A RESOLUTION ACCEPTING THE LOWEST AND BEST BID
FOR THE 2014 STORM STRUCTURE MAINTENANCE PROJECT
WHEREAS, formal advertising and competitive bidding procedures have been
conducted, pursuant to Section 8.04 of the Revised Charter and Chapter 37 of the
Dublin Code, for the 2014 Storm Structure Maintenance Project; and
WHEREAS, Council has determined that the bid submitted by Columbus Asphalt
Paving, Inc. constitutes the lowest and best bid; and
WHEREAS, the 2013 Community Plan states an objective to provide safe and
efficient collection of stormwater.
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of Dublin,
of its elected members concurring, that:
Section 1. The bid submitted by Columbus Asphalt Paving, Inc. in the total
amount of $238,867.00 is hereby accepted.
Section 2 . The City Manager is hereby authorized to enter into contracts with
Columbus Asphalt Paving, Inc. for the 2014 Storm Structure Maintenance Project,
pursuant to the Advertisement, Proposal and Contract Documents for said project
on file in the office of the City Engineer.
Section 3. This Resolution shall take effect upon passage in accordance with
Section 4.04(a) of the Revised Charter.
Passed thi day of 2014.
yor - � Presidirngbfficer
ATTEST:
Clerk of Council
I cityof Dublin
Office of the City Manager
5200 Emerald Parkway • Dublin, OH 43017 -1090
Phone: 614 - 410 -4400 • Fax: 614 - 410 -4490
To: Members of Dublin City Council
From: Marsha Grigsby, City Managerv
Date: May 15, 2014
Initiated By: Paul A. Hammersmith, P.E., Director of Engineering /City Engineer
Barbara Cox, P.E., Engineering Manager — Development
Todd A. Garwick, P.E., Civil Engineer II
Memo
Re: Resolution No. 37 -14 - 2014 Storm Structure Maintenance Project —
Bid Acceptance
Summary
The second annual Storm Structure Maintenance Project specifically provides for the
maintenance, rehabilitation, and repair of structures associated with the public storm sewer
system, which includes curb and gutter inlets, catch basins and manholes throughout the
community. The annual Storm Structure Maintenance Project is a critical component of the
City's ongoing efforts to maintain Dublin's public infrastructure and meet the National Pollutant
Discharge Elimination System (NPDES) Phase II regulations.
The 2014 budgeted funds for this project are $260,000 from the Capital Improvements Tax
Fund (a portion of the $560,000 provided for annual stormwater maintenance in 2014) and
represent a bid amount for labor and material costs to repair the deficiencies in 119 storm
structures identified during inspections. Storm structure inspection data, now being collected by
City staff, may provide justification for increasing the funds programmed in the future years.
On May 1, 2014, one (1) bid was received, publicly opened and read for the 2014 Storm
Structure Maintenance Project. Columbus Asphalt Paving, Inc. provided the lowest and best bid
of $238,867.00. Staff has reviewed the bid as summarized below.
Bidder
Bid as Read
Bid as Read
over (+) or Under (-) Engineer's
Estlmate
Corrected
Bid
Columbus Asphalt Paving, Inc.
$238,867.00
-8.10%
N/A
The bid was lower than the Engineer's estimate of $260,000.00.
This 2014 Storm Sewer Structure Maintenance Project will commence in June and will be
completed by October 15, 2014. A map is attached for the work locations in various areas
throughout the City. Staff will ensure that appropriate traffic control and site restoration is
done as necessary.
Recommendation
Staff has thoroughly reviewed the bid from Columbus Asphalt Paving, Inc. and found it to be a
true and accurate cost to perform the specified work for this project. The City of Dublin has
Res. 37 -14 - 2014 Storm Structure Maintenance Project — Bid Acceptance
May 15, 2014
Page 2 of 2
previous experience with Columbus Asphalt Paving, Inc. on this type of project with very
positive results. Regarding their most recent work (as a subcontractor on the 2011 Street
Maintenance Program and performing the 2013 Storm Structure Maintenance Project), staff has
been satisfied with the performance of Columbus Asphalt Paving, Inc. and the quality of their
completed work.
Staff recommends Council approval of Resolution No. 37 -14 accepting as lowest and best the
bid from Columbus Asphalt Paving, Inc. in the amount of $238,867.00 and authorizing the City
Manager to enter into a contract with Columbus Asphalt Paving, Inc. for this project.
2
co 3 a
® �_ s
° CSf
5 off,
8 o 0 0 `
Ems.:
0 �
100 11 d a12 G 1 15
e` m
e ( CD
16 B f7 0 18
0 0 ��
g Q 19
m
Q)
20
0 0 8
I of Dublin
2014 Storm Structure
Maintenance Project
4/16/2014
Storm Structure Repair
• Storm Structure Repair
stm MapGrid2014
1 inch = 879 feet
1 2
3 4.
5 6
7 8 9
10 11 12 13 14 15
16 17181 s
19
20