Resolution No.
38 -15
Passed
A RESOLUTION ACCEPTING THE LOWI
AND BEST BID FOR THE 2015 STREE
MAINTENANCE PROGRAM, PART 1
WHEREAS, formal advertising and competitive bidding procedures have been
conducted, pursuant to Section 8.04 of the Revised Charter and Chapter 37 of the
Dublin Code, for the 2015 Street Maintenance Program, Part 1; and
WHEREAS, Council has determined that the bid submitted by Decker Construction
Company constitutes the lowest and best bid; and
WHEREAS, Council has determined that there may be a legitimate need to declare
the relocation of the utilities in connection with the above - referenced project as a
°single source" procurement, for reason that the company owning the utilities in
question has the exclusive rights to relocate such utilities.
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of Dublin,
of its elected members concurring, that:
Section 1. The bid submitted by Decker Construction Company in the total
amount of $3,548,092.15 is hereby accepted.
Section 2 . The City Manager is hereby authorized to enter into contracts with
Decker Construction Company for performance and completion of the 2015 Street
Maintenance Program, Part 1 pursuant to the Advertisement, Proposal and Contract
Documents for said project on file in the office of the City Engineer.
Section 3. This Resolution shall take effect upon passage in accordance with
Section 4.04(a) of the Revised Charter.
Passed thi day of 2015.
M or - " Presiding 0hicer
ATTEST:
Clerk of Council
Office of the City Manager
1100 Emerald Parkway • Dublin, OH 43017 -1090
City of Dublin Phone: 614 - 410 -4400 • Fax: 614 - 410 -4490
To: Members of Dublin City Council
From: Dana McDaniel, City Manager
Date: April 23, 2015
Memo
Initiated By: Paul A. Hammersmith, P.E., Director of Engineering /City Engineer
Darren A. Lee, P.E., Civil Engineer II — Design
Re: Resolution No. 38 -15
2015 Street Maintenance Program, Part 1 - Bid Acceptance
Summary
On April 20, 2015, five (5) bids were received, publicly opened and read for the 2015 Street
Maintenance Program, Part 1. The Engineer's estimate is $4,200,000. A copy of the 2015
Street Maintenance Program, Part 1 construction drawings have been placed in the Council
Planning Room for your reference and review. Part 2 of the Street Maintenance Program will
be bid separately and is planned to be presented to council for award in June 2015.
The budgeted funds in the 2015 Capital Improvement Program are $4,500,000 in ET1501,
Annual Street Maintenance Program. Decker Construction Company submitted the lowest and
best bid of $3,548,092.15. Staff has thoroughly reviewed all bids and a summary of the bids
is listed below.
Bidder
Bid as Read
Bid as Read
Over ( +) or Under ( -)
Engineer's Estimate
Corrected
Bid
Strawser Paving Company, Inc.
$3,559,516.48
- 15.25%
Shelly and Sands, Inc.
$3,891,531.32
-7.34%
Decker Construction Company
$3,542,241.27
- 15.52%
$3,548,092.15
Kokosing Construction Company, Inc.
$4,115,317.78
-2.02%
Columbus Asphalt Paving, Inc.
$4,377,078.35
4.22%
Work included in the 2015 Street Maintenance Program, Part 1 consists of roadway resurfacing
and reconstruction, roadway base stabilization, roadway spot base repair, curb and gutter
replacement, installation of compliant curb ramps and associated work. All work is scheduled
to be complete by October 9, 2015.
Streets Included for the 2015 Street Maintenance Program, Part 1
The first part of this year's program includes resurfacing on several City streets as depicted on
the attached City map. The streets to be improved are as follows:
Res. 38 -15 - 2015 Street Maintenance Program, Part 1 - Bid Acceptance
April 23, 2015
Page 2 of 3
Memorial Drive
Shady Nelms Drive
Berkshire Court
O'Connell Court
Holyrood Court
Fitzgibbon Court
Cosgray Road
Alan Moss Court
Perimeter Drive (Discovery to Commerce
Corey Swirl Drive
Pkwy)
Romero Court
Clover Court
Stover Court
Old Spring Lane
Old Pond Drive
Tara Hill Drive
Innisfree Lane
Havington Court
Innisfree Court
Downpatrick Drive (adjacent to Tara Hill Dr.)
The base stabilization and reconstruction work on Cosgray Road will require full closure of the
roadway from Shier -Rings Road to the CSX railroad tracks for about three weeks (access to
residences along Cosgray Road will be maintained). Additionally, the base stabilization, curb
and gutter replacement and reconstruction work on Tara Hill Drive will require full closure to
through traffic of the roadway in phases from Muirfield Drive to Coffman Road (access to
residences along Tara Hill will be maintained as much as possible). All other work will be
performed while maintaining traffic with all efforts being taken to minimize interruptions to
motorists, provide access for emergency services, maintain access to driveways and adjacent
streets, and consistently provide a safe work area for motorists and workers.
Communications with Residents and Motorists
The following communication methods will be used to communicate construction information
with the residents and motorists throughout the duration of this project.
• Brochures are placed on mail boxes at each residence on affected streets (see attached
brochure). These brochures are distributed by Dublin staff.
• Residents whose driveways will be closed during construction will be given written
notice at their front door at least 24 hours in advance of the closure. These are
distributed by the contractor.
• Temporary signs are placed along streets at least 24 hours in advance of construction
to notify residents and motorists of upcoming construction work and anticipated
construction dates.
• When appropriate, portable message board signs are used for construction notification
on arterial and collector streets.
• The City of Dublin Engineering Division street maintenance website implemented in
2010 gives current construction schedule information. This website is listed on the
signs posted in advance of construction activities and in the brochure placed on mail
boxes. The website is www.dubin.oh.uslengineerina
• Due to the short notification time period for driveway closures, Dublin Engineering staff
makes adjustments to the construction schedule to accommodate resident needs on a
case -by -case basis.
• Social media (e.g. Twitter, Facebook, Instagram) is used to communicate timely
construction updates.
Res. 38 -15 - 2015 Street Maintenance Program, Part 1 - Bid Acceptance
April 23, 2015
Page 3 of 3
Staff has thoroughly reviewed the bid submitted by Decker Construction Company. Previous
experience with Decker Construction Company has been favorable, including these recent
projects: Dublin Road Shared Use Path Phase 1 (2012) and Dublin Road Shared Use Path
Phase 2 (2013). Decker Construction Company has also been a sub - contractor for concrete
work on past Street Maintenance Programs.
Recommendation
Staff recommends approval of Resolution No. 38 -15, accepting the lowest and best bid of
Decker Construction Company in the amount of $3,548,092.15 and authorizing the City
Manager to enter into a contract with Decker Construction Company for this project.
CKIT
R
u++■Nf
s■' `CK �O
i
F
1
3 Y
H
O ++■ff■fna�fefffr
2
■a� kei+�lkf;H
�,1.7�•
��.
S y C
ARAN
Rp
d
O
® F��
SUMMITVI W RD
y L
f �
HARD RO
Q
9 l
�
O
O
z
O
O
-
0
0
POST
IMETE DR
0 3 11
�X
5
+
®� 6
!
' SHIER- RINGS R
7 !flfff�+■�flf�lf�
n
ff
O
7
A
rfuf�■■
+�
O
o v
FR TE PLE RD
�, S� OR
RING RD
.f�
■
V [TlE RP O
H
R
+
g
HfsH
WEST CASE
LEGEND
ROADWAY CONSTRUCTION AND PAVING
2015 STREET MAINTENANCE PROGRAM
7 ci of Dublin PART 1
1. Memorial Drive
2. Berkshire Court
3. Holyrood Court
4. Cosgray Road
5. Perimeter Drive
6. Clover Court
7. Old Spring Lane
8. Monterey Park (Parking Lot)
9. Tara Hill Drive
10. Havington Court
11. Downpatrick Drive
12. Shady Nelms Drive
O'Connell Court
Fitzgibbon Court
13. Alan Moss Court
14. Corey Swirl Drive
Romero Court
Stover Court
15. Old Pond Drive
16. Innisfree Drive
Innisfree Court
Date: 4/16/2015