCTION PHASE 2 CONSTRUCTION (TYP. U.N.O.) 2'-0" (TYP.) 22'-0" (TYP.) 22'-0" 42'-6" (c/c BEARINGS) STA. 101+73.74 | REAR ABUTMENT BEARINGS STA. 102+16.24 ABUTMENT BEARINGS | FORWARD 2'-7•" (TYP.) 2'-7ƒ" (TYP.) 2'-7ƒ" ¬ = B17-36 BOX BEAM * = B17-48 BOX BEAM B = BEAM DESIGNATION 2'-0ƒ"6 SPA. @ 6'-3" = 37'-6"4'-3•" RAIL POST SPACING RAIL POST SPACING (TYP.) | RAIL POST 3'-8"6 SPA. @ 6'-3" = 37'-6"2'-8‚"12-B17-48 & 1-B17-36 BOX BEAMS51'-0" (PLUS FIT-UP)B12 ¬ (TYP.) 6" 3'-1" BEAM SEAT 2'-0" 3'-1" BEAM SEAT 2'-0" 1'-1" 16 24 BEARING ORIENTATION SEE SHEET FOR (WEB THICKENING AT RAIL POSTS NOT SHOWN, SEE PSBD-2-07 FOR DETAILS) 1'-1" 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SS002.dgn Sheet 5/6/2022 4:53:28 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220BDEBDEJMK-40 15BEAM DETAILSNOTES: 3'-0" XX BARS C BARS D BARS 4" (TYP.) •" DIA. STRAND 10 STRANDS 10 STRANDS 4'-0" 4" 16 STRANDS (TYP.) •" DIA. STRAND V BARS X BARS 1'-5" 1'-5"N BARS 4" 4" 6 STRANDS VIEW B-B CB17-36 (SEE NOTE 1) BEAM 12 SECTION @ MIDSPAN A 1" 2. 1. 4" 7„" 5" 9-"N" BARS @ 6" (BOT.) @ 12" (BOT.) 33-"N" BARS 26-"X" BARS (TOP) ¬ 25-"V" BARS (TOP) ¬ B 5" 5" 11†" @ 12" (BOT.) 26-"XX" BARS (TOP) ¬ 25-"C" BARS (TOP) ¬ 33-"D" BARS A A (PRESTRESSING STEEL AND STIRRUPS NOT SHOW FOR CLARITY) VIEW A-A (PRESTRESSING STEEL AND STIRRUPS NOT SHOW FOR CLARITY) 8•" 3" 5•"FASCIA BEAM FACE OF EXTERIOR OMIT KEY ON @ 2" = 10" 5 SPA. @ 2" = 10" 5 SPA. 4" 4"2"2"4"4" (ALTERNATE TOP U-BARS SHALL PROJECT 2" ABOVE TOP OF BEAM) A = 1 S.O. 6 - NO. 4 U-BARS @ 4" (TOP & BOT.) (ALTERNATE TOP U-BARS SHALL PROJECT 2" ABOVE TOP OF BEAM) B = 1 S.O. 4 - NO. 4 U-BARS @ 4" (TOP & BOT.) 9-"D" BARS (BOT.) 7 SPA. @ 6"5" B B (TYP.)6"(TYP.) 4"1"1'-6" (TYP. OF 2) NO. 5 WEB BAR ADDITIONAL (TYP. OF 6) NO. 5 FULL LENGTH BAR (SEE NOTE 2) 4-NO. 5 BARS, FULL LENGTH (SEE NOTE 2) 4-NO. 5 BARS, FULL LENGTH LONGITUDINAL BARS AS SHOWN IN VIEWS A-A AND B-B. PROVIDE ADDITIONAL LENGTH AND STANDARD HOOK TO ENDS OF SEE ODOT STD. DWG PSBD-2-07 FOR ADDITIONAL DETAILS. STANDARD HOOK 4 NO. 5 BARS WITH STANDARD HOOK 2 NO. 5 BARS WITH5"2 NO. 5 WEB BARS A A 3"30°0'0"3"30°0'0" 2" BEARING ANCHOR ROD HOLE 2" BEARING ANCHOR ROD HOLE ROD HOLE 2" BEARING ANCHOR ROD HOLE 2" BEARING ANCHOR 2" ANCHOR DOWEL HOLE 2" ANCHOR DOWEL HOLE 36" BEAM END DETAILS (SEE SHEET FOR LOCATION OF BEARING ANCHOR HOLES)16 24 (SEE SHEET FOR LOCATION OF BEARING ANCHOR HOLES)16 24 (LOOKING UPSTATION) (LOOKING UPSTATION) CB17-48 (SEE NOTE 1) (TYP. OF 2, SEE NOTE 2) NO. 5 BAR, FULL LENGTH (TYP. OF 2, SEE NOTE 2) NO. 5 BAR, FULL LENGTH 9" 10"2"2 STRANDS@ 2" = 4"2 SPA. 4" 4" 2 SPA. @ 2" = 4"2 SPA. @ 2" = 4" 2 SPA. @ 2" = 4"2 SPA. @ 2" = 4" BEAM 1-11 AND BEAM 13 SECTION @ MIDSPAN 48" BEAM END DETAILS 2'-2" (36" BEAM) 3'-2" (48" BEAMS) FASCIA BEAM FACE OF EXTERIOR OMIT KEY ON 7ƒ" (B12) 8ƒ" (B1-B11, B13) ALTERNATE "XX" AND "C" BARS ¬ = ALTERNATE "X" AND "V" BARS LEGEND: 2 SPA. @ 2" = 4"2 SPA. @ 2" = 4" 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SB001.dgn Sheet 5/6/2022 4:53:29 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220BDEJMK-41 16BEARING DETAILSKKNNOTES: 4. 3. 2. 1. LEGEND: | BEAM ELASTOMERIC BEARING BEARING ELASTOMERIC ABUTMENT SEAT BEARING ELASTOMERIC 5• " 5• " 6" 6" • " • " 4" 4"4•" 4•" •" •" 9‚ " ¬ 1'- 4„ " * PLAN VIEWAA SECTION A-A 6"x6" PEJF (6" x 6" PEJF NOT SHOW FOR CLARITY) 11" 5•" 5•" •" •" 1'-0"9‚" ¬ 1'-4„" * LOAD PLATE 9" x 12" BEVELED - -- --- B B 6" SECTION B-B 4" 4" 8" 9" •" •" 1•"1•" F.A.1†" R.A.MIDSPAN 30°0'0" 2" ANCHOR DOWEL HOLE | ANCHOR RODS | ABUTMENT BEARINGS LOAD PLATE 9" X 12" BEVELED NR.A.F.A. | ƒ" DIA. BEARING ANCHOR ROD DOWEL HOLE | 2" DIA. ANCHOR | ANCHOR RODS ANCHOR ROD ƒ" DIA. BEARING LOAD PLATE 9" X 12" BEVELED BEARING DESIGN SERVICE LOADS (KIPS) DEAD LOAD 31 LIVE LOAD W/0 IMPACT 13 TOTAL DESIGN LOAD 44 ANCHOR ROD HOLE 2" DIA. BEARING ANCHOR ROD HOLE 2" DIA. BEARING ANCHOR ROD HOLE 2" DIA. BEARING DETAILS. SEE ODOT STANDARD DRAWING PSBD-2-07 FOR ADDITIONAL ANCHOR DOWEL FOR ADDITIONAL BEVELED LOAD PLATE AND BEARING ANCHOR ROD DETAILS. REFER TO ODOT STANDARD DRAWING BD-1-11 FOR MEASUREMENT, PAYMENT, AND THE BEARING. VULCANIZE ALL STEEL PLATES IN CONTACT WITH AN ELASTOMERIC BEARING TO HIGHWAY BRIDGES, DIVISION II, SECTION 18.7.2.6) IS NOT REQUIRED. COMPRESSION PROOF LOAD TEST (AASHTO STANDARD SPECIFICATIONS FOR THE AASHTO LRFD BRIDGE DESIGN SPECIFICATIONS. THE LONG-TERM BEARINGS WERE DESIGNED IN ACCORDANCE WITH SECTION 14.7.6 (METHOD A) OF ELASTOMERIC BEARING PADS SHALL HAVE A HARDNESS OF 50 DUROMETER. THE 2ˆ" ---= 1 EXTERNAL ELASTOMER LAYER THICKNESS = 0.350" --= 1 STEEL LAMINATE LAYER THICKNESS = 0.0747" -= 1 INTERNAL ELASTOMER LAYER THICKNESS = 0.500" ¬ = B17-36 BOX BEAM (BEAM 12) * = B17-48 BOX BEAM (BEAMS 1-11 & 13) 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\ST001.dgn Sheet 5/6/2022 4:53:30 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220JMKBDE-42 17KKTRANSVERSE SECTION AND DECK PLANNTRANSVERSE SECTION (MINUS FIT-UP) 3•" B1 B2 B3 B4 B5 B6 B7 B8 B9B9 B10 B11 B12 B13 CROWN AND PROFILE GRADE \ CONSTR. SHAWAN FALLS DRIVE LEVEL C.J. 1.6%1.6% 1.6%6"2•"CLR.S603 SEE NOTE 3 SEE NOTE 3 LEGEND: NOTES: PHASE C.J. 6" 6" ** ** M.C. 16'-0" 11'-3•" 1'-6" 1'-6" SHAWAN FALLS DR. \ CONSTRUCTION PHASE C.J. BRIDGE LIMITS 46'-1„"7'-3•"SIDEWALK 7'-3•" PLUS FIT-UP SHOULDER 4'-0" LANE 12'-0" LANE 12'-0" LANE 12'-0" SHOULDER 4'-0" 51'-3•" PLUS FIT-UP OUT/OUT DECK 51'-3•" PLUS FIT-UP49-S602 @ 9" = 36'-0"(2 LENGTHS)16-S603 @ 1'-6" = 22'-6"(2 LENGTHS)18-S603 @ 1'-6" = 25'-6"3"3"49-S601 ¬ @ 9" = 36'-0" S601 S602 ON SHEET SLAB THICKNESS DIAGRAM SEE REINFORCED CONCRETE REINFORCED CONCRETE SLAB, 6" MIN. CAST-IN-PLACE 18 24 SEE CURB DETAIL RAILING, SEE SHEET MODIFIED TST-1-99 20 24 RAILING TST-1-99 STRIP STEEL DRIP @ EQ. SPA8-S404(2 LENGTHS)S403 S404 S402* S401* MIN. LAP (TYP.) 2'-8" #6 BAR MIN. LAP (TYP.) 1'-10" #4 BAR (TYP.)33°30'00" (2 LENGTHS) S603 39 SETS OF 1-S401*, 1-S402*, & 1-S403 ¬ @ 1'-0" = 38'-0" CURB DETAIL9"1•" 3" RAD. TOP OF DECK TOP OF OVERLAY11ƒ"PHASE 2 CONSTRUCTION 27'-3•" PHASE 1 CONSTRUCTION 24'-0" PLUS FIT-UP STA. 101+73.74 BEARINGS | REAR ABUTMENT STA. 102+16.24 BEARINGS | FORWARD ABUTMENT 10 24 11 24 102+00 PHASE 1 CONSTRUCTION24'-0" PLUS FIT-UPPHASE 2 CONSTRUCTION27'-3•"16'-0"35'-3•" PLUS FIT-UP SIDEWALKFIT-UPPLUSDECK PLAN AND RAILING LAYOUT 4'-2" 6 SPA. @ 6'-3" = 37'-6" 6 SPA. @ 6'-3" = 37'-6" = 17'-8" 4 SPA. @ 4'-5" RAIL POST SPACING SEE NOTE 4 RAIL POST SPACING SEE NOTE 4 10 24 11 24 14 24 , AND . 4. LOCATE POSTS AS SHOWN ON SHEETS , (SPREAD FORMS AT TOP TO PROVIDE TIGHT FIT). 3. SLOPE SIDES OF BEAM LOCATED AT CROWN POINT END OF DECK REINFORCING DETAILS. 2. SEE SHEETS AND FOR RAIL ANCHOR PLATES AS NECESSARY. 1. ADJUST DECK AND SIDEWALK REINFORCING AROUND 21 24 2 SPA. = 8'-4" @ 4'-2" 4'-2" 4'-2" 4'-5" 4'-5" 2 SPA. = 8'-10" @ 4'-5" (TYP.) | RAIL POST 3"3"BOX BEAM 1 - B17-48 BOX BEAM 1 - B17-36 11 - B17-48 BOX BEAMS  = SEE BENDING PLAN ON SHEET  = DIMENSION VARIES WITH TEMPERATURE, SHOWN AT (EPOXY-URETHANE) ** = LIMITS OF SEALING OF CONCRETE SURFACES AND SIDEWALK LIMITS AND TOUCH-UP PER 509.09 TO FIT BARS WITHIN DECK ¬ = FIELD CUT S601 AND S403 BARS AS NECESSARY CEMENT GROUT PER 510. PHASE 3 CONSTRUCTION. GROUT HOLES WITH * = DOWEL S401 & S402 BARS 6" INTO DECK DURING 3" ASPHALT OVERLAY TACK COAT AND ASPHALT ITEMS SEE ROADWAY PLANS FOR 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SS003.dgn Sheet 5/6/2022 4:53:31 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220JMKJMKBDE-43 18SCREED ELEVATIONS, TOPPING THICKNESS AND CAMBER 24'-0" PLUS FIT-UP 11'-3•" 3" ASPHALT OVERLAY BEARINGS | R.A. | SPAN TOP OF BEAM CAMBERTHICKNESSTOPPINGREINFORCED CONCRETE SLAB THICKNESS AND CAMBER DIAGRAM NOTES: 30 0 30 ABUTMENT | REAR • SPAN ABUTMENT | FORWARD 30 0 30 THE BEAM SEAT ELEVATIONS ASSUME ESTIMATED CAMBER D . CONCRETE DECK, SIDEWALK, RAILINGS, OVERLAY) IS 0.77 INCHES. AVERAGE DEFLECTION DUE TO REMAINING DEAD LOAD (E.G. ESTIMATED CAMBER AT DAY 30 (D ) IS 1.62 INCHES. ESTIMATED CAMBER AT DAY 0 (D ) IS 0.93 INCHES. 48" BEAM CAMBER: THE BEAM SEAT ELEVATIONS ASSUME ESTIMATED CAMBER D . SIDEWALK, RAILINGS, OVERLAY) IS 0.86 INCHES. DEFLECTION DUE TO REMAINING DEAD LOAD (E.G. CONCRETE DECK, ESTIMATED CAMBER AT DAY 30 (D ) IS 1.98 INCHES. ESTIMATED CAMBER AT DAY 0 (D ) IS 1.14 INCHES. 36" BEAM CAMBER: TOPPING THICKNESS* (IN) TOP OF CONCRETE DECK CONSTRUCTION * = MEASURED TO TOP OF CONCRETE DECK, PRIOR TO OVERLAY BEARINGS | F.A. ABUTMENT BEARING |'s BASELINE BETWEEN 51'-3•" PLUS FIT UP OUT/OUT OF DECK LEFT EDGE OF DECK RIGHT EDGE OF DECK PHASE C.J. \ CONSTR. SHAWAN FALLS DRIVE | B1 | B2 | B3 | B4 | B5 | B6 | B7 | B8 | B9 | B10 | B11 | B12 | B13 SCREED LOCATION DIAGRAM 8 6„ 6‡ 9„ SCREED ELEVATIONS | REAR ABUTMENT | FORWARD ABUTMENT STATION ELEVATION STATION ELEVATION STATION ELEVATION STATION ELEVATION STATION ELEVATION 101+50.24 855.63 101+60.87 855.59 101+71.49 855.50 101+82.12 855.34 101+92.74 855.15 101+66.28 855.87 101+76.90 855.79 101+87.53 855.66 101+98.15 855.48 102+08.78 855.25 101+73.74 855.96 101+84.37 855.86 101+94.99 855.72 102+05.62 855.53 102+16.24 855.29 101+84.33 855.57 101+94.96 855.46 102+05.58 855.31 102+16.21 855.09 102+26.83 854.82 PHASE C.J. PROFILE GRADE AND CROWN RIGHT EDGE OF DECK ‚ SPAN • SPAN ƒ SPAN 16'-0" 35'-3•" PLUS FIT-UP RIGHT EDGE OF DECK PROFILE GRADE AND CROWN PHASE C.J. LEFT EDGE OF DECK LEFT EDGE OF DECK ¬ PROFILE GRADE AND CROWN ELEVATION: +0.01', -0.00' STATION: +0.14', -0.00' THE ACTUAL FIT-UP AS FOLLOWS: ALLOWANCE OF 2•". ACTUAL VALUES MAY VARY BASED ON CALCULATED ASSUMING THE MAXIMUM ALLOWABLE FIT-UP ¬ = LEFT EDGE OF DECK STATIONS AND ELEVATIONS SHOWN ARE LEGEND: 19 24 8‡ 6• 7 8… 7ƒ 6• 7† 10• (ASHPALT OVERLAY NOT SHOWN) LOADS. CAUSED BY DECK PLACEMENT AND OTHER ANTICIPATED DEAD CONCRETE DECK SURFACE LOCATION PRIOR TO DEFLECTIONS 3. SCREED ELEVATIONS SHOWN REPRESENT THE THEORETICAL GRADE ADJUSTMENT AND BEAM CAMBER. THICKNESS THAT PROVIDES AN ALLOWANCE FOR: VERTICAL THICKNESS, THE QUANTITY INCLUDES A VARIABLE HAUNCH ACCORDING TO CMS 511. IN ADDITION TO THE DESIGN SLAB ESTIMATED QUANTITY OF DECK CONCRETE IS MEASURED 2. DECK SLAB THICKNESS FOR CONCRETE QUANTITY: THE DIAGRAM. 1. SEE SHEET FOR CRITICAL BRIDGE POINTS 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SM001.dgn Sheet 5/6/2022 4:53:31 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220BDEBDEJMK-44 19FINAL DECK SURFACE ELEVATIONSNLEFT EDGE OF DECK RIGHT EDGE OF DECK TOE OF CURB (TYP .)33 °30 '0 " ‚ S P A N ƒ S P A N • S P A N | R. A. CRITICAL POINTS DIAGRAM SPAN 42'-6" B E A RI N G S B E A RI N G S | F. A. PHASE C.J. 102+00 NOTES: B11 B10 B1 B2 B3 B4 B5 B6 B7 B8 B9 28'-0"16'-0"11'-3•"| REAR ABUTMENT | FORWARD ABUTMENT STATION ELEVATION STATION ELEVATION STATION ELEVATION STATION ELEVATION STATION ELEVATION 101+50.24 101+60.87 101+71.49 101+82.12 101+92.74 101+51.57 101+62.19 101+72.82 101+83.44 101+94.07 101+54.24 101+64.87 101+75.49 101+86.12 101+96.74 LEFT TOE OF CURB 101+55.21 855.96 101+65.83 855.86 101+76.46 855.74 101+87.08 855.60 101+97.71 855.43 | BEAM 3 101+56.92 855.99 101+67.54 855.88 101+78.17 855.76 101+88.79 855.61 101+99.42 855.45 | BEAM 4 101+59.59 856.03 101+70.22 855.92 101+80.84 855.79 101+91.47 855.64 102+02.09 855.46 | BEAM 5 101+62.27 856.06 101+72.89 855.95 101+83.52 855.81 101+94.14 855.66 102+04.77 855.48 | BEAM 6 101+64.94 856.10 101+75.57 855.98 101+86.19 855.84 101+96.82 855.68 102+07.44 855.50 PHASE C.J.101+66.27 856.12 101+76.89 856.00 101+87.52 855.85 101+98.14 855.69 102+08.77 855.50 | BEAM 7 101+67.62 856.13 101+78.24 856.01 101+88.87 855.86 101+99.49 855.70 102+10.12 855.51 | BEAM 8 101+70.29 856.17 101+80.92 856.04 101+91.54 855.89 102+02.17 855.72 102+12.79 855.52 | BEAM 9 101+72.97 856.20 101+83.59 856.07 101+94.22 855.91 102+04.84 855.73 102+15.47 855.53 PROFILE GRADE & CROWN 101+73.74 856.21 101+84.37 856.07 101+94.99 855.92 102+05.62 855.74 102+16.24 855.54 | BEAM 10 101+75.64 856.14 101+86.27 856.00 101+96.89 855.84 102+07.52 855.66 102+18.14 855.45 | BEAM 11 101+78.32 856.05 101+88.94 855.90 101+99.57 855.73 102+10.19 855.55 102+20.82 855.34 | BEAM 12 | BEAM 13 101+84.33 101+94.96 102+05.58 102+16.21 102+26.83 35'-3•" PLUS FIT-UPPROFILE GRADE & CROWN \ CONSTR. SHAWAN FALLS DRIVE ‚ SPAN • SPAN ƒ SPAN ¬ ¬ ¬ ¬ ¬ ¬ ¬ ¬ ¬ ¬ ¬ ¬ ¬ ¬ LEGEND: LEFT EDGE OF DECK* | BEAM 1* | BEAM 2* RIGHT EDGE OF DECK* * = ¬ = EXCEPT WHERE LOCATIONS ARE MARKED WITH AN '*'. ELEVATIONS ARE GIVEN AT THE TOP OF THE APSHALT SURFACE, DEFLECTIONS HAVE OCCURRED. SURFACE LOCATION AFTER ALL ANTICIPATED DEAD LOAD FINAL DECK SURFACE ELEVATIONS SHOWN REPRESENT THE DECK 2. 1. 855.63 855.66 855.70 855.54 855.56 855.60 855.43 855.45 855.48 855.30 855.31 855.34 855.15 855.16 855.18 855.57 855.42 855.24 855.04 854.82 CONCRETE DECK ELEVATIONS AT THIS LOCATION ARE GIVEN AT THE TOP OF ELEVATION: +0.01', -0.00 STATION: +0.14', -0.00' MAY VARY BASED ON THE ACTUAL FIT-UP AS FOLLOWS: BETWEEN BEAMS. AT THE LEFT EDGE OF DECK, ACTUAL VALUES THE MAXIMUM ALLOWABLE FIT-UP ALLOWANCE OF •" PER JOINT STATIONS AND ELEVATIONS SHOWN ARE CALCULATED ASSUMING B12 B13 101+80.66 101+83.01 855.96 855.87 101+91.29 101+93.63 855.81 855.72 102+01.91 102+04.26 855.64 855.54 102+12.54 102+14.88 855.45 855.34 102+23.16 102+25.51 855.23 855.13 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SA001.dgn Sheet 5/6/2022 4:53:32 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220JMKODW-45 20JMKRAILING DETAILS - 13"DETAILS POST CONNECTION TST-1-99 FOR SEE STD. DWG. W6x25 POST | RAILING (TST-1-99)1'-9•"| RAILING (TST-1-99) EDGE OF DECK TOP OF DECK AT VARIES10"VARIESTOP OF SIDEWALK 2•" 4" BOLT PROJECTION1'-9•"ON APPROACH SLAB TOP OF SIDEWALK 2" PEJF2'-3•"| RAILING (TST-1-99)1'-9•"1'-9•"MOT CONFIGURATION FINAL CONFIGURATION SECTION A-A3"SEE NOTE 2 1•"STD. DWG. TST-1-99 DETAIL ON SEE RAILING CONNECTION STD. DWG. TST-1-99 DETAIL ON SEE RAILING CONNECTION W6x25 POST DETAILS POST CONNECTION TST-1-99 FOR SEE STD. DWG. SEE NOTE 31•"3"STD. DWG. TST-1-99 DETAIL ON SEE RAILING CONNECTION 10"11…"1'-3"1'-6•"1'-3"1'-6•"9•"1'-6"4" BOLT PROJECTION 9•"3'-2"MOT CONFIGURATION FINAL CONFIGURATION W6x25 POST W6x25 POST SECTION B-B WINGWALL 2•" WINGWALL TS 4x4xŠ TS 4x4xŠ TS 4x3xŠ 21 24SHEET ) BASEPLATE AS SHOWN ON ON WINGWALLS (MODIFY FOR ANCHOR CONNECTION SEE STD. DWG. TST-1-99 TS 4x3xŠ SLAB TOP OF APPROACH C.J.3"VARIES10"VARIESDETAILS POST CONNECTION TST-1-99 FOR SEE STD. DWG.3'-6"3'-6"1"1"2•" 4" BOLT PROJECTION1'-9•"2" PEJF2'-2•"9•"1'-5"W6x25 POST WINGWALL 21 24SHEET ) BASEPLATE AS SHOWN ON ON WINGWALLS (MODIFY FOR ANCHOR CONNECTION SEE STD. DWG. TST-1-99 2"SEE STANDARD DRAWING TST-1-99 FOR SECTION AT BRIDGE SECTION AT WINGWALL SHOWN, 21 24SHEET ) MODIFY BASEPLATE AS SHOWN ON STD. DWG. TST-1-99 DETAIL ON CONNECTION SEE RAILING LEFT RAILING ONLY LEFT RAILING ONLY RIGHT RAILING TYPICAL SECTION STD. DWG. TST-1-99 DETAIL ON CONNECTION SEE RAILING 2" PEJF AS SHOWN) DIRECTLY AGAINST (PLACE OVERLAY TOP OF 3" OVERLAY TOP OF APPROACH SLAB 2" PEJF TS 8x4xŠ TS 4x4xŠ DETAILS CONNECTION GUARDRAIL TST-1-99 FOR SEE STD. DWG. (TST-1-99) | RAILING TS 4x3xŠ SIDEWALKDECK ANDBEAMBOXA A AT TS 8x4xŠ CONNECTIONS) AND LOCATIONS (TYP. FOR HOLE DIMENSIONS SEE STD. DWG. TST-1-99 B B W6x25 POST (TYP.) TOP OF WINGWALL | SPLICE AND WINGWALL OF ABUTMENT FRONT FACE END OF WINGWALL 21 24TYP. POST SPACING ON BRIDGE 6'-3" SEE TS 4 CONNECTION DETAIL ON SHEET | SPLICE AT EDGE OF DECK TOP OF SIDEWALK SEE ODOT STANDARD DRAWING TST-1-99 FOR RIGHT RAILING LEFT RAILING SHOWN, RAILING PARITAL ELEVATION SEE TS 4 TERMINATION DETAILS ON SHEET 21 24 21 24 TS 4x3xŠ CONNECTIONS) (TYP. AT TS 4x4xŠ AND FOR HOLE DIMENSIONS AND LOCATIONS 1'-8" 1'-8" (TYP.) ON SHEET SEE SPLICE DETAILS SOUTH END OF RAIL AND BOLT HOLES AT OMIT CONNECTION PLATE NOTES: 6. 5. 4. 3. 2. 1. 2 24 MODIFIED TST-1-99 RAILING. IN THE UNIT PRICE BID FOR ITEM 517 RAILING, MISC,: PAINTING, ANCHOR BOLTS, AND POSTS SHALL BE PAID FOR BUT NOT LIMITED TO, ALL BOLTS, PLATES, TUBES, CONSTRUCT THE RAILINGS AS SHOWN HEREIN INCLUDING, ALL MATERIALS, LABOR, AND EQUIPMENT NEEDED TO SPECIFICATIONS. SEE GENERAL NOTES ON SHEET FOR PAINT FABRICATION. DUBLIN ENGINEERS OFFICE FOR APPROVAL PRIOR TO SHOP DRAWINGS MUST BE SUBMITTED TO THE CITY OF CONCRETE AND FINISH INSTALLATION OF THE RAILING. BOLTS USING COUPLING NUTS. POUR THE PHASE 3 THREADED ROD EXTENSIONS TO THE EXISTING ANCHOR PLATE PER ODOT STANDARD DRAWING TST-1-99. INSTALL FROM THE ANCHOR BOLTS AND INSTALL A NEW SPACER DURING PHASE 3 CONSTRUCTION, REMOVE THE MOT RAILING INSTALL THE FINAL RAILING AS SHOWN ON THIS SHEET. SIDEWALK CONCRETE. REMOVE THE MOT RAILING AND AND STUDS, TOUCH-UP GALVANIZING, AND CAST INTO THE CONSTRUCTION, FIELD WELD THE TOP ROW OF SLEEVE NUTS OF STUDS AND SLEEVE NUTS. DURING PHASE 3 NUTS ATTACHED AS SHOWN. DO NOT ATTACH THE TOP ROW CONSTRUCTION WITH ONLY THE BOTTOM ROW OF SLEEVE CAST RAILING ANCHOR PLATES IN THE DECK DURING PHASE 1 DETAILS NOT SHOWN. MODIFIED BASE PLATE. SEE TST-1-99 FOR DIMENSIONS AND SHOWN IN THESE PLANS WITH ADDITIONAL TS 4 RAILS AND SHALL BE ODOT STANDARD DRAWING TST-1-99 MODIFIED AS WINGWALLS SHOWN IN THESE PLANS. THE LEFT RAILING TST-1-99 EXCEPT FOR THE MODIFIED BASEPLATE ON THE RIGHT RAILING SHALL BE ODOT STANDARD DRAWING 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SA002.dgn Sheet 5/6/2022 4:53:33 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220JMKODW-46 21AAARAILING DETAILS - 2T1 - PLAN T1 - ELEVATION T2 - ELEVATION T2 - PLAN TS 4x4xŠ TS 4x4xŠ 14° 14° 14° 14° T3 - ELEVATION T3 - PLAN TS 4x4xŠ TS 4x4xŠ TS 4x4xŠ TS 4x4xŠ | ‡" DIA. HOLE (TYP.)2"2"‡" DIA. HOLE (TYP.) | POST 1'-8‚"8ƒ" 1'-8‚"8ƒ" 3•"5Š" 7ˆ" 1ƒ"1ƒ"5Š" TS 4x4xŠ TERMINATION ASSEMBLY - PLAN TS 4x4xŠ TERMINATION ASSEMBLY - ELEVATION ‚ALL AROUND (TYP.) GROUND SMOOTH G 45° ‚ALL AROUND (TYP.) GROUND SMOOTH G 45° T1 T2 T3 T3 T2 T1 W6x25 POST W6x25 POST (AT EACH END OF LEFT RAILING) | ƒ" DIA. HOLES TYP. ‚ ‚ TYP. AND HEX NUT CAP SCREW WITH FLAT WASHER ASTM A499 †" DIA. x 1ƒ" LONG INNER SLEEVE SPLICE (TYP.) THE OUTER TUBE AND THE INNER TO PREVENT SLIDING BETWEEN NOT BE DRAWN UP SO TIGHT AS BOLTS IN SLOTTED HOLES SHALL INNER SLEEVE OUTER TUBE HOLES | INNER SLEEVE AND TUBE ONLY (TYP.) SLOTTED HOLE IN OUTER ƒ" WIDE BY 1•" LONG | SPLICE D D SECTION D-D - AT SPLICE †" DIA. HEX NUT TS 4X3xŠ TS 4x4xŠ OR 4"4"4"4"2" 1'-8" 2" - TS 4x3xŠ 3" - TS 4x4xŠ 3" } Š"x2•"x1'-8" (TS 4x3xŠ) }Š"x1…"x1'-8" (TS 4x4xŠ) } Š"x2…"x1'-8" GAP ‚" TS 4 SPLICE INNER SLEEVE SECTION TS 4 SPLICE ASSEMBLY SECTION 20'-0"R2'-5•" 1'-1•" 4'-7†" STRAIGHT2'-8„"CURVED STRAIGHT TS 8x4xŠ TS 8x4xŠ BENDING PLAN AT RIGHT REAR WINGWALL, TYPICAL OF 2-TS 8x4xŠ MEMBERS WINGWALLFACE TRAFFIC 2"2"•"| POST 1•"C C VIEW C-C IN TUBE (TYP.) ‡" DIA. HOLE OF POST (TYP.) TRAFFIC SIDE FLANGE SLOTTED HOLE IN ‡" WIDE x 1‡" HIGH (TYP.)2"(TYP.) AND TUBE FLANGE | HOLE IN 2"10"2"1'-2"7"7"MODIFIED BASE PLATE (TYP.) 1‚" HOLE ‹ ‹Š POST 1‚" PLATE FACE TRAFFIC TS 4 CONNECTION DETAIL 5"7" 3Ž"6…"1Ž" 1'-0" TOP OF POST (TYP.) 1ƒ" TS 4x4xŠ TS 4x4xŠ TS 4x3xŠ POST W6x25 HEX NUT AND WASHER BUTTON HEAD BOLTS WITH ƒ" DIA. x 4•" LONG A307 POST TS 4x3xŠ AND | BOLT HOLE IN TS 4x3xŠ HEX NUT AND WASHER BUTTON HEAD BOLTS WITH ƒ" DIA. x 5•" LONG A307 POST TS 4x4xŠ AND | BOLT HOLE IN WP 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SM002.dgn Sheet 5/6/2022 4:53:34 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 43220NNJMKJMKBDE-47 22APPROACH SLAB PLANA A 11'-3•"SLEEPER8'-0" SLAB SLAB SEAT 6" APPROACH SHAWAN FALLS DR. \ CONST. PHASE C.J. A1B2 4 D 3 C 10 K 9 12 N 11 M J L 20'-0" APPROACH SLAB PLAN - REAR ABUTMENTPHASE 2 CONST.29'-10‡"PHASE 1 CONST.24'-0" PLUS FIT-UP53'-10‡" PLUS FIT-UP3" A B XX YY101+50 ** ** **3"FIT-UP8'-0†" PLUSFIT-UP7'-3•" PLUSSTEEL NOT SHOWN) (APPROACH SLAB REINFORCING LEFT CURB DETAIL9"1•"A.S.1'-1" OVERLAY 3" ASPHALT 3" RAD. C.J. SECTION C-C SECTION B-B SECTION A-A 7'-3•" PLUS FIT-UP (F.A.) 8'-0†" PLUS FIT-UP (R.A.) VARIES 7'-3•" TO 1.6% 7'-3•" PLUS FIT-UP VARIES 5'-5„" TO 7'-3•" PLUS FIT-UP S408 S409 (SEE SECTION A-A FOR INFORMATION NOT SHOWN) (SEE SECTION A-A FOR INFORMATION NOT SHOWN) TO 9" VARIES 3" A.S.1'-1" OVERLAY 3" ASPHALT ON THIS SHEET CURB DETAIL SEE LEFT REINFORCING NOT SHOWN) (APPROACH SLAB S408 (F.A.) S405 (R.A.) S409 (F.A.) S406 (R.A.) S402* S401* S402* S401*SIDEWALKVARIESSIDEWALKVARIESSIDEWALKVARIESVARIES OF REINFORCING STEEL APPROACH SLAB TOP LAYER NOTE 4 SEE S412 S411 OR OF 8) S410 (TYP. S411 S403 9'-3•" PLUS FIT-UP 1.6%1.6% 1.6%OVERLAY3" ASPHALTA A B B C C 11'-3•"SLABSLEEPER8'-0" SLAB SEAT 6" APPROACH SHAWAN FALLS DR. \ CONST. PHASE C.J. P 15 S 16 14Q13 R 7 8 FE G H 5 6 20'-0" APPROACH SLAB PLAN - FORWARD ABUTMENTPHASE 2 CONST.27'-3•"PHASE 1 CONST.24'-0" PLUS FIT-UP51'-3•" PLUS FIT-UP3"1'-0" C D EF 102+50 ** ** **3"FIT-UP7'-3•" PLUSGTRANSISTION 6'-6"H J S411 S403 11"6"`2'-0"NOTE 4 SAWCUT, SEE BOUNDARY FOR 15' -0"R11'-6‚" ELEVATIONSTATIONOFFSETPT.ELEVATIONSTATIONOFFSETPT. TOP OF SLEEPER SLAB ELEVATIONS NOTES: LEGEND: TOP OF APPROACH SLAB ELEVATIONS*** CONSTRUCTION OF THE ASPHALT OVERLAY AT THE TOP OF CONCRETE, PRIOR TO TOP OF APPROACH SLAB ELEVATIONS ARE GIVEN *** ¬ ¬ ¬ ¬ ¬ ¬ ¬ ¬ ELEVATION: +0.01', -0.00' OFFSET: +0.00', -0.21' STATION: +0.14', -0.00' FIT-UP AS FOLLOWS: 2•". ACTUAL VALUES MAY VARY BASED ON THE ACTUAL ASSUMING THE MAXIMUM ALLOWABLE FIT-UP ALLOWANCE OF ¬ = STATION, OFFSET, AND ELEVATION SHOWN ARE CALCULATED ABOVE TOP OF APPROACH SLAB ** = •" PEJF BETWEEN ADJACENT SIDEWALKS AND CURBS CEMENT PER 510. DURING PHASE 3 CONSTRUCTION. GROUT HOLES WITH * = DOWEL S401 & S402 BARS 3" MIN. INTO APPROACH SLAB 4. 3. 2. 1. INCLUDED WITH THE APPROACH SLAB FOR PAYMENT. PLACED IN DIRECT CONTACT WITH THE REINFORCING STEEL. COST OF CONCRETE REMOVALS IS TO A DEPTH OF 1" BELOW THE TOP LAYER OF REINFORCING STEEL. PNEUMATIC HAMMER SHALL NOT BE THE WEIGHT OF THE HAMMER SHALL NOT BE MORE THAN 10 POUNDS. CONCRETE SHALL BE REMOVED MEANS OF APPROVED HAND-OPERATED HAMMERS EMPLOYING POINTED OR BLUNT CHISEL TYPE TOOLS. SAWCUT BOUNDARIES OF PROPOSED CONCRETE REMOVALS 1" DEEP. CONCRETE REMOVAL SHALL BE BY APPROACH SLAB INSTALLATION SHALL BE TYPE A. SEE ODOT STANDARD DRAWING AS-2-15 FOR ADDITIONAL DETAILS AND SLEEPER SLAB DIMENSIONS. PAYMENT WITH ITEM 509 - EPOXY COATED REINFORCING STEEL. COC 2 CONCRETE, SIDEWALK. REINFORCING STEEL FOR THE SIDEWALK SHALL BE INCLUDED FOR BE EPOXY COATED. SIDEWALK CONCRETE SHALL BE INCLUDED FOR PAYMENT WITH ITEM 511 - CLASS 526 - REINFORCED CONCRETE APPROACH SLABS (T=13"), AS PER PLAN. ALL REINFORCING STEEL SHALL APPROACH SLAB CONCRETE AND REINFORCING STEEL SHALL BE INCLUDED FOR PAYMENT WITH ITEM CALLOUTS XX AND YY ARE IN ADDITION TO REINFORCING SHOWN IN THE STANDARD DRAWING. SEE STANDARD DRAWING AS-1-15 FOR REINFORCING IN APPROACH SLAB. REINFORCING GIVEN IN S R Q P N M L K J H G F E D C B A 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 102+48.31 102+28.46 102+38.04 102+18.04 101+62.90 101+70.83 101+82.36 101+51.94 101+71.94 102+30.56 102+10.56 102+14.54 101+94.71 101+44.47 101+64.47 101+28.61 101+48.61 16.00' R 16.00' R 0.00' 0.00' 17.83' R 16.00' R 16.00' R 0.00' 0.00' 11.29' L 11.29' L 35.50' L 35.50' L 11.29' L 11.29' L 35.50' L 35.50' L 102+53.42 102+43.83 102+42.83 102+33.24 101+59.46 101+67.79 101+47.14 101+56.74 102+35.36 102+25.77 102+19.34 102+09.74 101+39.67 101+49.26 101+23.65 101+33.24 16.00' R 16.00' R 0.00' 0.00' 18.62' R 16.70' R 0.00' 0.00' 11.29' L 11.29' L 35.50' L 35.50' L 11.29' L 11.29' L 35.50' L 35.50' L 854.34 854.78 854.82 855.25 855.79 855.74 855.59 856.18 855.98 854.80 855.22 854.75 855.10 856.05 855.88 855.74 855.63 853.16 853.35 853.63 853.84 854.73 854.68 855.13 855.05 853.61 853.83 853.57 853.76 854.99 854.93 854.68 854.64 YY = 3-#10 BARS 12'-5" LONG (BOT.) , 2-#5 BARS 8'-8" LONG (TOP) XX = 4-#5 BARS 3'-6" LONG, T&B J = 1 S.O. 6-S412 @ 11" (FIELD BEND AS NECESSARY) H = 4-S411 @ 11" (FIELD BEND AS NECESSARY) G = 1 SET OF 8-S410 @ EQ. SPA. F = 1 SET OF 1-S401, 1-S402, & 1-S403 E = 1 S.O. 8-S409 @ EQ. SPA. D = 12 SETS OF 1-S401, 1-S402, & 1-S408 @ 1'-0" = 11'-0" C = 1 S.O. 4-S407 @ 4-S402 @ 1'-0" = 3'-0" B = 1 S.O. 9-S406 @ EQ. SPA. A = 1 S.O. 20-S405, 20-S401, & 20-S402 @ 1'-0" = 19'-0" 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SL001.dgn Sheet 5/6/2022 4:53:35 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 4322048JMKJMKREINFORCING STEEL LIST - 1ODW23 MARK NO.LENGTH WEIGHT TYPE DIM. A DIM. B DIM C DIM D DIM E/RAD.INCR. REINFORCING STEEL LIST - ABUTMENTS MARK NO.LENGTH WEIGHT TYPE DIM. A DIM. B DIM C DIM D DIM E/RAD.INCR. A601 A558 A557 A556 A555 A554 A553 A552 A551 A550 A549 A548 A547 A546 A545 A544 A543 A542 A541 33 2 14 2 2 2 4 4 1 1 2 2 8 7 S.O. 1 11 2 2 4 4 TOTAL 6'-10" 9'-11" 6'-2" 7'-9" 18'-1" 17'-9" 17'-10" 17'-7" 16'-8" 19'-3" 13'-0" 7'-5" 10'-2" 12'-7" TO 9'-1" 17'-11" 22'-10" 21'-10" 22'-7" 21'-7" 15755 339 21 90 16 38 37 74 73 17 20 27 15 85 79 206 46 94 90 1 20 26 STR 20 20 20 20 20 20 STR 20 STR 18 18 STR STR STR 6'-0" 2'-7" 2'-3•" 0'-8•" 0'-8•" 0'-8•" 0'-8•" 0'-5•" 4'-4" 3'-3" 1'-2" 1'-2" 1'-0" 1'-8" 0'-9•" 3'-2" 2'-11•" 3'-2" 3'-0•" 1'-11•" 2'-1•" 0'-10" 5'-10" TO 4'-1" 8'-6" 6'-11" 1'-5•" 14'-10•" 14'-8•" 14'-7•" 14'-5•" 14'-7•" 14'-5•" 4'-2" 5'-10" TO 4'-1" 8'-6" 1'-6" 1'-11" 0'-7" 10 2 7 S.O. 1 15 5 3 S.O. 2 3 2 4 S.O. 2 6 63 36 2 4 8 3 S.O. 2 6 S.O. 2 14 4 13 13 38 127 290 2 4 2 14 16 10 2 17 16 3 S.O. 2 516 4 S.O. 8 28 8 14 120 169 13'-6" 11'-10" 9'-5" TO 7'-7" 16'-5" 6'-5" 5'-11" TO 2'-2" 2'-2" 9'-5" 5'-8" TO 4'-0" 8'-5" 2'-1" 3'-9" 10'-10" 12'-5" 12'-2" 12'-2" TO 7'-6" 5'-10" TO 3'-8" 8'-0" 29'-8" 6'-3" 5'-11" 4'-11" 7'-2" 6'-9" 3'-8" 6'-0" 6'-11" 9'-0" 28'-0" 10'-0" 18'-9" 7'-6" 14'-10" 6'-2" TO 2'-6" 6'-8" 5'-7" TO 1'-0" 7'-1" 12'-2" 6'-3" 30'-0" 4'-6" 141 25 62 257 33 25 7 20 40 53 137 141 23 52 102 62 59 117 124 85 80 195 949 2042 8 25 14 131 467 104 39 133 248 27 3588 110 207 102 91 3755 508 STR 20 18 18 STR STR STR 20 STR STR 18 18 20 STR STR STR STR STR STR 20 3 STR 99 1 STR STR 20 STR STR STR 3 STR STR STR STR STR STR 3 STR STR 18 8'-9" 1'-2" 1'-2" 5'-0" 0'-8" 0'-8" 6'-9" 2'-0" 1'-4" 1'-0" 6'-0" 1'-8" 2'-8" 1'-11" 0'-8" 1'-1" 4'-3" TO 3'-4" 7'-9" 2'-10" 0'-10" 1'-8" 2'-10" 1'-4" 2'-0" 0'-8†" 0'-10" 3'-10" 4'-0" 2'-11" 2'-0" 3'-2" 4'-3" TO 3'-4" 7'-9" 3'-8" 0'-10" 1'-8" 3'-7" 3'-11" 1'-3" 2'-11" 2'-9" 2'-5" 2'-5•" 2'-0" 2'-5" 0'-9" 11'-8" 6'-4•" 2'-4" 0'-3†" 1'-10•" 0'-6†" 2'-4" 0'-5‚" 1'-10" 1'-6…" REINFORCING STEEL LIST - ABUTMENTS (CONTINUED) TYPE 1 A BTYPE 3 BCA D TYPE 18 CAB TYPE 20ACB TYPE 26A DCB E1 1 AB C DETYPE 99 NOTES: 1.24 24SEE SHEET FOR NOTES AND LEGEND. A540 A539 A538 A537 A536 A535 A534 A533 A532 A531 A530 A529 A528 A527 A526 A525 A524 A523 A522* A521 A520 A519 A518 A517 A516 A515 A514 A513 A512* A511 A510 A509 A508 A507 A506 A505* A504 A503 A502 A501* A401 2568773SHAWAN FALLS DRIVE BRIDGEOVER SOUTH FORK INDIAN RUN24DATESTRUCTURE FILE NUMBERREVIEWEDJCS3/8/22REVISEDDRAWNCHECKEDDESIGNEDDRIVESHAWAN FALLS P:\PR58074\FRA\000000\Design\Structure\Sheets\SL002.dgn Sheet 5/6/2022 4:53:36 PM jkelley66EngineersArchitectsPlanners 5085 REED RO AD, COLUMBUS, O HIO 4322049JMKJMKREINFORCING STEEL LIST - 2ODWMARK NO.LENGTH WEIGHT TYPE DIM. A DIM. B DIM C DIM D DIM E/RAD.INCR. 70 4 8 8 16 127 127 TOTAL 4'-8" 6'-0" 29'-8" 4'-11" 29'-8" 3'-3" 3'-7" 2705 872 36 356 41 495 430 475 28 STR STR STR STR 18 16 1'-5" 1'-6" 1'-0" 1'-6" 2'-4†" 0'-6" 0'-6" MARK NO.LENGTH WEIGHT TYPE DIM. A DIM. B DIM C DIM D DIM E/RAD.INCR. REINFORCING STEEL LIST - DECK AND SIDEWALK NOTES: LEGEND: TYPE 18 CAB TYPE 20ACB TYPE 1 A BTYPE 16 BA TYPE 28 135° B BEND STD. 180°A* = A BAR. INDICATES A STANDARD BEND AT THE END OF STD. WRITTEN IN PLACE OF A DIMENSION SERIES BARS. INCR. INDICATES THE LENGTH INCREMENT FOR OTHERWISE NOTED. RAD INDICATES INSIDE RADIUS, UNLESS STRAIGHT BAR. STR. IN THE BAR TYPE COLUMN INDICATES A UNLESS OTHERWISE INDICATED. BAR DIMENSIONS SHOWN ARE OUT-TO-OUT 01 = BAR SEQUENCE NUMBER 1 10 = #10 BAR SA = SUPERSTRUCTURE BAR EXAMPLE: SA1001 THE SEQUENCE NUMBER. THE BAR SIZE, AND THE REMAINING TWO DIGITS ARE LOCATION. THE NEXT ONE OR TWO DIGITS INDICATE LETTERS OR NUMBERS THAT IDENTIFY THE BAR BAR MARK. THE MARK BEGINS WITH TWO OR THREE BAR SIZE: THE BAR SIZE IS INDICATED IN THE ALL REINFORCING STEEL SHALL BE EPOXY COATED. 7. 6. 5. 4. 3. 2. 1. D801 D602 D601* D504 D503* D502 D501 REINFORCING STEEL LIST - DIAPHRAGMS MECHANICAL CONNECTOR FURNISHED. NECESSARY DEPENDING UPON THE TYPE OF AND/OR BAR END PREPARATION MAY BE CONSTRUCTION JOINT. EXTRA BAR LENGTH CONNECTOR. BAR LENGTH IS MEASURED TO THE REINFORCING BAR UTILIZES A MECHANICAL S603 S602* S601* S412 S411 S410 S409 S408 S407 S406 S405 S404 S403 S402 S401 72 49 49 6 S.O. 1 5 8 S.O. 1 8 S.O. 1 12 4 S.O. 1 9 S.O. 1 20 S.O. 1 16 41 76 72 TOTAL 24'-3" 32'-6" 28'-10" 8'-4" TO 1'-4" 9'-2" 11'-6" TO 7'-0" 16'-1" TO 11'-4" 7'-2" 6'-0" TO 1'-6" 19'-7" TO 19'-0" 9'-6" TO 8'-7" 23'-10" 8'-7" 2'-0" 1'-9" 8288 2622 2392 2122 19 31 49 73 57 10 116 121 255 235 102 84 STR STR STR STR STR STR 20 STR STR STR STR STR STR 1 1 0'-6" 0'-9" 0'-9" 6'-6" 1'-4" 1'-1" 9'-7" TO 4'-10" 1'-4ƒ" 0'-7ƒ" 0'-8„" 1'-6" 0'-0‡" 0'-0†" 24 JZM 66 4/7/22 58074 P:\PR58074\FRA\000000\Design\Signals\Sheets\CN001.dgn Sheet 5/6/2022 5:00:59 PM jkelleyEMW JZM EMW NONE 52 52 BRIDGE REPLACEMENTSHAWAN FALLS DRIVE& W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ NOTES TRAFFIC SIGNAL GENERAL These specifications, together with the accompanying plans, are intended to describe the type, size, and location of the products and materials to be provided and installed under various bid items related to traffic control. The Contractor shall furnish and install traffic control devices and related materials in compliance with these plans and specifications, as well as the Specifications, the Ohio Manual of Uniform Traffic Control Devices (OMUTCD) for Streets and Highways, and the Standard Construction Drawings issued by the ODOT. These specifications set forth the minimum performance and operating requirements of the traffic control items referred to herein. The signal controller(s), conflict monitor(s), terminal facilities, flashers and load switches shall preferably be of the same manufacture. All load switches interface relays shall be furnished with input side LED's UNDERGROUND UTILITIES The location of the underground utilities shown on these plans are as obtained from the owners of the utility as required by Ohio Revised Code section 153.64 The City of Dublin and the Engineer assume no responsibility for the accuracy of the location or the depths of the underground facilities shown on these plans. Support, protection, and restoration of all existing utilities and appurtenances shall be the Contractor's responsibility. The cost of this work shall be included in the bid price for the various items of work. It shall be the Contractor's responsibility to notify the Ohio Utilities Protection Service (OUPS) so their respective facilities can be marked prior to construction. PLAN AND SPECIFICATION COMPLIANCE The Contractor shall furnish and install traffic signal devices in compliance Material Specifications including all supplemental specifications, the Ohio Manual of Uniform Traffic Control Devices for Streets and Highways, and the "TC" and "HL" standard construction drawings issued by ODOT. These specifications set forth the minimum design and operating requirements for traffic signal. Traffic signal control equipment shall meet or exceed the standards specified in the following documents: a)Specifications listed in this plan. b)NEMA Standards Publication no. TS1-1989 and/or TS2-2003 (or current NEMA issue) sections 1, 2, 5, 6, 8, 11,13 and 14. c) 725, 732, 733, 815, 816, 906 and 907. In case of a conflicting specification statement, the specification document hierarchy shall be in the order listed from (A), highest, to (C), lowest. GUARANTEE The Contractor shall guarantee that the traffic control equipment installed as part of this contract shall operate satisfactory for a period of 1 year following completion of the 10 day performance test. In the event of unsatisfactory operations, the Contractor shell correct faulty installations, make repairs and replace defective parts with new parts from the same manufacturer. Material and labor cost incurred in correcting the unsatisfactory operations shall be borne by the Contractor. Customary manufacturers guarantees for the foregoing items shall be turned over to the City of Dublin following acceptance of the equipment. The cost of guaranteeing the traffic control equipment shall by incidental to and included in the contract unit price of the various items making up the signal installation. The Contractor shall be responsible for maintaining traffic signal installations within the project under the following conditions: 1.The Contractor shall be responsible for existing signal installations which the plan requires the Contractor to adjust, modify, add on to, or remove, or which the Contractor actually adjusts, modifies, or otherwise disturbs, from the time his operations first disturb the installation until the time the installation has subsequently been removed or modified and the work has been accepted. 2.The Contractor shall be responsible for maintenance of new signal installations or devices, installed by the Contractor, from the time of installation until the work is accepted. The Contractor shall correct as quickly as possible all outages or malfunctions. He shall provide the Engineer such addresses and phone numbers where his maintenance forces can be contacted. The Contractor shall provide one or more persons to receive all calls and dispatch the necessary maintenance forces to correct outages. Such a person or persons may be used to perform other duties as long as prompt attention is given to these calls and a person is readily available continuously 24 hours a day, 7 days a week. All lamp outages, cable outages, electrical failures, equipment malfunctions and misaligned signal heads shall be corrected to the satisfaction of the Engineer with the signal back to service within four hours after the Contractor has been notified of the outage. In the event new signals are damaged prior to acceptance all damaged equipment except poles and control equipment shall be replaced by the Contractor to the satisfaction of the Engineer with the signal back in service within 8 hours after the Contractor's notification of the outage. If poles and/or control equipment are damaged and must be replaced, the Contractor shall make temporary repairs as necessary to bring the signal back into full operation within the allowed 8-hour period, and shall make permanent repairs or replacement as soon thereafter as possible. None of the above shall be construed as collective or consecutive outage time periods at any one location. That is, where more than one outage occurs at any one location, then the allotted time limit shall be for the worst single outage. Where outages are the direct result of a vehicular crash, the response of the Contractor shall be as outlined above. The Contractor shall be responsible for collection of any compensation for this work from those parties responsible for the damage. Where the Contractor has failed to or cannot respond to an outage or signal equipment malfunction, at these locations within his responsibility, within periods as specified above, the Engineer may invoke the provisions of Section 105.15 and any subsequent costs to the City of Dublin for Police Services and Maintenance Services shall be deducted from monies due or to become due the Contractor in accordance with provisions of Section 105.15. When a left turn movement is unavailable, the left turn green and yellow arrows shall be covered leaving circular red, yellow, and green display visible. Any signalized intersection, where the signal is out of service due to construction procedures, or due to an outage or malfunction of equipment Any vehicular traffic signal head which will be out of operation shall be covered in the manner described in 632.25. All costs resulting from the above requirements shall be considered to be included in the lump sum price bid for Item 614 Maintaining Traffic, As Per Plan. PAINT CHIP SUBMITTAL Prior to any painting, the Contractor shall submit paint samples to the Engineer for review and comment. Paint samples shall be representative of the color, type and manufacture that will be used for finishing the various items. The Engineer shall review the paint samples prior to the commencement of the finishing process. Paint samples shall be submitted for all proposed traffic signal items called for in this plan set, including, signal supports, signal heads, pedestrian heads, pushbuttons, signs, bracket arms, luminaires and controller cabinets. Any cost associated with providing paint samples shall be incidental to the individual items to be painted. GROUNDING AND BONDING The requirements of the Construction and Material Specifications (C&MS) and the HL and TC series of Standard Construction Drawings are modified as follows: 1. joined to form an Effective Ground Fault Current Path back to the grounded conductor in the power service disconnect switch. a)Provide an equipment grounding conductor in metallic conduits (725.04) in addition to the conductors specified and bond the conduit to this grounding conductor. b)When an equipment grounding conductor is required in plastic conduit (725.05), the installation shall include a separate equipment grounding conductor in addition to the conductors specified. c)Metallic conduit carrying the loop wires from in the pavement to the pull box splice location will only be bonded at the pull box end, and will not contain an equipment grounding conductor. d)Metal pull box lids shall be bonded by attachment of the equipment grounding conductor to the frame diagonal as provided on HL-30.11. e)If multiple conduit runs begin and end at the same points, only one equipment grounding conductor is required. 2.Conduits. a)The 725.04 conduit shall have grounding bushings installed at all termination points. The bushing material shall be compatible with galvanized steel conduit and the grounding lug material shall be compatible for use with copper wire. Threaded or compression type bushings may be used. b)The 725.05 conduit shall have the inside and outside diameters of the conduit deburred at all termination points. c)Both ends of metallic conduit shall be bonded to the equipment grounding conductor. d)Metallic conduit may be bonded to metallic boxes through the use of conduit fittings UL approved for this type of connection, with the box bonded to the equipment grounding conductor. 3.Wire for grounding and bonding. a)Use insulated, copper wire for the equipment grounding conductor. Bonding jumpers in boxes and enclosures may be bare or insulated copper wire. Wire size shall be as follows: i.Use 4 AWG between the power service and supports, poles, pedestals, controller or flasher cabinets. ii.Use a minimum 8 AWG between loop detector pull boxes and the first conduit that requires a larger size as specified in 3.a.i above. iii.The insulation shall be green or green with yellow stripe(s). For 4 AWG or larger, insulation may also be black with green tape/labels installed at all access points. b)In a highway lighting system, the equipment grounding conductor shall be the same wire size as the duct cable or distribution cable circuit conductors, with the minimum conductor size of 4 AWG. Bonding jumpers will be minimum size 4 AWG. 4.Ground rod. a)A 3/4 inch Schedule 40 PVC conduit will be used in foundations and concrete walls for the grounding conductor (ground wire) raceway to the ground rod. Should metallic conduit be used, both ends of the conduit shall be bonded to the grounding conductor. b)The typical grounding conductor (ground wire) shall be 4 AWG insulated, copper. 5.The green conductor in signal cables (conductor #4) shall not be used to supply power to a signal indication. It will be connected to the signal body as an equipment ground in aluminum heads and it will be unused in plastic heads. Unused conductors shall be grounded in the cabinet. Typical use of conductors is as follows: Cond. No. Color Vehicle Signal Pedestrian signal 1 Black 2 White 3 Red Red Ball 4 Green 5 Orange 6 Blue 7 North DON'T WALK 6.Power Service and Disconnect Switch. 1.At the power service location, the grounding conductor (ground wire) from the disconnect switch neutral (AC-) bar to the ground rod shall be a continuous, unspliced conductor. If spliced, it shall be an exothermic weld butt splice. 2.The service neutral (AC-) shall only be connected to ground at the main power service disconnect switch. i.NEMA controller cabinets: If a power service disconnect switch is located before the controller cabinet, the neutral (AC-) and the grounding bars in the controller cabinet shall not be connected together as shown in NEMA TS-2, Figure 5-4. ii.If secondary disconnect switches are connected after the main disconnect switch, the neutral (AC-) shall only be grounded at the main switch. Equipment grounding conductors shall be brought to the main switch, but shall be grounded at both secondary and main switches. Payment for the above work shall be incidental to "Item 625 No. 4 AWG ITEM 625 PULL BOX, 725.07, 18”, AS PER PLAN In addition to the specifications of ODOT Item 625, the unit supplied and installed shall be a Hubbell Power Systems, Part Number Quazite PG1118BA18 or approved equal. Overall dimensions of the pull box shall be 11” wide by 18” long by 18” deep. “TRAFFIC” shall be on raised letters or embossed letters on the pull box cover. All pull boxes within or adjacent to sidewalk shall be flush with the walk. Any rock excavation required to install pull boxes shall be considered incidental to this item of work. Payment shall be per item 625. Pull boxes shall be per the details furnished within. All pull boxes within or adjacent to sidewalk shall be flush with the walk. Any rock excavation required to install pull boxes shall be considered incidental to this item of work. Payment shall be per item 625. ITEM 625, GROUND ROD, AS PER PLAN In addition to Items 625 and 725, this item shall also include a cadweld wire connection at the ground rod (as per city of Dublin Specifications), the cost of which shall be included in the ground rod installation. It is the intent of this item that the No. 4 AWG grounding conductor be installed in the 3/4” conduit between the ground rod and the enclosure ground bar, or service neutral at main switch, as per City of Dublin specifications. Payment shall be per Item 625. In addition to Item 625 and 725 of the ODOT Standard Specifications, the conduit shall be Schedule 80 PVC conduit. Six inch conduit sleeves should meet, but shall not enter pull boxes or pole foundations. Payment shall be per item 625. A green colored, insulated, cable shall be used for the ground wire (GND) where indicated. This GND cable shall be separate from the ground rod wire, but shall be connected to the same grounding bolt used for the ground rod wire attachment at the pole. The GND cable shall be tagged as "GND SYS" at all pole locations & control cabinets. Payment shall be as per Item 625. ITEM 625 TRENCH, AS PER PLAN In addition to the requirements of Item 625, the trench, depth and backfill material shall be as specified herein. Street crossings shall be backfilled with compacted Item 304 or 613 Type 2 or 3. Concrete encasement shall not be used. Metalized Plastic caution tape (3 in.) shall be furnished and installed under this item of work. The tape shall be three inch yellow plastic caution tape. The tape shall be installed over all 725.05 conduit, outside of driveways and roadway, as per City Specifications. The installation depth of the proposed conduit shall correlate to the depth of the pull box structure serving the conduit run. It shall be the Contractors responsibility to modify the depth of the conduit to accommodate the various termination depths. Sharp changes in conduit elevation will not be permitted. If both ends of a conduit run enter the same size structure, then the entire length of conduit shall be placed at that depth. If the two ends enter different depth structures the change in elevation shall be made over the entire length of the conduit run. Any rock excavation required to achieve proper trench depth shall be considered incidental to this item of work. Payment shall be as per Item 625. "TRAFFIC" shall be on raised letters on the pull box cover. MAINTENANCE OF TRAFFIC SIGNAL INSTALLATIONS ITEM 625 NO. 4 AWG 600 VOLT DISTRIBUTION CABLE, AS PER PLAN ITEM 625 PULL BOX, MISC.: 725.08, 27" AS PER PLAN ITEM 625 PULL BOX, 725.08, 32", AS PER PLAN ITEM 625, CONDUIT, JACKED OR DRILLED, 725.051, AS PER PLAN, 6" 2019 Ohio Department of Transportation (ODOT) Construction and Material with these plans and specifications, the 2019 ODOT Construction and as described above, shall be placed under law enforcement officer control. Metallic parts containing electrical conductors shall be permanently East DON'T WALK 8 9 10 L/T Red Arrow Neutral Neutral Yellow Ball Green Ball South DON'T WALK South WALK West DON'T WALK West WALK L/T Green Arrow North WALK White w/Black Tracer L/T Yellow Arrow Orange w/Black Tracer Red w/Black Tracer Green w/Black Tracer R/T Red Arrow R/T Yellow Arrow R/T Green Arrow NOT USED East WALK 2019 ODOT Construction and Material Specifications 625, 632, 633, 600 Volt Distribution Cable, As Per Plan". P:\PR58074\FRA\000000\Design\Signals\Sheets\CN001.dgn Sheet 5/6/2022 5:01:18 PM jkelleyJZM 66 4/7/22 58074 EMW JZM EMW NONEBRIDGE REPLACEMENTSHAWAN FALLS DRIVE53 53 & W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ NOTES TRAFFIC SIGNAL The Contractor shall furnish and install a Cree Luminaire Luminaires shall be manufactured by Cree, Inc. 4600 Silicon Drive, Durham, North Caroline, 27703, www.cree.com. Luminaires shall operate on 120 volt/60 hertz circuits. All mounting hardware and bracket arms shall be considered incidental to this item. Luminaires shall be as per item 625 except that the luminaires at each intersection shall run off a single photoelectric cell. The luminaire and all mounting hardware shall be painted to match the signal support. Measurement and payment shall be as per Item 625. ITEM 625 BRACKET ARM, 6', AS PER PLAN Bracket arms shall be furnished as per 625 except that the bracket arms shall be coated to match the signal supports. Bracket arms shall be monotube, tapered elliptical arms that match the bracket arms furnished for the lighting plan. The rise of the bracket arm shall not exceed the height depicted on the detail, measured from the vertical center of the arm at the attachment end to the vertical center of the arm at the opposite end. Payment shall be as per Item 625. Under this item of work the Contractor shall furnish and install LED internally edge lit street name signs, as manufactured by National Sign and Signal, 301 South Armstrong Road, Battle Creek, Michigan 49015 (269) 963-2817 or approved equal. Internally illuminated signs shall be supplied with all the hardware for mounting to the specified mast arm. The sign shall be constructed of cast and extruded aluminum components welded to provide a weatherproof housing suitable for outdoor use. Drip rails shall overhang the sign face to prevent water from entering the electrical housing. Drain holes shall be provided in the bottom of the housing. Each door shall be secured to the housing by a full length, open, stainless steel hinge on the door and three-quarter turn air lock fasteners. A neoprene gasket shall form a watertight seal between the door and the housing. The exterior of the sign housing shall be primed and coated to match the signal supports. Surface preparation shall be as per the paint manufacturer's recommendations. Prior to painting the Contractor shall submit paint samples to the Engineer and Dublin officials for review and comment. All sign components shall be accessible when one door is open and shall not require removal of the sign for access or maintenance operations. LED's shall be mounted to a white aluminum panel and have a conformal coating applied for protection. LED drivers shall be housed inside the sign enclosure and shall not be visible from the exterior. Signs shall operate on 120 volt/60 hertz power and shall be capable of continuous operation over a range in temperatures from -35 degrees to 140 degrees Fahrenheit. A wire entrance junction box shall be supplied with the sign and shall mount inside the sign enclosure. Signs shall not have individual photocells. The sign face shall be constructed of shatterproof, translucent polycarbonate material. The sign face and legend shall conform to the requirements of the Ohio Manual of Uniform Traffic Control Devices. The background color shall be translucent white. Black letters shall be twelve inch upper case and nine inch lower case. A clear coat shall be applied to all sign faces to prevent fading and protect the surface. Mounting hardware shall be provided to rigid mount the sign in line, not below, with the mast arm using a two point attachment system. Mounting brackets shall be adjustable to allow the sign to hang plumb. All mounting hardware shall be manufactured of heat treated aluminum bar stock or galvanized steel of adequate design and strength for its intended use. All hardware, including stainless steel cables if used, shall be painted as per this specification to match the mast arm and support. The use of stainless steel banding will not be permitted. Payment for Item 630 Sign, Single Faced, Street Name, As Per Plan will be made at the contract unit price bid per each sign including all labor, ITEM 630 SIGN HANGER ASSEMBLY, MAST ARM MOUNTED, AS PER PLAN ITEM 630 SIGN SUPPORT ASSEMBLY, POLE MOUNTED, AS PER PLAN The back of all signs, mounting hardware, and support assemblies mounted on either signal supports or pedestal supports shall be coated to match its respective support. Finish requirements shall be in accordance with that listed for the support, pedestal, or light pole used for attachment. All mast arm mounted signs shall be rigid mounted, with cable clamp assemblies. Stainless steel banding will not be permitted. Payment shall be as per Item 630. ITEM 632 SIGNAL CABLE, (BY CONDUCTOR), NO. 14 AWG, AS PER PLAN In addition to the requirement of Item 632 and 725 the following shall also apply: -All wire splices shall be waterproof splices, butt splices are not acceptable. However, splices will only be permitted where indicated. -Signal cable jackets shall not be removed or pulled back leaving exposed wires or colored insulation jackets outside of signal heads. Jackets are to be only pulled back once cable has been pulled into signal head. -Three feet of slack is required (drip loop) in cable adjacent to signal heads. -A separate 7 conductor signal wire shall be used for each signal heads. Signal wire shall not be spliced from a 3 section signal head to a 5 section head. -All cables entering and exiting a pull box shall be uniquely color coded to trace the wire through the intersection; colors shall be noted on signal plans in the signal cabinet. Payment shall be per Item 632. ITEM 632 POWER SERVICE, AS PER PLAN Power cable shall be provided as per 632.23 between the control cabinet and the tap-in location noted in the plan. When the power cable is in place and two weeks prior to the time that electrical power will be required, the Contractor shall contact the American Electric Power Company (Paul Paxton 614-883-6831 and Greg Zorich 614-883-7935) which will make the electrical service connection. Under no circumstances shall the Contractor connect power cable into the power company's circuits. A common photo electric relay and contactor with ON/OFF/AUTO switch shall control all street lighting and internally illuminated street name signs. The voltage supplied shall be 120/240 volts. 120 volts per circuit with one circuit for traffic signals and one circuit for street lighting and street name signs. Power and service cable conductors shall be copper. The neutral of the power cable shall only be grounded in the main power service disconnect switch at the signal support. Power Service shall also provide for the following: -Service shall be unmetered. -Power cable from the power source shall be routed in a separate conduit to the disconnect switch on the signal support closest to the controller (flex conduit inside signal support). A tracer wire shall be installed with the power cable from power source to the disconnect switch and continued into the signal cabinet. This tracer wire shall be identified at the transformer, disconnect, and signal cabinet. -The disconnect switch shall be stainless steel, NEMA 4X. -The disconnect switch and enclosure shall each include a padlock equal to Master No. 4B KA or Wilson Bohannon 66D with lock body of bronze or brass. All padlocks shall use the same key and four keys shall be given to the City. -The disconnect switch shall be GE a heavy duty safety switch (Model NP1578000K) or approved equal. Location and placement of disconnect to be field located at the signal support by City of Dublin representative. Two, one inch rigid conduits shall be installed on the bottom of the disconnect switch. -Provide for all copper conductors. All street lights installed on the combination signal supports shall be wired to a 120 volt circuit controlled at the signal controller cabinet at each intersection and include the following: -A fourth and fifth circuit breaker (20 amp), and a 2-pole lighting contractor on the cabinet side panel (electrically held, open style); -A photocell (3 position on-off-auto) rated as per City Specifications, installed on the signal support closest to the signal controller -All photocell wiring to the controller -All wiring to be controlled by a single disconnect switch for the signal and lighting. (Two 30 amp fuses-one for lighting, one for signal). Provide an available fault current sign on the outside of the front door of the power service disconnect switch in accordance with the National Electrical Code paragraph 110.24. Measurement and payment shall be as per Item 632. Service and power cable shall be provided as per 632.23 between the control cabinet and the utility tap-in location noted in the plan. When the service and power cable are in place and two weeks prior to the time that electrical power will be required, the Contractor shall contact the American Electric Power Company as specified under Item 632 Power Service, As Per Plan, which will make the electrical service connection. Under no circumstances shall the Contractor connect power cable into the power company's circuits. Power cable conductors shall be copper. The neutral of the power cable shall only be grounded in the main power service disconnect switch at the signal support. Power cable from the power source shall be routed in a separate conduit to the disconnect switch on the signal support closest to the controller (flex conduit inside signal support). A tracer wire shall be installed with the power cable from power source to the disconnect switch and continued into the signal cabinet. This tracer wire shall be identified at the transformer, disconnect, and signal cabinet. Flex conduit shall be incidental to this item of work. Measurement and payment shall be as per Item 632. Traffic signal supports shall be as per Item 632 except that the support poles and arms shall have a circular cross section and shall be tapered tubes having a true and continuous taper. Multi-sided or fluted poles and poles having a tapered effect accomplished with the use of reducers will not be accepted. Arm length shall be as specified but arms forty feet in length or less shall be of one piece construction. Arms more than forty feet long may be constructed in no more than two pieces. Supports shall be manufactured by Valmont or an approved equal. A two-piece anchor bolt cover shall be provided. Anchor bolts shall be oriented as required by the plans however the formed top of the support foundation shall be oriented square to the adjacent sidewalk where applicable. All signal cables shall be run inside the poles. Standard Drawing TC-83.10 is hereby modified to prohibit the use of external conduit risers for signal cabling, or any other use. The Contractor shall provide all necessary attachments or connections to the poles. Additional wiring holes in the pole shall be drilled, reamed, or hole sawed. Flame cutting (oxyacetylene or electrical arc) will not be accepted. All cut edges or other defects in the zinc coating shall be cleaned and covered with two coats of zinc rich repair paint matching the factory finish. Brackets and appurtenances shall be securely attached with stainless steel screws of sufficient size for the intended loading. Stainless steel banding shall not be used. The Contractor shall coordinate with City of Dublin Personnel, to be on site, prior to drilling or cutting signal supports which includes but is not limited to placement of pedestrian push buttons/signal heads, auxiliary signal heads and installation of the disconnect switch. All couplings fittings and attachment hardware necessary for bolting the disconnect switch to the signal support shall be field drilled, installed and furnished by the Contractor. Design Criteria In addition to the requirements of Item 632, signal support structures shall be designed and constructed by the supplier to support the loads caused by the signs, signals, and other equipment that the plan requires the Contractor to install. The use of standard ODOT design designations provided in this plan, are intended to promote uniformity of design and are not warranted to be structurally adequate. To the maximum extent practicable, the Contractor and supplier shall provide a structurally adequate support that utilizes standard ODOT anchor bolt sizing and spacing. The contractor shall verify the anchor bold circle, anchor bolt diameter, and orientation pattern with the signal support manufacturer. The mast arm support pole assembly, and the mast arm assembly shall be made by the same manufacturer and designed and sold as a unit. The manufacturer shall be responsible for verifying the pole design, and shall prepare shop drawings and structural design calculations stamped by an Ohio Professional Engineer. The shop drawings and calculations shall be submitted to the City of Dublin for approval prior to fabrication. The Contractor shall be responsible for verifying and coordinating with the pole manufacturer and the luminaire manufacturer the attachment requirements for installing the luminaire and bracket arm on the signal support. Luminaire shall be paid for under a separate item. All pre-drilled holes for all items shall be deburred and free of all sharp edges. All outside welds shall be rolled or ground smooth. All inside welds shall be void of sharp edges. Any structural fastener (3/4" or greater) shall be galvanized per ASTM 153 and shall be made of high strength carbon steel. Any other fastener (less than 3/4") shall be stainless steel. All visible fasteners shall match the coating of the structure. Finish Poles and arms, including base and flange plates, bolt covers, handholes, and wire entrances, shall be hot dipped galvanized after fabrication in accordance with 711.02. All visible elements of the signal support, and any other parts required to be coated, shall be galvanized and then powder-coated. All painting shall be performed under controlled environmental conditions, and in accordance with the paint manufacturer's recommendations pertaining to surface preparation, material handling, and application. The top finish coat of paint shall be similar to Federal Specification 595-B Color #27038, BLACK. Paint samples shall be submitted with the signal support shop drawings for review and approval prior to ordering material. The manufacturer shall be responsible for buffing/grinding the vertical welded seam flush with parent material to cosmetically blend the seam. The inside of each signal support pole assembly, each mast arm assembly, and other signal support accessories shall be coated with galvanizing material. The inside area formed by the gussets, pole, and pole flange plate shall be coated to protect the area from corrosion. It is to be noted that some type of opening shall be required to coat the gusset area. This opening shall not hamper the structural integrity of the flange assembly. All exterior surfaces of the signal support pole shaft assembly, mast arm assembly, all bolt covers, all clamps, clevis-to-clevis universal, wire entrance, all handhole covers, luminaire and brackets, pole and arm caps, signal head hangers and weather-heads shall have a coating properly applied to them. Exterior surfaces of all fastener bolts/screws, washers, nuts, and other attachment hardware shall have a coating applied to them. Fastener threads shall not be clogged with coating material. All coated items shall be shipped in a manner to minimize damage in transit. Surfaces should be protected by foam padding, by wrapping in cardboard, by spiral wrapping with wax paper, by crating, by a combination of methods, or by any other method selected by the manufacturer which will insure delivery of undamaged materials. Materials damaged in transit caused by improper packaging or improper transit handling shall be rejected. The Contractor shall be responsible for obtaining matching paint coating material for touch-up work identical to the original coating placed on the structure. Each coating layer shall be properly cured before the application of the next coat. The application procedure shall be such to guarantee a finish that will not scale, flake or peel, and will retain its color brightness and fresh, attractive appearance for 5 years without dulling or fading. The finishing process shall be Valmont V-Pro 54 providing a 5 year finish warranty or approved equal process. Payment This item of work shall be measured as each complete signal support, in place in essentially a vertical position under full plan loading. All labor, equipment, and materials necessary to pickup, transport, store, erect, adjust, and repair the signal support and anchor bolts shall be included for payment in the bid item. Payment shall be as per Item 632. such as those described on Standard Drawing TC-81.22, and any details materials, connections, cables, and appurtenances complete, in place, tested and accepted. ITEM 630 SIGN, STREET NAME, SINGLE FACED, ILLUMINATED, AS PER PLAN ITEM 632 POWER CABLE, 3 CONDUCTOR, NO. 6 AWG, AS PER PLAN ARE-EDG-3M-AA-08-E-UL-525-40K on signal supports where indicated. 110 WATT, AS PER PLAN ITEM 625 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED) TYPE III, PER PLAN ITEM 632 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, (BY SIZE), AS JZM 66 4/7/22 58074 EMW JZM EMW NONEBRIDGE REPLACEMENTSHAWAN FALLS DRIVE54 54 & W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ NOTES TRAFFIC SIGNAL Signal heads shall be as per Item 632 and shall be furnished with cut away visors and louvered aluminum backplates per ODOT Standard Drawing TC-85.20. Aluminum backplates shall have a factory applied black powder coat finish. Backplates shall not have a reflective yellow reflective border. Vehicular signal heads shall conform to the Equipment and Material Standards of the ITE as published by the Institute of Transportation Engineers and all indications shall use a light emitting diode (LED) light source conforming therewith. Vehicular signal heads shall be rigidly mounted to the signal support as per standard drawing TC-85.20. However, stainless steel banding will not be permitted. All bolts and washers for securing sections together, all mounting hardware for the lens, all door latching bolts, and all hinge pins shall be stainless steel. Vehicular signal heads shall be polycarbonate and the top and bottom of the housing shall have an opening to accommodate standard 1-1/2" pipe brackets. Mounting hardware shall attach to the signal head housing with tri-stud type connections. Signal supports shall be designed to also accommodate aluminum signal heads. LEDs shall be GE Lighting Solutions Type GTX or approved equal for circular indications and GT1 for arrows indications. The exterior housing of the vehicular signal heads and visors shall be federal yellow. The interior of the visor shall be black per Item 632. Prior to finishing the Contractor shall submit paint samples to the Engineer and Dublin officials for review and comment. Pole or pedestal mounted vehicular signal heads shall be mounted via half blind couplings. All drip loops shall be used per Standard Drawing TC-85.20 to prevent water entry into the signal head assembly. Payment shall be as per Item 632. Pedestrian signal heads shall display international symbols in lieu of the words "WALK" and "DON'T WALK" and shall be supplemented by a clearance interval countdown timer. The international symbols and the countdown display shall be housed in a single enclosure. The display shall utilize an LED light source that complies with applicable standards promulgated by the ODOT and the Institute of Transportation Engineers. Countdown timer requirements: 1.The countdown feature shall automatically adjust to the programmed intervals of the traffic controller per the requirements of 732.05 2.The countdown timer shall be to the right of the international symbols. 3.Countdown numbers shall be created using two rows of L.E.D.'s and be 9 inches high. 4.Use GE Lighting Solutions TYPE GT1, Model No. PS7-CFF1-26A or approved equal). Final placement of pedestrian signal heads shall be approved by the Engineer. The housing shall be field drilled to fit the hinged mounting bracket and reinforced with parts furnished by the manufacturer. Heads shall be mounted on two-hinged type brackets which are bolted to the pole. Banding will not be permitted. The Contractor shall supply the mounting brackets and all other necessary hardware. The bottom of the pedestrian signal heads shall be mounted 8 feet above pedestrian pathway. The brackets shall be hinged to allow the pedestrian heads to swing away from each other. A clear, shatterproof, lens shall cover the face of the signal head and be of sufficient strength to protect the components from roadside hazards and vandalism. The signal housings shall be black polycarbonate to match the signal supports. Payment shall be as per Item 632. ITEM 632 PEDESTRIAN PUSHBUTTON, AS PER PLAN Pedestrian pushbuttons shall meet the Accessible Pedestrian Signals and Detector requirements set forth by the Ohio Manual of Uniform Traffic control devices, Sections 4E.09 through 4E.13. Pushbuttons shall be Polara EZ Communicator Navigator, 2 wire pushbutton stations. The pushbutton housing shall be yellow. The pedestrian pushbutton system shall provide audible cues for, pushbutton locator tones, walk indication and don't walk indications. The system shall also include custom voice messages for location and walk messages, provide for a vibrating arrow capable of being placed on mute and self-adjusting to ambient street noise. The system shall be furnished with all equipment and cables needed to operate and program the system, including but not limited to a Polara EZ Communicator Navigator Configurator hand-held remote. The configurator shall be delivered to the City of Dublin Engineering Division at 6555 Shier-Rings Road, Dublin, OH 43016 to the attention of Eagan Foster,(614-410-4637). One aluminum sign shall be supplied with each pushbutton. The bottom of the sign shall be mounted just above the top of the pushbutton, using necessary mounting bracket with the Polara Navigator Pedestrian System. Mount the center of the pushbutton 42" above the pedestrian pathway surface. The signs shall be as detailed in these plans. Final location and placement of pushbutton shall be approved by the Engineer. The back of all signs, mounting hardware, and support assemblies mounted on either signal supports or pedestal supports shall be coated to match its respective support. Finish requirements shall be in accordance with that listed for the support or pedestal used for attachment. All equipment needed to render a fully operational pushbutton system shall be considered incidental to this item of work. Payment shall be as per Item 632. ITEM 632 PEDESTAL, 11', TRANSFORMER BASE, AS PER PLAN Pedestals shall be per the details in this plan. All exterior surfaces shall be powder coated in accordance with the finish section requirements of Plan and provide a 5 year warranty. All signal cables shall be run inside the poles. Standard Drawing TC-83.10 is hereby modified to prohibit the use of external conduit risers for signal cabling, or any other use. Design Criteria In addition to the requirements of item 632, pedestal support structures shall be designed and constructed by the supplier to support the loads caused by the signs, signals, and other equipment that the plan requires the Contractor to install. The use of standard ODOT design designations and any details provided in this plan, are intended to promote uniformity of design and are not warranted to be structurally adequate. The contractor shall verify the anchor bold circle, anchor bolt diameter, and orientation pattern with the signal support manufacturer. The manufacturer shall be responsible for verifying the pole design, and shall prepare shop drawings and structural design calculations stamped by an Ohio Professional Engineer. The shop drawings and calculations shall be submitted to the City of Dublin for approval prior to fabrication. Payment shall be as per Item 632. ITEM 632 PEDESTAL FOUNDATION, AS PER PLAN ITEM 632 SIGNAL SUPPORT FOUNDATION, AS PER PLAN The formed top of the anchor base pole foundation shall be oriented parallel to the sidewalk or back-of-curb or edge-of-pavement as shown on the signal plans. When installed in the pedestrian pathway area, the top of the foundation shall be held down below the any adjacent sidewalk as detailed within. A minimum of three conduit ells, used or unused, shall be installed in each signal support foundation. A minimum of two conduit ells, used or unused, shall be installed in each pedestal foundation. Contractor shall vacuum excavate proposed foundation locations prior to installation. Pedestal foundations shall be 2 ft. x 4 ft. as detailed on the City of Columbus Standard Construction Drawing 4163. The bolt circle shall be adjusted to accommodate the proposed pedestals. All rock excavation required to provide foundation depth as specified as in work. Payment shall be as per Item 632. ITEM 632 REMOVAL OF TRAFFIC SIGNAL INSTALLATION, AS PER PLAN Contractor as detailed within. Alternate methods of traffic control shall be approved by the Engineer and in place and operating prior to the deactivation and removal of any existing equipment. Reference is made to the requirements of Item 614. Law enforcement officers shall be hired by the Contractor to Control traffic during any period of time that the traffic signal is not cycling. Traffic signals are not to be removed until replacement fiber optic interconnect connectivity is installed and active. All removed items shall remain the property of the City of Dublin with the exception of pull boxes, foundations, signal cable, mast arms and conduit. The Contractor shall properly dispose of those items only and deliver the other removed items to the City. The Contractor shall contact the City of Dublin 24 hours, not including Saturday and Sunday, in advance to schedule delivery. Signal support foundation shall be entirely removed. Removed pull boxes, conduit, foundation, signal cable and mast arms shall be disposed of by the Contractor in accordance with Item 632. All existing unused signal cable shall be removed from underground conduits. Payment shall be lump sum per intersection as per item 632. In addition to the requirements of Item 633 and 733, the controller and cabinet shall provide the following features: 1.The signal controller, conflict monitors, terminal facilities, and load switches shall be from the same supplier. All load switches and interface relays shall be furnished with input/output side LEDs. The system operation. 2. 3.The controller cabinet type shall be a P-58UPS (Siemens/Eagle Size P-UPS cabinet Catalog Number ELS1014) double door controller and battery backup enclosure type cabinet or approved equal. The controller door shall be furnished with hinges along the left hand side of door. The battery backup door shall be furnished with hinges along the right hand side of door. The cabinet shall provide a single enclosure to house the controller (with all accessories) and the complete battery backup system with each compartment accessible by a separate door. 4.The cabinet exterior shall be powder coated black to match the signal supports. Polyester paint finished to a gloss of 35% (at 60 degrees) should be used. The interior of the cabinet shall be powder coated gloss white. Paint chip samples shall be submitted to the Engineer for review and approval along with shop drawings for all components prior to ordering materials. 5.The cabinet shall come equipped with a cabinet detector rack (CDR) and enough four channel detector cards to operate the signal with 6.A second ventilation fan shall also be installed (110 cfm). This secondary fan shall be manually activated by a toggle switch located on the maintenance panel. 7.The cabinet power surge suppressor/line filter shall be a plug-in style for easy replacement, and shall be an EDCO Model SHA1250 with SHA1250 base, or approved equal. 8.An auxiliary generator connection enclosure shall be mounted on the outside of the upper section of the cabinet on the same side as the cabinet circuit breakers. The drawings for the required enclosure, components and wiring are included in this plan. The enclosure shall be painted to the same specifications as the cabinet. 9.Surge suppressors shall be provided at the field terminals for all inductive loops. These surge suppressors shall be an EDCO Model SRA 16C-1, or approved equal. 10.The controller cabinet shall be keyed to the state master. 11.Provide a slide out laptop shelf. 12.Printed board type back panels of the controller cabinet will not be acceptable. Soldered connections will be permitted for wiring on the back side of the back panel. All controller memories shall be involatile and shall not require batteries or other source of energy to retain the data while power is removed from the controller. 13.The design of the conflict monitor shall be microprocessor architecture and liquid crystal displays. The monitor shall indicate the exact load switch channel in which the failure occurred. The conflict monitor shall have min. 12 channels and an event logging memory. A minimum of nine (9) events shall be logged. Examples of events include: power outages, conflicts, controller voltage monitor, etc. Events shall be displayed on the conflict monitor's liquid crystal display when interrogated. 14.Cabinet serial communication link a.An RS-232 serial communications link shall be provided in the cabinet between the controller, EDI conflict monitor, and all Canoga 800 and/or 900 series vehicle detector devices to allow remote central office connection of these devices. b.The central office user interface shall be part of the software used for communicating with the controller. The interface shall launch the software developed by the device manufacturer and provide all functions of that software from the central office. c.All hardware required to make this connection shall be supplied with the cabinet and be fully functional. 15.See Item 633 Uninterruptible Power Supply (UPS), 1000 Watt, As Per Plan for additional cabinet requirements. 16.Cabinet shall include wiring from uninterruptible power supply to signal cabinet to provide alarms for on battery, two hour timer, low battery and off battery in signal cabinet. 17.Auxiliary power shall charge batteries. 18.Provide a 20 Amp circuit breaker ahead of the street lighting/street name sign circuit contactor pole. 19.Provide an Arc Flash Hazard Warning sign on the outside front door of the enclosure in accordance with the National Electrical Code paragraph 110.16. 20.Provide an available fault current sign on the outside of the front door of the power service disconnect switch in accordance with the National Electrical Code paragraph 110.24. 21.Contractor must coordinate with the City of Dublin staff to program controller settings and coordination timings. All equipment, material, software and labor needed to render a fully functioning vehicle queue detection system shall be considered incidental Payment for item 633, Controller Unit, Type TS2/A2, with Cabinet, Type TS1, As Per Plan, will be at the contract bid price per each, complete and in place including all connections tested and accepted. The existing traffic signal installations at the intersection of: Bridge Street and Shawan Falls Drive/Corbin Mills Drive shall be removed by the ITEM 632 VEHICULAR SIGNAL HEAD, (LED), (BY TYPE AND SIZE), 1-WAY, POLYCARBONATE, AS PER PLAN AS PER PLAN ITEM 632 PEDESTRIAN SIGNAL HEAD (LED), TYPE D2, COUNTDOWN, ITEM 632 PEDESTAL, MISC.: 19', TRANSFORMER BASE, AS PER PLAN WITH CABINET, TYPE TS1, AS PER PLAN ITEM 633, CONTROLLER ITEM, MISC.: CONTROLLER UNIT, TYPE TS2/A2, Item 632 Combination Signal Support, Type TC-81.22 (BY SIZE), As Per ODOT TC-21.21/COC 4163 shall be considered incidental to this item of controller and cabinet supplied shall be capable of complete TACTICS The controller supplied shall be Yunex M60 with Ethernet communications port and USB data port for loading controller timing YAML files. The cabinets shall be wired for the proposed and future phasing shown on the plans and shall be capable of using all phases of the controller with the addition of loop detectors and field wiring. software for up to sixteen detectors. Detectors shall be Eberle Oracle 4EC or approved equal. AS PER PLAN ITEM 632 POWER METER CABINET, BASE MOUNT, WITH FOUNDATION, specified, complete in place. wiring in the power meter cabinet, necessary to complete the work materials, equipment, labor and incidentals, including conduit ells and meter cabinets furnished and installed and shall include furnishing all The work as described will be measured as the number of power signal controller cabinet. The exterior of the cabinet shall be coated to match the main traffic paragraph 110.24. door of the cabinet in accordance with the National Electrical Code Provide an Available Fault Current sign on the outside of the front National Electrical Code paragraph 110.16. Provide an Arc Flash Hazard Warning sign in accordance with the other requirements of the CMS 625 and 725. bar. Ground rods shall be installed to be 10 ohms or less and all meter socket enclosure shall also be connected to the ground bus the cabinet foundation, directly grounding it to the cabinet. The power which shall be mounted on the cabinet back plate within one foot of within the load center shall then be bonded to the ground bus bar, neutral bus bar within the load center enclosure. The neutral bus bar a ground rod. The grounding wire lug shall be connected to the A #4 wire lug shall be provided for attaching a grounding wire from installation shall be incidental to the cost of this item. conduit and four (4) anchor bolts and required conduit ells and their conduit shall extend 2-inches above the top of the foundation. The to four inches above the top of the foundation. One 3/4-inch load (signal controller) power conduits, typically 2", shall extend two meter cabinet foundation detail as shown in the plans. Service and The concrete foundation shall be installed according to the power service supplier shall lock the utility section lift-off service cover. remove the locks and the City will place their locks. The power accepted by the City of Dublin, at which point the Contractor shall and the customer section lift-off service cover with padlocks until The contractor shall lock the meter cabinet's hinged meter section described herein. load center panel, concrete foundation, grounding and incidentals as This item shall include the power meter cabinet, power meter socket, commercial pedestal, Catalog No. CP3A51C1VIAOSP3-City of Columbus. The power meter cabinet supplied shall be a Milbank Slimline series to ITEM 633, CONTROLLER ITEM, MISC.: CONTROLLER UNIT, TYPE TS2/A2, WITH CABINET, TYPE TS1, AS PER PLAN. JZM 66 4/7/22 58074 EMW JZM EMW NONEBRIDGE REPLACEMENTSHAWAN FALLS DRIVE55 55 & W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ NOTES TRAFFIC SIGNAL ITEM 633 EMERGENCY VEHICLE PREEMPTION, AS PER PLAN The Contractor shall furnish and install a fully functioning Opticom GPS based priority control system manufactured by Global Traffic Technologies (GTT) at the intersections listed below. The Opticom System shall be compatible with the existing emergency vehicle preemption system currently used within the City of Dublin and compatible with the proposed traffic signal controllers. - One confirmation light shall be furnished and installed on the signal support with the antenna component of the system. Opticom cable shall be continuous, with no splices between the controller cabinet and the confirmation lights. Payment for the Opticom cable shall be considered part of this item. Payment for this item of work shall be at the contract bid price for ITEM 633 Emergency Vehicle Preemption, As Per Plan and shall include furnishing, installing, tuning, testing and acceptance of the Opticom system. A "System" shall be considered all of the equipment needed to render a fully functional emergency vehicle preemption system at one intersection. ITEM 633 UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 WATT, AS PER PLAN In addition to the requirements of CMS 633 and 733, the UPS cabinet shall include a generator power panel and inlet as detailed within. The backup unit shall be a system based on Myers Power Products Model MP2000E or approved equal. The battery backup equipment with batteries shall be complete, mounted and contained within the battery compartment of the P-UPS controller cabinet. The controller and battery back-up cabinet shall appear as one cabinet from the outside with two internal compartments accessed by separate doors (P58UPS). The UPS output notifications for on battery, battery 2 hour timer, off battery and low battery shall be wired into the traffic signal cabinet back panel to provide special status alarms for each output into the signal controller. This item shall include a green led status indicator lamp to allow maintenance personnel and law enforcement to quickly assess whether a traffic signal cabinet is being powered by an uninterruptible power supply (UPS). The LED housing shall be NEMA 4X or IP 66 rated for outdoor use and be tamper/shatter resistant. It shall be domed green lens, approximately 1” diameter with LED that is visible from 100 ft. minimum. The enclosure and LED lamp unit should be placed on the side of the cabinet most visible to traffic and sealed from water intrusion. It should be wired using minimum 20 AWG stranded, insulated hookup wire to the status relay outputs of the UPS. The wires shall be terminated by lugs at the display end and permanently labeled "backup power status display," with wire polarity indicated. The green LED shall only illuminate to indicate the cabinet is operating under UPS backup power (the "backup" operating condition). This item also includes programming the UPS status relay outputs to produce the lamp status displays. These status displays will be solid 100% duty cycle (not flashing) displays. The operating voltage of the LED lamp shall be 120V AC unless otherwise indicated. The cabinet's exterior finish shall match the color of the main traffic signal controller cabinet. All connections, wiring, attachment hardware and miscellaneous materials for both attaching the cabinets and for full operation of the UPS system shall be included in the unit price bid for this item. Payment shall be per item 633 and shall be made at the unit price bid per each, complete, in place, tested and accepted. ITEM 633, CABINET FOUNDATION, AS PER PLAN The controller cabinet foundations shall be sized for the P-58UPS (Siemens/Eagle size P-UPS cabinet Catalog Number ELS1014) double door cabinet. The size of the foundation shall be verified with the City prior to installation of the foundation. The anchor bolts shall be considered incidental to the cost paid for this item. The cost of coordination with the City shall also be incidental to this item of work. Payment shall be per Item 633. 36" GROUND LINE ELEVATION SIDE VIEW CABINET FOUNDATION 4" CONCRETE ITEM 633 CABINET FOUNDATION, AS PER PLAN NOT TO SCALE ITEM 633 CONTROLLER WORK PAD, AS PER PLN TS2 CABINET TYPE P UPS DOOR HINGE PLAN VIEW 36" 36" 69"36" CONCRETE PAD DOOR HINGEBridge Street and Shawan Falls Drive/Corbin Mills Drive ITEM 816 - VIDEO DETECTION SYSTEM, AS PER PLAN accepted. complete video vehicle detection system, installed, tested, and bid, including all labor, materials and appurtenances for each Payment for all of the above will be made at the contract unit price FOster, EFOSTER@DUBLIN.OH.US. information shall be provided to the City Traffic Engineer, Eagan shall provide an ITERIS back up file for each intersection. Said set of drawings for the video detection zones per intersection and needed by the contractor. THe contractor shall provide an as-built vehicle detection needs are met but may be expanded or modified as Vehicle detection zones are shown in the plans to ensure that all - 1 each: VANTAGE EDGE2 four (4) camera input processor. (complete unit). - 1 each: VANTAGE VECTOR HYBRID VIDEO DETECTION CAMERA, 120VAC to the cost of this video detection system. provided per project and the cost of the devices shall be incidental FOster, Traffic Engineer, 614-410-4637. These devices shall be plans, the contractor shall also furnish the following devices to Eagan In addition to the materials that are mounted above or shown in the sensor to the controller cabinet (no splices). detection and power cable shall be run continuously from the image shall be factory finished in a light grey color. The composite video mounting assembly and the image sensor housing including the visor the existing internally illuminated street name sign. The image sensor riser length shall allow a camera mounting height of 4 inches above mounting assembly. Steel strap banding is not permitted. ASTRO BRAC 2 foot ASTRO BRAC vertical support with stainless steel cable band The image sensor units shall be mounted on the mast arm using a parts of the video detection system. cabinet devices. Vendor shall provide a five (5) year warranty on all be positioned so they are accessible and do not interfere with other doors can be fully opened for servicing. Shelf mounted devices shall be mounted so all cable connections are accessible and all device (cameras) shall be housed in the controller cabinet. All devices shall All video detection equipment except the image sensor units - 1 each: VANTAGE VECTOR module. - 1 each: video security monitor, 9" LED flatscreen. SYSTEM. - 1 each: surge protected power panel for ITERIS VIDEO DETECTION with 600 volt insulation, including connectors. - 200 lin. ft. per camera: video composite detection & power cable - 1 each: power supply TS1 rack mounted 1.5 AMP VANTAGE VIDEO. - includes print markup and tech support. - 1 per 4 cameras: VANTAGE EDGE2 four (4) camera input processor - 4 each: VANTAGE CAMERA power connector cable pigtail 18". risers with a stainless steel cable band attachment. DETECTION CAMERA, 120VAC complete with 2 foot ASTRO BRAC vertical - 4 each: VANTAGE NEXT with VANTAGE VECTOR HYBRID VIDEO the following component items at a minimum: The video detection system at each project intersection shall include plans. zones shall be established for each intersection leg as detailed in the 120VAC, 60 Hz incoming controller cabinet power line. Video detection supply). The proposed system shall be designed to operate on a component devices (camera input processor and shelf mounted power all mounting hardware, all cabling/harnesses, and controller cabinet appropriate number of hybrid image sensor units, as specified below, DETECTION SYSTEM. The video detection system shall include the complete ITERIS VANTAGE NEXT with VANTAGE VECTOR HYBRID VIDEO Under this item of work the contractor shall furnish and install a ITEM 632 - SIGNALIZATION, MISC.: RELOCATION OF ITS ITEMS (614)410-4637 to coordinate. cabinet to the new traffic signal cabinet. Contact Eagan Foster, existing Ethernet network switch from the existing traffic signal - Coordinate with the City of Dublin IT Department to relocate the device with MH Corbin Company, Bill Corbin, (614)873-5216. - Coordinate the relocation of the ConnectITS device and the RSU the new traffic signal cabinet. - Relocate ConnectITS device from existing traffic signal cabinet to loop. from the mounting plate of the mast arm with a three foot (3') drip cable into the mast arm to reach the RSU mounted five feet (5') bottom of the traffic signal enclosure). Pull sufficient CAT6 Ethernet traffic signal cabinet (coil ten feet (10') of extra cable on the intersection. Install exterior grade CAT6 Ethernet cable from the new from the mast arm support on the southwest corner of the pole on the southwest corner to the new traffic signal mast arm - Relocate Road Side Unit (RSU) from existing traffic signal strain JZM 66 4/7/22 58074 EMW JZM EMW NONEBRIDGE REPLACEMENTSHAWAN FALLS DRIVE56 56 & W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ NOTES TRAFFIC SIGNAL JZM 66 4/7/22 58074 EMW JZM EMW NONEBRIDGE REPLACEMENTSHAWAN FALLS DRIVE57 57 & W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ NOTES TRAFFIC SIGNAL JZM 66 4/7/22 58074 EMW JZM EMW NONEBRIDGE REPLACEMENTSHAWAN FALLS DRIVE& W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ NOTES TRAFFIC SIGNAL 58 58 100PI Sta. 100+76.19101201 202 203EX. 24" SANI TARY, CI TY OF DUBLI N, QL "B"12"1+009.0'S D 5 1" = 20' BPT 66 4/7/22 58074 EMW BPT EMW 59 59 R G Y R Y G Y G & W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ SIGNAL PLAN R Y G Y G BRIDGE REPLACEMENTSHAWAN FALLS DRIVER Y G Y/G BIMODAL - YELLOW ARROW / GREEN ARROW S D Shawan Falls Dr Corbins Mill Dr W Bridge St VEHICLES TURNING FOR WATCH TURNING VEHICLES TO YIELD Shawan Falls Dr Corbins Mill Dr STEADY FLASHING TIMER DON'T START Finish Crossing If Started START CROSSING Watch For TIME REMAINING DON'T CROSS To Finish Crossing PUSH OR WAVE AT Vehicles BRIDGE ST BUTTON TO CROSS STEADY FLASHING TIMER DON'T START Finish Crossing If Started START CROSSING Watch For TIME REMAINING DON'T CROSS To Finish Crossing PUSH OR WAVE AT Vehicles BRIDGE ST BUTTON TO CROSS STEADY FLASHING TIMER DON'T START Finish Crossing If Started START CROSSING Watch For TIME REMAINING DON'T CROSS To Finish Crossing PUSH OR WAVE AT Vehicles SHAWAN FALLS DR BUTTON TO CROSS STEADY FLASHING TIMER DON'T START Finish Crossing If Started START CROSSING Watch For TIME REMAINING DON'T CROSS To Finish Crossing PUSH OR WAVE AT Vehicles SHAWAN FALLS DR BUTTON TO CROSS STEADY FLASHING TIMER DON'T START Finish Crossing If Started START CROSSING Watch For TIME REMAINING DON'T CROSS To Finish Crossing PUSH OR WAVE AT Vehicles CORBINS MILL DR BUTTON TO CROSS SIGNS SIGNAL HEADS TYPE D2) (LED, COUNTDOWN, PEDESTRIAN HEADS BLACK HOUSING 2 834 5 7 1 6 28' IN TRENCH 19' IN TRENCH WITH ARROWS 3 UNIT HEAD, 12" TRAFFIC SIGNAL, PROP EXIST 3 UNIT HEAD, 12" TRAFFIC SIGNAL, 4 OR 5 UNIT HEAD, 12" TRAFFIC SIGNAL, PEDESTRIAN SIGNAL PEDESTRIAN PUSH BUTTON TRAFFIC PULL BOX SIGNAL SUPPORT POLE DETECTION ZONE LEGEND AND WORK PAD (TS-2) CONTROLLER CABINET DETECTION UNIT DILEMMA ZONE RADAR DETECTION UNIT STOP BAR RADAR PEDESTAL SUPPORT PTZ CAMERA 20' IN TRENCH 1 2 3 4 56 7 8 6PA6PB 8PA 8PB 2PA 2PB R9-3-24 E F E F G H G H STA. 201+19.3, 73.0' RT 22' IN TRENCH 7' IN TRENCH 7' IN TRENCH Z5 Z8A Z8B Z8C Z1 Z4A Z4B JACKED OR DRILLED 125' JACKED OR DRILLED 103' Z6A Z6B Z2A Z2B B CA D A B C D W BRIDGE STSHAWAN FALLS DRCORBI NS MI LL DRW BRIDGE ST 16"W (DU0008 009) PROPOSED 8"W I J 18"X18" CMR-188.03 ABOVE PED HEAD POLE MOUNTED I K L K L J 11 1210 9 9 1112 10 SPECIAL-R10-15-30 O P O P 1 EACH 120" X 48" INTERNALLY ILLUMINATED WHITE BACKGROUND BLACK LETTERING ON D3-1 2 EACH 108" X 24" INTERNALLY ILLUMINATED WHITE BACKGROUND BLACK LETTERING ON D3-1 1 EACH 120" X 48" INTERNALLY ILLUMINATED WHITE BACKGROUND BLACK LETTERING ON D3-1 RETRO-REFLECTIVE STRIPE ON THE BACKPLATE CUTAWAY VISOR YELLOW HOUSING WITH NO WITH BLACK LOUVERED ALUMINUM BACKPLATES SHALL BE YELLOW POLYCARBONATE 12" LED ALL VEHICULAR SIGNAL HEADS HOUSINGS SP-3 COMBINATION SIGNAL SUPPORT P-1 PEDESTRIAN PEDESTAL, 19' SP-1 COMBINATION SIGNAL SUPPORT SP-4 COMBINATION SIGNAL SUPPORT P-2 PEDESTRIAN PEDESTAL, 11' (1)-2" CONDUIT W/(1)-5/C (1)-2" CONDUIT W/(1)-LIC M N MN STA. 201+09.7, 67.3' RT ADD (1)-2" CONDUIT RISER EX. UTILITY POLE POWER SOURCE (1)-3" RMC CONDUIT W/ POWER (1)-3" RMC CONDUIT W/ POWER 5' IN TRENCH STA. 201+13.9, 68.8' RT PULLBOX 5, 18" SP-2 COMBINATION SIGNAL SUPPORT (1)-2" CONDUIT W/(1)-7/C, (1)-5/C (1)-2" CONDUIT W/(1)-LIC (1)-2" CONDUIT W/(2)-7/C, (1)-5/C, (1)-V/C (1)-2" CONDUIT W/(1)-DIST. (1)-2" CONDUIT W/(1)-LIC (1)-2" CONDUIT W/(1)-9/C, (1)-5/C, (1)-V/C (1)-2" CONDUIT W/(1)-DIST. (1)-2" CONDUIT W/(1)-LIC (1)-6" CONDUIT SLEEVE W/(1)-3" CONDUIT W/(2)-7/C, (1)-5/C, (1)-V/C (1)-6" CONDUIT SLEEVE W/(1)-3" CONDUIT W/(1)-DIST. (1)-6" CONDUIT SLEEVE W/(1)-3" CONDUIT W/(1)-LIC (1)-3" CONDUIT W/(2)-7/C, (1)-5/C, (1)-V/C (1)-2" CONDUIT W/(1)-DIST. (1)-2" CONDUIT W/(1)-LIC STA. 202+20.3, 43.1' LT W/(1)-AUXILIARY VEHICULAR SIGNAL HEAD W/(1)-PEDESTRIAN PUSHBUTTON W/(1)-PEDESTRIAN SIGNAL HEAD STA. 202+32.9, 59.6' RT W/(1)-PEDESTRIAN PUSHBUTTON W/(1)-PEDESTRIAN SIGNAL HEAD STA. 201+30.2, 73.1' RT PULLBOX 2, 32" ROUND STA. 202+33.1, 66.1' RT PULLBOX 4, 27" ROUND STA. 201+96.3, 53.5' LT PULLBOX 3, 27" ROUND STA. 199+87.8, 48.1' LT PULLBOX 1, 27" ROUND CABINETS SHALL BE BLACK. MOUNTED METERED POWER CABINETS, AND DISCONNECT BLACK. TRAFFIC SIGNAL CONTROLLER CABINETS, GROUND- SIGN BRACKETS, AND STREET NAME SIGN HOUSINGS SHALL BE 1. MAST ARMS AND THEIR SUPPORTS, PEDESTRIAN POLES, NOTE: JACKED OR DRILLED 109' SPECIAL-R10-3E-9 PEDESTRIAN SIGNS RQ S T U V Q R S T U V 11' IN TRENCH (1)-3" RMC CONDUIT W/ POWER 8' IN TRENCH STA. 201+07.7, 73.8' RT (1)-6" CONDUIT SLEEVE W/(1)-3" CONDUIT W/(5)-5/C, (3)-V/C (1)-6" CONDUIT SLEEVE W/(1)-3" CONDUIT W/(4)-7/C, (2)-9/C (1)-6" CONDUIT SLEEVE W/(1)-3" CONDUIT W/(3)-DIST. (1)-6" CONDUIT SLEEVE W/(1)-3" CONDUIT W/(5)-LIC (1)-3" CONDUIT W/(1)-9/C, (1)-7/C, (1)-5/C, (1)-V/C (1)-2" CONDUIT W/(1)-DIST. (1)-2" CONDUIT W/(1)-LIC (1)-6" CONDUIT SLEEVE W/(1)-3" CONDUIT W/(3)-5/C, (2)-V/C (1)-6" CONDUIT SLEEVE W/(1)-3" CONDUIT W/(3)-7/C, (1)-9/C (1)-6" CONDUIT SLEEVE W/(1)-3" CONDUIT W/(2)-DIST. (1)-6" CONDUIT SLEEVE W/(1)-3" CONDUIT W/(3)-LIC STA. 201+32.9, 66.9' RT W/(1)-LUMINAIRE & BRACKET ARM W/(1)-HYBRID VIDEO DETECTION CAMERA W/(1)-AUXILIARY VEHICULAR SIGNAL HEAD W/(1)-PEDESTRIAN PUSHBUTTON W/(1)-PEDESTRIAN SIGNAL HEAD STA. 202+42.0, 49.8' RT W/(1)-LUMINAIRE & BRACKET ARM W/(1)-HYBRID VIDEO DETECTION CAMERA W/(1)-AUXILIARY VEHICULAR SIGNAL HEAD W/(1)-PEDESTRIAN PUSHBUTTON W/(1)-PEDESTRIAN SIGNAL HEAD STA. 201+79.9, 67.3' LT W/(1)-LUMINAIRE & BRACKET ARM W/(1)-HYBRID VIDEO DETECTION CAMERA W/(1)-PEDESTRIAN PUSHBUTTON W/(1)-PEDESTRIAN SIGNAL HEAD STA. 200+97.5, 65.3' LT W/(1)-LUMINAIRE & BRACKET ARM W/(1)-HYBRID VIDEO DETECTION CAMERA W/(1)-AUXILIARY VEHICULAR SIGNAL HEAD W/(1)-PEDESTRIAN PUSHBUTTON W/(1)-PEDESTRIAN SIGNAL HEAD (2) DISCONNECT SWITCHES (1-LIGHTING & 1-SIGNAL) GROUND MOUNTED CONTROLLER W/ UPS & (1)-3" CONDUIT W/(2)-9/C (1)-3" CONDUIT W/(4)-V/C (1)-3" CONDUIT W/(6)-5/C (1)-3" CONDUIT W/(6)-7/C (1)-3" CONDUIT W/(4)-DIST. (1)-3" CONDUIT W/(6)-LIC BASE MOUNT POWER METER CABINET 12' IN TRENCH BPT 66 4/7/22 58074 P:\PR58074\FRA\000000\Design\Signals\Sheets\CD001.dgn Sheet 5/6/2022 5:04:21 PM jkelleyEMW BPT EMW NONEBRIDGE REPLACEMENTSHAWAN FALLS DRIVE60 60 N & W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ DETAILS TRAFFIC SIGNAL PHASING DIAGRAM PERMITTED £ VEHICLE £ PEDESTRIAN £ LEGEND £1 & £6 PED 2P PED 6P £01 £05 £06 £02 £05 £06 £02 £01 (RECALL) £2 & £6 PED 6P PED 2P £1 & £5 £2 & £5 PED 8P£04 £08 £4 & £8 OLA OLA USE EXISTING SIGNAL TIMINGS SIGNAL TIMING CHART VIDEO DETECTION CHART ZONEDETECTIONMOVEMENTPRESENCEPULSE ORPHASEASSOCIATED(SEC.)IN CONTROLLERPROGRAMMEDDELAYPHASEDELAY INHIBITDETECTOR NO.PURPOSE(FT)ZONE LENGTHDETECTION(FT)STOP BARDISTANCE FROMZ1 WB LEFT PRESENCE 1 2 1 D6 CALL/EXTEND PHASE 1 40 0 Z2A EB THRU PULSE 2 8 2 D2 DILEMMA ZONE 450 50-500 Z2B EB THRU PULSE 2 --D2 DILEMMA ZONE 450 50-500 Z4A SB LEFT PRESENCE 4 2 4 D4 CALL/EXTEND PHASE 4 40 0 Z4B SB THRU PRESENCE 4 8 4 D4 CALL/EXTEND PHASE 4 40 0 Z5 EB LEFT PRESENCE 5 2 5 D2 CALL/EXTEND PHASE 5 40 0 Z6A WB THRU PULSE 6 8 6 D6 DILEMMA ZONE 450 50-500 Z6B WB THRU PULSE 6 --D6 DILEMMA ZONE 450 50-500 Z8A NB LEFT PRESENCE 8 2 8 D8 CALL/EXTEND PHASE 8 40 0 Z8B NB THRU PRESENCE 8 --D8 CALL/EXTEND PHASE 8 40 0 Z8C NB RIGHT PRESENCE 8 8 8 D8 CALL/EXTEND PHASE 8 40 0 BPT 66 4/7/22 58074 P:\PR58074\FRA\000000\Design\Signals\Sheets\CD002.dgn Sheet 5/6/2022 5:04:30 PM jkelleyEMW BPT EMW NONEBRIDGE REPLACEMENTSHAWAN FALLS DRIVE& W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ DETAILS TRAFFIC SIGNAL 61 61 INCREASING RIGHT OF | STATIONING LEFT OF | | MAST ARM (INDEX)90°M ASTARM ANGLEORI ENTATI ONANGLES ORIENTATION ORIENTATION ANGLE MAST ARM | MAST ARM (INDEX)90°ANGLES ORIENTATION | MAJOR STREET POLE ORIENTATION MAST ARM TABLE PEDESTAL SUPPORT TABLE SUPPORT NO.STATIONOFFSETELEVATIONFOUNDATIONPEDESTAL HEIGHTINDEX ANGLEORIENTATION FROM INDEX ANGLE HANDHOLEPEDESTRIAN SIGNAL WITH SIGNACTIVATION SYSTEMPEDESTRIAN(CMR-188.03)VEHICLESWATCH FOR TURNING(3-SECTION)AUXILLARY HEADP-1 202+20.3 43.1' LT 856.57 19'0 180 90 90 90 283 P-2 202+32.9 59.6' RT 856.96 11'0 180 0 0 0 - * * SIGNAL HEADS; ONE CENTERED OVER EACH LANE). FUTURE FLASHING YELLOW ARROW SIGNAL HEAD ARRANGEMENT (THREE * NOTE: SUPPORTS SP-1 & SP-4 HAVE BEEN DESIGNED TO SUPPORT A 42" 8'ARM ATTACHMENT HEIGHTPOLE HEIGHTMaximum = 19' Preferred = 17' Minimum = 16.5' Clearance S1 S2 PUSHBUTTON PEDESTRIAN L2 BRACKET ARM HEIGHT12' 27" LIGHT WITH CONFIRMATION PREEMPTION DETECTOR RADIUS ID POLE BASE PLATE RADIUS CORNER RADIUS TO MATCH M WIDTH +1/4" POLE PLATE K 1"TOP VIEW POLE PLATE SKIRT SECTION A-A SECTION ATTACHMENT COVER GUIDE AND THREADED HOLE W/ S.S. BOLT PRE-DRILLED PLATE 1/4" STEEL BE PERMITTED.NOT3. BANDING WILL MOUNTED VIA BLIND HALF COUPLINGS (BHC). 2. VEHICULAR SIGNAL HEADS SHALL BE CLAMSHELL MOUNTED. 1. PEDESTRIAN SIGNAL HEADS SHALL BE NOTES: AA FOUNDATION ID = POLE OD + 1/4" NOT TO SCALE STEEL BASE COVER POLE SIGNAL ELEVATION DETAIL Street NameSIGN NOT TO SCALE ON EACH PLAN SHEET. SIGNS ARE DETAILED D1 L L1 X SUPPORT NO.STATIONOFFSETELEVATION SIGNAL SUPPORT DETAILS ORIENTATION ANGLES FROM MAST ARM Elev.) (Pavt. A Found.) (Top of B DESIGN TYPEDESIGN NO.HEIGHTPOLEARM HEIGHT L L1 L2 D1 S1 S2 X ANGLEMAST ARM ASIGNALPEDESTRIANPUSHBUTTONPEDESTRIANSIGNAL HEADSUPPLEMENTALDETECTIONRADARPOWER SERVICESIGNAL CABINETBRACKET ARMHANDHOLE12" FROM TOPCABLE ENTRANCEFT FT FT FT FT FT FT FT FT DEG DEG DEG DEG DEG DEG DEG DEG DEG DEG SP-1 200+97.5 65.3' LT 858.37 856.84 TC-81.22 14 37.0 22.0 68.0 58.1 42.5 46.5 50.2 19.5 6 0 0 0 185 28 --0 180 - SP-2 201+32.9 66.9' RT 856.93 858.04 TC-81.22 4 34.0 19.0 36.0 30.4 13.4 17.1 21.8 5.6 6 90 270 270 195 11 --0 180 - SP-3 201+79.9 67.3' LT 856.26 855.45 TC-81.22 4 36.0 21.0 35.0 30.5 17.0 19.7 23.7 10.2 6 90 270 270 -16 --0 180 - SP-4 202+42.0 49.8' RT 856.39 856.98 TC-81.22 13 35.0 20.0 54.0 44.7 32.1 36.2 38.4 18.4 6 0 264 264 189 29 --0 180 - BPT 66 4/7/22 58074 P:\PR58074\FRA\000000\Design\Signals\Sheets\CD003.dgn Sheet 5/6/2022 5:04:32 PM jkelleyEMW BPT EMW NONEBRIDGE REPLACEMENTSHAWAN FALLS DRIVE& W BRIDGE ST CORBINS MILL DR SHAWAN FALLS DR/ DETAILS TRAFFIC SIGNAL 62 772 FIELD WIRING HOOK-UP CHART METER BASE PC 5C MB PEDESTRIAN PUSH BUTTON LIC NO. 14 AWG SIGNAL CABLE, 5 CONDUCTOR, 7C NO. 14 AWG SIGNAL CABLE, 7 CONDUCTOR, NO. 6 AWG POWER CABLE, 2 CONDUCTOR, VC VIDEO DETECTION CABLE POWER SOURCE LEGEND 2/C NO. 14 AWG (LEAD-IN CABLE) DS DS MB PCPCPC PEDESTRIAN SIGNALCONTROLLER CABINETVC WIRING DIAGRAM D6 AEP AEP 2 3 10 DISCONNECT SWITCH P6B 5C6PB 7C VCD2 5C P8B 8PB D4 VC 5C P2A 2PA 56 5C P2B 2PB LIC LIC LIC LIC 7C PCPE N10 DS PEN10 PE N10 N4N42 SP N10 PE N41 SP N4 4 SP 3 SP PAD MOUNTED TRANSFORMERTRAFFIC SIGNAL, 5 UNIT HEAD 12" TRAFFIC SIGNAL, 3 UNIT HEAD 12" N4 N10 NO. 4 AWG DISTRIBUTION CABLE NO. 10 AWG POLE & BRACKET CABLE PE PHOTOELECTRIC CELL LUMINAIRE, APP 1 SP SIGNAL SUPPORT POLE NO. __ 7C 1 12 7C 7C7C 4 9C11 7 7C 8 7C 5C P8A 8PA LIC 7C9 5C P6A 6PA LIC VC D8 9C7C SNS ILLUMINATED STREET NAME SIGN SNS N10 SNS N10 SNSN10 N10SNS HEAD SIGNAL INDICATION FIELD TERMINAL FLASH HEAD SIGNAL INDICATION FIELD TERMINAL FLASH 1, 9 R Ø6 RED R 11 R Ø8 RED R Y Ø6 YEL ---Y-->Ø8 YEL G Ø6 GRN --FYA-->Ø1 YEL (WB)--(NB)---G-->Ø8 GRN ---- 2 R Ø6 RED R 3, 4, 10 R Ø4 RED RYØ6 YEL Y Ø4 YEL G Ø6 GRN (SB)G Ø4 GRN (WB LT)<--Y---Ø1 YEL - -- - <--G---Ø1 GRN -- 8 R Ø2 RED R -- Y Ø2 YEL --- G Ø2 GRN -- (EB LT)<--Y---Ø5 YEL PEDESTRIAN MOVEMENTS <--G---Ø5 GRN 2P W Ø2 PED/LS10 G OUT 7, 12 R Ø2 RED R -DW Ø2 PED/LS10 R Y Ø2 YEL 6P W Ø6 PED/LS11 G OUT (EB)G Ø2 GRN -DW Ø6 PED/LS11 R 5 R Ø8 RED R 8P W Ø8 PED/LS12 G OUT Y Ø8 YEL -DW Ø8 PED/LS12 R G Ø8 GRN --- - (NB RT)---Y-->Ø1 YEL --- ---G-->Ø1 GRN OVERLAPS 6 R Ø8 RED R OLA ---Y-->Ø1 YEL OUT Y Ø8 YEL ---G-->Ø1 GRN (NB)G Ø8 GRN OLA = LS 13 LS = LOAD SWITCH 9C NO. 14 AWG SIGNAL CABLE, 9 CONDUCTOR, VIDEO DETECTION UNIT 66 63 63 58074 MDJ 2 4 P:\PR58074\FRA\000000\Design\RW\Sheets\RS001.dgn Design 10/5/2021 2:18:18 PM rileyRIGHT OF WAY ADDITIONAL SUMMARY OF N/A ALL AREAS IN ACRES MDJ ENR ENR 58SHAWAN FALLS BRIDGE REPLACEMENTCITY OF DUBLIN, OHIO56 56 10/5/2021 NET RESIDUE = RECORD AREA - TOTAL PRO - NET TAKE NET TAKE = GROSS TAKE - PRO IN TAKE (c) = CALCULATED AREA * DENOTES RIGHT OF WAY ENCROACHMENT GRANTEE: UNLESS OTHERWISE SHOWN. THE CITY OF DUBLIN ALL RIGHT OF WAY ACQUIRED IN THE NAME OF NOTE: UNLESS NOTED OTHERWISE. MATERIAL OR EQUIPMENT BY THE CONTRACTOR EASEMENTS TO BE USED FOR STORAGE OF UNDER NO CIRCUMSTANCES ARE TEMPORARY BE OF 18 MONTH DURATION. NOTE: ALL TEMPORARY PARCELS TO TOTAL NUMBER OF : 3 OWNERSHIPS 6 PARCELS 0 TOTAL TAKES 3 OWNERSHIPS W/ STRUCTURES INVOLVED DATE COMPLETED: 10/5/2021 REV. BY DATE DESCRIPTION OR = OFFICIAL RECORD IN = INSTRUMENT NUMBER T = TEMPORARY EASEMENT U = UTILITY EASEMENT WD = WARRANTY DEED LEGEND: PARCEL OWNER SHEET OWNERS RECORD AUDITOR'S RECORD TOTAL GROSS P.R.O. IN NET STRUC-NET RESIDUE TYPE REMARKS AS ACQUIRED NO.NO.BOOK PAGE PARCEL AREA P.R.O.TAKE TAKE TAKE TURE LEFT RIGHT FUND INSTRUMENT NUMBER 1-WD OHIOHEALTH CORPORATION, AN OHIO IN 201803260038938 273-000797-00 2.187 0.541 0.090 0.000 0.090 Y 2.097 CITY TAKE 10' OF 6" WIDE TIMBER LANDSCAPE WALL, FLOWER BED NOT-FOR-PROFIT CORPORATION PORTION, (2) 2" CRABAPPLE TREES, (2) BUSHES, SHRUBS, (6) PARKING SPACES, CLEAN OUT 1-U 273-000797-00 0.012 S (1) TAKE BRICK AND LIGHTED "OHIOHEALTH" PRIVATE SIGN, ELEC. BOX, FLOWER BED PORTION, (8) BUSHES SEWER EASEMENT OVERLAP = 3.0 SQ.FT. 1-T 273-000797-00 0.102 S (1) TEMPORARY CONSTRUCTION AND GRADING EASEMENT TAKE FLOWER BED PORTION, TEMP. IMPACT (4) PARKING SPACES TOTAL, (2) 2" CRABAPPLE TREES REMOVE AND RESET PARKING SIGN SEWER EASEMENT OVERLAP = 39.3 SQ.FT. 2-T 220 W BRIDGE ST, LLC, AN OHIO LIMITED IN 201807310102242 273-000785-00 0.450 0.000 0.002 Y TEMPORARY CONSTRUCTION AND GRADING EASEMENT LIABILITY COMPANY 273-000786-00 1.010 0.365 0.031 TAKE (2) TREES TOTAL 1.460 0.365 0.033 REMOVE AND RESET APPROX. 30 FT. CH. LINK FENCE 3-WD BISCAR PROPERTIES, LLC IN 199811170295482 273-002485-00 0.962 0.000 0.014 0.000 0.014 0.948 TAKE (4) BUSHES, PORTION OF FLOWER BED & SHRUB UTILITY EASEMENT (P.B. 61, PG. 94) OVERLAP = 0.014 AC. 3-T 273-002485-00 0.000 0.094 S (1) TEMPORARY CONSTRUCTION AND GRADING EASEMENT TAKE PRIVATE SIGN, LARGE ROCK, FLOWER BED, (10) BUSHES 4 CITY OF DUBLIN, AN OHIO MUNICIPAL IN 199706030013594 273-000787-00 2.197 0.000 0.000 NO ADDITIONAL R/W REQUIRED CORPORATION 5 UNITED STATES POSTAL SERVICE OR 4875 J01 273-002474-00 2.585 0.000 0.000 NO ADDITIONAL R/W REQUIRED 6 OCLC ONLINE COMPUTER LIBRARY CENTER OR 16551 F20 273-000788-00 40.053 0.000 0.000 NO ADDITIONAL R/W REQUIRED 66 64 64 100 PI Sta. 100+76.19101 102 PC St a. 102+50.84PT Sta. 102+85.74103 104 ¬ = 3°58'37"10200 20120212"12"2IN2IN2IN24IN16IN8IN12IN8IN32IN18IN2IN4IN3IN18IN3IN2IN2IN10IN12IN2IN2IN2IN2IN10IN6IN18IN8IN-IMG2874IN4IN4IN4IN201 202 203 204200 +02.90PI Sta.201+30.64 PI Sta.201+96.48PI St a. 1" = 20' ENR 58074 P:\PR58074\FRA\000000\Design\RW\Sheets\RD001.dgn Sheet 10/5/2021 2:18:20 PM rileyMDJ ENR MDJSHAWAN FALLS BRIDGE REPLACEMENTCITY OF DUBLIN, OHIO57 3 4 STA. 204+00 TO BEGIN ACQUISITION PLAN RIGHT OF WAY 5857 VMS NO. 2542 CITY OF DUBLIN FRANKLIN COUNTY SHAWAN FALLS DRIVE BRIDGE REPLACEMENT 10/5/2021*** 2 COMMERCIAL 1 COMMERCIAL 3 COMMERCIAL INST. 201807310102242 A.P.N. 273-000786-00 DUBLIN, OH 43017 220 W. BRIDGE ST. AN OHIO LIMITED LIABILITY COMPANY 220 W BRIDGE ST, LLC, INST. 201803260038938 A.P.N. 273-000797-00 DUBLIN, OH 43017 250 W. BRIDGE ST. OHIO NOT-FOR-PROFIT CORPORATION OHIOHEALTH CORPORATION, AN INST. 199811170295482 A.P.N. 273-002485-00 DUBLIN, OH 43017 650 SHAWAN FALLS DR. BISCAR PROPERTIES, LLC 4 INST. 199706030013594 A.P.N. 273-000787-00 DUBLIN, OH 43017 5200 EMERALD PARKWAY AN OHIO MUNICIPAL CORPORATION CITY OF DUBLIN, P.I. Sta. 102+68.33 R = 200.00' T = 17.50' L = 34.91' E = 0.76' C = 34.86' ¬ 1-WD 1-T \ CONST. SHAWAN FALLS CURVE DATA - 3 4 3-WD 3-T A.P.N. 273-000785-00 PARK 1-U73.33 LT 201+44.76 63.33 LT 201+42.82 56.33 LT 201+41.46 73.33 LT 201+94.59 63.33 LT 201+94.70 56.33 LT 201+93.05 35.00 LT 203+83.90 1-WD Bearing Distance A B C D E F G H I J 12.67' (1-WD) K 15.00' (1-WD) L 51.58' (1-WD) M 49.78' (1-WD) N 64.01' (1-WD) O 89.67' (1-WD) P 5.00' (1-WD) Q 190.05' (1-WD) R 65.59' (1-WD) S T 7.13' (1-U) U 118.43' (1-T) A 1 B 2 C D E F 3G H I 4 J L N O P Q R U T M S LINE TABLE 51.87' (1-U) 50.03' (1-U) 10.18' (1-T) 49.83' (1-T) 46.00' (1-T) 39.32' (1-T) 24.50' (1-T) 49.50' (3-WD) 49.50' (3-WD) 71.02 LT 202+27.88 53.94 LT 202+33.09 SAVE SAVE 35.00 LT 202+94.23 12"12" K STA. 201+10.46 BEGIN ACQUISITION Station 1 2 3 4 STATION & OFFSET TABLE Offset 201+33.51 30.00' 201+38.60 41.60' 30.00'203+83.90 201+96.48 30.11' 50.40' (3-T) 59.50 LT 203+83.90 BRICK 2 STORY 23.0' ASPHALT *** +18.60 | DR. STA. 100+88.60 BEGIN PROJECT 5 5 STA. 101+44.91 \ CONST. STA. 201+19.11 | EX. R/W = STA. 103+65.18 END PROJECT 2-T 33.22' RT 202+49.18 29.89' RT 202+49.18 33.76' RT 201+13.35 29.87' RT 201+93.76 V W X Y V W X Y 86.50' (2-T) 50.19' (2-T) Z Z 13.10' (2-T) 3.34' (2-T) 140.61' (2-T) SOUTH FORK INDIAN RUN SHAWAN FALLS DRIVE (60' R/W) 59.50 LT 202+65.47 46.54' RT 201+10.46 ** * ** *(WIDTH VARIES)(AKA W. BRIDGE ST.) US ROUTE 33 / SR 161EX. WATER EX. 24" SAN. CONST. LIMITS SHAWAN FALLS DR. | EX. R/W (APROXIMATE LOCATION) DB 2809 PAGE 303 20' WIDE SEWER EASEMENT 58MATCH LINE STA. 204+00 (SEE SHEET )WATER EX. 8" EX. 3" GAS SAVE LIMITS CONST.DND PROP. 8" WATER SAVE BED FLOWER TAKE**23.0' ASPHALT+50.64 | DR.SHAWAN FALLS DR. \ CONST. BED PORTION TAKE FLOWER DEDICATED IN P.B. 61, PG. 94) SHAWAN FALLS DRIVE SHAWAN FALLS DR. | EX. R/W P.B. 61, PG. 94 UTILITY EASEMENT 10' WIDE PUBLIC & PRIVATE BRIDGE STREET \ CONST. W DND SHAWAN FALLS DR. \ CONST. FLOWER BED (PORTION) TAKE ELEC. BOX, ******** "OHIOHEALTH" PRIVATE SIGN TAKE BRICK & LIGHTED REMOVE & RESET SIGN CHAIN LINK FENCE APRROX. 30' REMOVE AND RESET **** **** CLEAN OUT ** PARCEL 1-WD = TAKE 10' OF 6" WIDE TIMBER LANDSCAPE WALL, * PARCEL 1-WD = PERMANENTLY TAKE 6 PARKING SPACES TOTAL SAVESAVE **** 1-T = TEMPORARILY IMPACT 4 PARKING SPACES TOTAL DATE COMPLETED: 10/5/2021 REV. BY DATE DESCRIPTION US ROUTE 33/SR 161 | EX. R/W AA AA 20.71' (REF)D.B. 2686, PG. 20STATE OF OHIOEASEMENT FOR HIGHWAY PURPOSES PARCEL 308 (FRA-270-7.47N)D.B. 2686, PG. 20STATE OF OHIOEASEMENT FOR HIGHWAY PURPOSES PARCEL 308 (FRA-270-7.47N)3/4" PIPE FOUND CAPPED "S-6096" 5/8" PIN FND. BASIS FOR BEARINGS: HEAD AT 30.11 FEET LEFT OF STATION 201+96.48. OF STATION 203+83.90 AND A MAG NAIL FOUND WITH BROKEN TOP DRIVE BETWEEN A 3/4-INCH IRON PIPE FOUND AT 30.00 FEET LEFT ON THE WESTERLY EXISTING RIGHT-OF-WAY LINE OF SHAWAN FALLS A BEARING OF SOUTH 00 DEGREES 59 MINUTES 31 SECONDS EAST OHIO STATE PLANE, SOUTH ZONE, NAD83 (2011) AND DERIVING ALL BEARINGS SHOWN ARE FOR PROJECT USE ONLY. ORD. NO. 81-76) (SEE VILLAGE OF DUBLIN 0.376 AC. TRACT D.B.3508, PG. 212 VILLAGE OF DUBLIN 66 65 65 PC Sta. 104+46.60105 106PT Sta. 106+51.3910 7 10 8PC Sta. 10+81.4211 12SIZE 8 INCHSIZE 16 INCHSIZE 16 INCHSIZE 10 INCHSIZE 8 INCH8IN-IMG2871" = 20' ENR date 58074 P:\PR58074\FRA\000000\Design\RW\Sheets\RD002.dgn Sheet 10/5/2021 2:18:22 PM rileyMDJ ENR MDJSHAWAN FALLS BRIDGE REPLACEMENTCITY OF DUBLIN, OHIO4 4 END ACQUISITION TO STA. 204+00 PLAN RIGHT OF WAY 5858 VMS NO. 2542 CITY OF DUBLIN FRANKLIN COUNTY SHAWAN FALLS DRIVE BRIDGE REPLACEMENT 23.0' ASPHALT+23.40 | DR.206+43.71PT Sta.204 PC Sta. 204+33.40205 20620 7 20 8 POT Sta. 208+04.713 COMMERCIAL INST. 199811170295482 A.P.N. 273-002485-00 DUBLIN, OH 43017 650 SHAWAN FALLS DR. BISCAR PROPERTIES, LLC 4 INST. 199706030013594 A.P.N. 273-000787-00 DUBLIN, OH 43017 5200 EMERALD PARKWAY AN OHIO MUNICIPAL CORPORATION CITY OF DUBLIN, P.I. Sta. 105+51.77 R = 365.00' T = 105.17' L = 204.79' E = 14.85' C = 202.11' ¬ E = 15.24' P.I. Sta. 205+41.40 ¬ R = 375.00' T = 108.00' L = 210.31' C = 207.56' SHAWAN FALLS DR. | EX. R/W | EX. R/W SHAWAN FALLS CURVE DATA - \ CONST. SHAWAN FALLS CURVE DATA - 3-T MATCH LINE STA. 204+00 (SEE SHEET )3-WD 575 6 COMMERCIAL PARK 30.00' LT 204+33.40 35.00' LT 204+33.40 50.00' LT 205+89.23 30.00' LT 205+93.40 A B D C SAVE 26.6'P.B. 61, PG. 94 UTILITY EASEMENT & PRIVATE 10' WIDE PUBLIC SAVE SAVE CURVE DELTA RADIUS ARC LENGTH CHORD LENGTH CHORD BEARING TANGENT LENGTH PR1 307.93'56.36' ER1 405.00'55.56' PR2 425.00'89.59' ER2 405.00'62.38'62.32'31.25' RIGHT OF WAY CURVE DATA 110.87'111.48' 110.42'110.08' 176.60'175.33' SHAWAN FALLS DR. \ CONST. BED PORTION TAKE FLOWER SHRUB FLOWER BED & TAKE PORTION OF SAVE PRIVATE SIGN TAKE A B 49.50' (3-WD) 49.50' (3-WD) C LINE TABLE Bearing Distance D 50.40' (3-T) 20.53' (3-T) PR1 ER1 ER2 PR2 DRIVEEX. CONC.CONST. LIMITS 21.0' ASPHALT+52.58 | DR.30.00' LT 205+35.64 STA. 205+93.40 END ACQUISITION LIMITS CONST. STA. 106+33.00 END WORK P.B. 61, PG. 94 UTILITY EASEMENT & PRIVATE 10' WIDE PUBLIC FEDERAL GOVERNMENT OFFICE 50.00 LT 204+33.40 BRICK 2 STORY PROP. 5' SIDEWALK DEDI CATED I N P.B. 61, PG. 94SHAWAN FALLS DRI VE (60' R/W) DATE COMPLETED: 10/5/2021 REV. BY DATE DESCRIPTION BASIS FOR BEARINGS: HEAD AT 30.11 FEET LEFT OF STATION 201+96.48. OF STATION 203+83.90 AND A MAG NAIL FOUND WITH BROKEN TOP DRIVE BETWEEN A 3/4-INCH IRON PIPE FOUND AT 30.00 FEET LEFT ON THE WESTERLY EXISTING RIGHT-OF-WAY LINE OF SHAWAN FALLS A BEARING OF SOUTH 00 DEGREES 59 MINUTES 31 SECONDS EAST OHIO STATE PLANE, SOUTH ZONE, NAD83 (2011) AND DERIVING ALL BEARINGS SHOWN ARE FOR PROJECT USE ONLY. O.R. 4875 J01 A.P.N. 273-002474-00 UNITED STATES POSTAL SERVICE O.R. 16551 F20 A.P.N. 273-000788-00 LIBRARY CENTER OCLC ONLINE COMPUTER 66 66 66