A RESOLUTION ACCEPTING THE LOWEST AND BEST BID
FOR THE DARREE FIELDS NORTHWEST PARKING LOT
PROJECT AND AUTHORIZING THE CITY MANAGER TO
ENTER INTO A CONTRACT FOR THE PROJECT.
WHEREAS, formal advertising and competitive bidding procedures have been
conducted, pursuant to Section 8.04 of the Revised Charter, for the Darree Fields
Northwest Parking Lot Project; and
WHEREAS, Council has determined that the base bid in the amount of
$227,680.00, submitted Janco LLC is the lowest and best bid; and
WHEREAS, Darree Fields Northwest Parking Lot Project was programmed in the
approved 2015 Capital Improvement Program (CIP); and
WHEREAS, funding is available in the Capital Projects Funds.
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of Dublin,
State of Ohio, of the elected members concurring, that:
Section 1 . The base bid in the amount of $227,680.00, submitted by Janco LLC
is hereby accepted.
Section 2 . The City Manager is hereby authorized to enter into a contract for
said project as specified within the bid proposal and the City's bid documents on
file in the Division of Parks and Open Space.
Section 3 . This Resolution shall take effect and be in force upon passage in
accordance with Section 4.04(a) of the Revised Charter.
Passed this day of 2015
J =T1
yor — Presiding Officer
Attest:
Clerk of Council
Office of the City Manager
5200 Emerald Parkway • Dublin, OH 43017 -1090
City of Dublin Phone: 614 - 410 -4400 • Fax: 614 - 410 -4490
To: Members of Dublin City Council
From: Dana L. McDaniel, City Manage
Date: March 5, 2015
Initiated By: Fred Hahn, Director of Parks & Open Space
Re: Resolution 27 -15 - Darree Fields Northwest Parking Lot Project
Summary
Memo
On Wednesday, February 25, 2015, bids were opened for the Darree Fields Northwest Parking Lot
Project. Eight (8) bids were received:
The budget for this project is included in the 2015 CIP as a part of the $660,000 allocated for
Darree Fields improvements. The base bid estimate for this project was $339,000.00. This project
will be completed by the beginning of summer 2015.
The project consists of all the materials and labor necessary to construct a 119 -car parking lot
expansion, re -grade approximately one and one half soccer fields, and all associated storm
water related improvements. Complete construction details are available for review in the
Council Planning room.
The need for the soccer field re- grading is due to the existing grades, which makes it difficult
for players to see the full length of the field because of the height of the crown. The parking
lot expansion is needed due to the number of times each year that parking in designated areas
becomes problematic. This project was originally funded in 2011, but due to conflicts with
programmed events, it was deferred to this year.
All sports organizations impacted by these improvements were notified in 2014 to allow for
accommodations to be made in their scheduling.
Janco LLC has completed multiple projects for the City of Dublin and staff has found their work to
be most satisfactory.
Recommendation
Staff recommends adoption of Resolution 27 -15, accepting Janco LLC's base bid of $227,680.00
and authorizing the execution of contracts for the project.
Base Bid
Boss Excavating & Grading
$270,000.00
Columbus Asphalt Paving
$368,400.00
Facemyer Landscaping LLC
$232,000.00
Janco LLC
$227,680.00
Jess Construction
$255,200.00
OPC Contracting
$339,000.00
Park Enterprise Construction
$288,195.56
Strawser Paving Co., Inc.
$263,690.00
The budget for this project is included in the 2015 CIP as a part of the $660,000 allocated for
Darree Fields improvements. The base bid estimate for this project was $339,000.00. This project
will be completed by the beginning of summer 2015.
The project consists of all the materials and labor necessary to construct a 119 -car parking lot
expansion, re -grade approximately one and one half soccer fields, and all associated storm
water related improvements. Complete construction details are available for review in the
Council Planning room.
The need for the soccer field re- grading is due to the existing grades, which makes it difficult
for players to see the full length of the field because of the height of the crown. The parking
lot expansion is needed due to the number of times each year that parking in designated areas
becomes problematic. This project was originally funded in 2011, but due to conflicts with
programmed events, it was deferred to this year.
All sports organizations impacted by these improvements were notified in 2014 to allow for
accommodations to be made in their scheduling.
Janco LLC has completed multiple projects for the City of Dublin and staff has found their work to
be most satisfactory.
Recommendation
Staff recommends adoption of Resolution 27 -15, accepting Janco LLC's base bid of $227,680.00
and authorizing the execution of contracts for the project.