A RESOLUTION ACCEPTING THE LOWEST AND BEST BID
FOR THE DUBLIN SPRING PARK SHELTER PROJECT AND
AUTHORIZING THE CITY MANAGER TO ENTER INTO A
CONTRACT FOR THE PROJECT.
WHEREAS, formal advertising and competitive bidding procedures have been
conducted, pursuant to Section 8.04 of the Revised Charter, for the Dublin
Spring Park Shelter Project ; and
WHEREAS, Council has determined that the base bid in the amount of
$104,370.00 submitted by Jess Construction is the lowest and best bid; and
WHEREAS, Dublin Spring Park Shelter Project was programmed in the
approved 2014 Capital Improvement Program (CIP); and
WHEREAS, funding is available in the Capital Projects Funds.
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of Dublin,
State of Ohio, _ of the elected members concurring, that:
Section 1 . The base bid in the amount of $104,370.00 submitted by Jess
Construction is hereby accepted.
Section 2 . The City Manager is hereby authorized to enter into a contract for
said project as specified within the bid proposal and the City's bid documents
on file in the Division of Parks & Open Space.
Section 3 . This Resolution shall take effect and be in force upon passage in
accordance with Section 4.04(a) of the Revised Charter.
Passed this day of /y(Gr�/� 2015
J
or — Presiding Officer
Attest:
cam_
Clerk of Council
r c l ityof Dublin
Office of the City Manager
5200 Emerald Parkway • Dublin, OH 43017 -1090
Phone: 614-410-4400 • Fax: 614-410-4490
To: Members of Dublin City Council
"0/1 From: Dana L. McDaniel, City Maria
Date: March 19, 2015
Initiated By: Fred Hahn, Director of Parks & Open Space
Re: Resolution 28 -15 - Dublin Spring Park Shelter Project
Summary
Memo
On Wednesday, March 4, 2015, bids were opened for the Dublin Spring Park Shelter Project.
Five (5) bids were received:
Charter -Hill Construction
Structural Erectors
OPC Contracting
Janco LLC
Jess Construction
Base Bid
$135,440.00
$155,900.00
$119,320.00
$108,840.00
$104,370.00
The funds for the Dublin Spring Park improvement were originally included in the 2014 CIP Park
Renovation budget in the amount of $120,530.00. The base bid estimate for this project was
$133,000.00. This project will be completed by the beginning of summer 2015.
The project consists of all the materials and labor necessary to completely renovate the
existing shelter while preserving its historic foundation. In addition, this project will remove the
existing asphalt path and replace it with a new concrete walk.
Jess Construction has completed multiple projects for the City of Dublin and staff has found their
work to be most satisfactory.
Recommendation
Staff recommends adoption of Resolution 28 -15, accepting Jess Construction's base bid of
$104,370.00.