HomeMy WebLinkAboutResolution 009-15RECORD OF RESOLUTIONS
Dayton Legal Blank, Inc.. Form No, 30045
Resolution No.
09 -15
Passed . 20
A RESOLUTION ACCEPTING THE LOWEST AND
BEST BID FOR THE DUBLIN COMMUNITY
RECREATION CENTER GEOTHERMAL PROJECT
WHEREAS, formal advertising and competitive bidding procedures have been
conducted pursuant to Section 8.04 of the Revised Charter for installing a
geothermal system at the Dublin Community Recreation Center; and
WHEREAS, Council has determined that the bid submitted by General
Temperature Control in the amount of $449,000 constitutes the lowest and best
bid for the construction work.
NOW, THERE�BE IT RESOLVED by the Council of the City of Dublin,
State of Ohio, of the elected members concurring, that:
Section 1 . The bid submitted by General Temperature Control in the amount
of $449,000 is hereby accepted for the installation of a geothermal system at
the Dublin Community Recreation Center.
Section 2 . The City Manager is hereby authorized to enter into a contract with
General Temperature Control for said project as specified within the bid proposal
and the City's bid documents.
Section 3 . This Resolution shall take effect immediately upon passage in
accordance with Section 4.04(a) of the Revised Charter.
Passed this day of 2015
yor — Presiding O cer
Attest:
Clerk of Council
Office of the City Manager
5200 Emerald Parkway • Dublin, OH 43017 -1090
City of Dublin Phone: 614 - 410 -4400 • Fax: 614 - 410 -4490
To: Members of Dublin City Council
From: Marsha I. Grigsby, City Manager --
Date: January 22, 2015
Initiated By: Michelle L Crandall, Assistant City Manager
Brian K. Ashford, Facilities Manager
Memo
Re: Resolution 09 -15 - Accepting the Lowest and Best Bid for the Dublin Community
Recreation Center Geothermal Project
Background
On December 23, 2014, two bids were opened for the installation of a geothermal system at the
Dublin Community Recreation Center. This project will replace the two large cooling towers that
are located in the mechanical courtyard at the Recreation Center (see attached photo) with one
small facility that will house the above ground portion of the geothermal system. This enclosure
will be located where the cooling tower closest to the building is currently located, shielded behind
the wall and large wooden gates of the courtyard.
The purpose of the existing cooling towers is to remove excess heat from the water loop that
feeds two HVAC units called "chillers" which provide cooling for most of the Recreation Center.
These large tubular chillers are located inside the Recreation Center's mechanical room. In simple
terms, water flows into the two chillers which then disperse extremely cold water though pipes
throughout the building. Fans blow air over the chilled water to provide cool air to the building.
Ultimately the water comes back into the mechanical room at a much warmer temperature. The
warmer water is fed out to the cooling towers. The water temperatures are reduced in the towers
and then fed back into the cooling system. Unfortunately, a significant amount of water is lost to
evaporation in the cooling towers and thus new water must be continuously added to the cooling
system.
The geothermal system takes advantage of the huge aquifer that runs underneath Dublin to
provide the water needed to operate the chillers and ultimately cool the Recreation Center. Two
wells will be dug near the overflow parking lot. One well will serve as a backup though both may
be used on extremely hot days. The aquifer water from these wells will brought into the
mechanical courtyard through piping installed underneath the parking lot. Directional boring will
be utilized to install the underground pipes, thus the parking lot will not be disturbed.
The aquifer water will pass through heat exchanger plates housed in the mechanical courtyard and
then go into a nearby storm drain. The heat exchanger plates will then cool the water that is used
in the cooling system that feeds into the chillers. The aquifer water temperature will be raised due
to the heat transfer that occurs in the heat exchangers, but will not come into contact with any
chemicals or other contaminates.
Memo re. Resolution 09 -15
January 22, 2015
Page 2 of 2
The geothermal system will significantly reduce water consumption and requires less powerful
motors to move water throughout the cooling system. The savings from reduced water
consumption and the use of more efficient motors will result in a payback conservatively estimated
at nine years. The expected life of the system is a minimum of 25 years.
Impact on Residents and Patrons
The two wells that will be created by this project will pump approximately 300 gallons of water per
minute. A test was performed to ensure that the new wells would not negatively impact the City's
current well located next to the pond and a neighboring geothermal system owned by a residence
located on Post Road. The City hired a well pump contractor to perform a 24 hour test in which
the capacity of the City's existing well was increased to simulate the flow that will occur with the
geothermal system. The owners of the residential geothermal system graciously allowed our
contractor to monitor their well to determine if the aquifer levels changed in any significant
manner. The result of the test indicated that the two new wells would not adversely impact any
neighboring wells.
The two well systems will be almost entirely underground with approximately one foot extending
above ground. This portion of the well systems can be shielded with vegetation.
One cooling tower will remain in operation while this project is performed in late winter and early
spring. The one tower will provide sufficient cooling for the Recreation Center as the weather
starts to get warmer. The second cooling tower will not be removed until the geothermal system is
operational. Apart from fencing off a portion of the grounds area between the sidewalk and the
mechanical courtyard where the directional boring machine will be located, there should be
minimal impact on patrons entering and utilizing the Dublin Community Recreation Center.
Bid
Because this project involves almost equal amounts of work from several different disciplines (e.g.
mechanical, well digging, electrical and directional bore), few bids were anticipated. Fortunately,
General Temperature Control, a mechanical firm that has performed work at the Dublin
Community Recreation Center in the past, put together a strong team that is quite capable of
performing this project. Their bid of $449,000 is above the amount that was budgeted for the
project ($400,000) but close to our engineering consultant's revised cost estimate of $440,000.
Part of the reason for the additional cost was an added design feature that will enable a mobile
cooling tower to be utilized in the unlikely event that both of the geothermal wells fail for an
extended period of time. It is anticipated that additional budget funds will be acquired from
savings from other capital projects.
Recommendation
Staff recommends approval of Resolution 09 -15, accepting the bid submitted by General
Temperature Control in the amount of $449,000 for the installation of a geothermal system at the
Dublin Community Recreation Center. The resolution authorizes the City Manager to enter into a
contract with General Temperature Control.
IGINEERING ASSOCIATES
6130 Wilcox Road
Dublin, Ohio 43016
Phone: (614) 7664896 Fax: (614) 766 -2354
January 5, 2015
Mr. Brian K. Ashford, Facilities Manager
Facilities Division
City of Dublin
6555 Shier Rings Road
Dublin, Ohio 43016
Reference: Dublin Community Recreation Center
Geothermal Project, PEA -13390
Subject: Bid Summary and Recommendations
Dear Brian,
Bids for this project were received on December 23, 2014, for the single prime contract for this project.
The bids followed a pre -bid meeting on December 9, 2014, and an addendum that was issued on
December 18, 2014.
Apparent Low bid received is as follows:
Dublin Coymmmu *tv Recreation Center Geothermal Project Bid Results Summar
Contract
Contractor
Bid Amount
Estimate
% from estimate
Single Prime
General Temperature
Control
$449,000.00
$440,000.00
+2%
One other bid, from Gutridge Mechanical, was received, in the amount of $791,000.00.
Prater Engineering contacted the low bidder, and confirmed that the bidder is comfortable with their
bid. General Temperature is ready to proceed with the work; our "post -bid meeting" notes from
January 5, 2015 are attached. General Temperature Control's bid appears to be responsive and
responsible, and should be awarded the contract for work.
We recommend award of the single prime contract to General Temperature Control, for a lump sum
contract amount, not including contingency, of $449,000.00. Please call if you have any questions.
Respectfully submitted,
Prater Engineering Associates, Inc.
John B. Kerr, P.E., LEEDAP
,- COOLING TOWERS TO BE REMOVED
t � -
L
7
Y 1
} C
- 'i
A
Cooling Tower VS Geothermal System
Cooling Towers
Higher Horse Powered Pumps
Requires Multiple Fans
Require a lot of space
High water consumption
Noisy
Geothermal System
Lower Horse Powered Pumps
Fans Not Required
Underground
Low Water Usage
No noise
City of Dublin
Recreation Center Geothermal Project
Bid Results
General Temperature
$ 449,000.00
Gutridge Plumbing
$ 791,000.00
! .�.
� .
_ � - ■ � �$ \
.-
o�`
0 � --
/'% rw
/ ryl
■
-.� --
� .-
\�
,mac m