HomeMy WebLinkAboutResolution 17-14RECORD OF RESOLUTIONS
Dayton Legal Blank. Inc Form No 30045
Resolution No.
17 -14
A RESOLUTION AFFIRMING KEY PUBLIC INFRASTRUCTURE
IMPROVEMENT PROJECTS IN THE SCIOTO RIVER CORRIDOR
AREA OF THE BRIDGE STREET DISTRICT AND DIRECTING
THE ADMINISTRATION TO PROCEED WITH THE FINAL
DESIGN OF VARIOUS PUBLIC IMPROVEMENTS
Passed _ 20.
WHEREAS, since 2010, the Dublin City Council has prioritized the implementation of
the Bridge Street District plan through their annual goal setting to reinforce the City's
competitiveness, create a vibrant and walkable environment with a dynamic mix of
land uses and housing types, and enhance the City's long -term sustainability; and
WHEREAS, in late 2012, Dublin City Council determined the Scioto River Corridor
area of the Bridge Street District would be the initial focus area for advancement of
the City's implementation of the Bridge Street District due to the proximity to Dublin's
vibrant Historic District, opportunities to expand access to and engage the riverfront,
the significant number of important capital projects and needs being planned for this
area, and the potential for exciting new mixed -use development projects proposed by
private development interests to establish an expanded civic core at the heart of the
Bridge Street District; and
WHEREAS, at a Joint Session of City Council and the Planning and Zoning
Commission on January 17, 2013, initial concepts for an urban design framework
were presented as a product of the Scioto River Corridor planning efforts; and
WHEREAS, the concepts for an urban design framework identified key public
projects within the Scioto River Corridor, including the realignment of Riverside Drive,
a new riverside park, a roundabout at the intersection of Riverside Drive and Bridge
Street/State Route 161, and an iconic pedestrian bridge connecting the Historic
District with the riverside park and new development opportunities on the east side of
the Scioto River; and
WHEREAS, in the spring of 2013, the City of Dublin proceeded with the preliminary
engineering and more advanced planning for these catalytic public improvements;
and
WHEREAS, the urban design framework also identified a future vehicular bridge
between the existing I -270 and Bridge Street bridges at the location of the new John
Shields Parkway intersection with Riverside Drive; and
WHEREAS, these key public improvements and urban design concepts were
reaffirmed by the Dublin City Council and incorporated into the Bridge Street District
area plan and Thoroughfare Plan within the updated Dublin Community Plan as
adopted on July 1, 2013; and
WHEREAS, the Dublin City Council approved the City's Five -Year Capital
Improvements Program on September 9, 2013, which included funding for the key
capital projects identified for the Scioto River Corridor, including the pedestrian
bridge, the State Route 161 /Riverside Drive roundabout, the realignment of Riverside
Drive, and the initial development of parkland along the Scioto River; and
WHEREAS, the Scioto River Corridor planning and design efforts have indicated that
the construction of a new north -south roadway connection from Tuller Ridge Drive to
Dale Drive is necessary as a critical prerequisite to facilitate vehicular traffic flow
during the construction of the State Route 161 /Riverside Drive roundabout; and
WHEREAS, the products and outcomes of the preliminary engineering and urban
design of the public improvements and private development concepts for the Scioto
River Corridor were shared with the public at a Community Forum held on October
22, 2013 at the OCLC Conference Center; and
RECORD OF RESOLUTIONS
Dayton Legal Blank, Inc., Forth No. 30045
17 -14
Resolution No. Passed
Page 2 of 2
WHEREAS, the Dublin City Council desires to advance these
capital projects to the preparation of final construction plans
continue implementation efforts toward realizing the plans for
District.
0
c
and other related
and drawings to
the Bridge Street
N01AI, THEREFORE, BE IT RESOLVED by the Council of the City of Dublin,
of its elected members concurring, that:
Section 1 . The Dublin City Council hereby affirms and approves the key Scioto
River Corridor capital improvements, including:
a. The location and general realignment of Riverside Drive as depicted in
EXHIBIT A, generally located from Dale Drive to Tuller Road;
b. The location and general alignment of the State Route 161 /Riverside Drive
roundabout as the preferred alternative for addressing the design and
capacity issues associated with this important intersection, as depicted in
EXHIBIT A;
c. The conceptual design and general location of landing points for an iconic
pedestrian bridge, subject to additional refinement in planning and design
studies, as depicted in EXHIBIT A; and
d. The location of a future vehicular bridge over the Scioto River as part of
future phases of John Shields Parkway, in lieu of an additional vehicular
bridge crossing adjacent to the pedestrian bridge, as depicted in EXHIBIT
A.
Section 2 . The Dublin City Council further directs the City's Administration to:
a. Proceed with the final design of the following Bridge Street District Scioto
River Corridor public improvement projects included within the current
2014 -2018 Capital Improvements Program, with design completed by the
end of 2014:
i. State Route 161 /Riverside Drive roundabout;
ii. Realigned Riverside Drive; and
iii. Grading and utilities plans for the proposed new park area
along the east side of the Scioto River.
b. Continue to evaluate and refine final design, costs, and landing options for
the Scioto River pedestrian bridge, and develop alternatives for
consideration as soon as possible.
c. Prepare options for streetscape and furnishing standards for roadways
within the Bridge Street District and finalize the authorized project designs
by the end of 2014.
d. Proceed with design of the Tuller Ridge /Dale Drive connector, as depicted
in EXHIBIT A, including preparing the final construction plans, right -of -way
acquisition documents, and advance all other related actions necessary to
initiate the construction of this key roadway connection in 2014, and
prepare for Council the appropriate amendments to the 2014 -2018 Capital
Improvement Program to include this project.
Section 3. This Resolution shall take effect upon passage in accordance with
Section 4.04(a) of the Revised Charter.
Passed this day of ' &O— rCl , 2014.
f '
yor — Presiding Cifficer
ATTEST:
Clerk of Council
I cityof Dublin
Office of the City Manager
5200 Emerald Parkway - Dublin, OH 43017 -1090
Phone: 614 - 410 -4400 - Fax: 614 - 410 -4490
To: Members of Dublin City Council
From: Marsha I. Grigsby, City Manager NAPA,
Date: March 6, 2014
Initiated By: Terry D. Foegler, Director of Strategic Initiatives /Special Projects
Memo
Re: Resolution 17 -14 Affirming Key Public Infrastructure Improvement Projects in the
Scioto River Corridor Area of the Bridge Street District and Directing the
Administration to Proceed with the Final Design of Various Public Improvements /
Bridge Street District Follow Up Items
Background
At the February 28 Goal Setting Retreat, Council discussed a number of items related to planned
public projects and emerging private development opportunities in the Bridge Street District.
Council members expressed interest in scheduling one or more work sessions to review additional
information, discuss remaining policy questions and provide further direction to staff as
implementation efforts proceed. This memo outlines the major topics for consideration as follow up
discussion items and provides recommendations on prioritization and timing for addressing these
topics.
Design Expectations
Council expressed a desire to develop tools and /or processes to help better communicate and align
Bridge Street District planning and design expectations among key participants in the development
process (project developers /designers, staff, Planning and Zoning Commission and Council). Staff
recommends that Council hold a work session to establish shared expectations for project design
and architecture in key locations within the Bridge Street District. To provide clear and timely
direction for applicants currently moving through the development review process and for others
interested in pursuing near term development opportunities, staff recommends a work session be
held as soon as is convenient for Council. Staff will be prepared to offer potential meeting dates for
Council's consideration at the March 10"' Council meeting.
Project Review for Development Agreements
Due to the amount of public street infrastructure necessary to create the grid system in the Bridge
Street District, most of the key private development projects will require partnerships with the City
in order to move forward. City Council will thus have substantial discretion to provide significant
oversight regarding which projects achieve the City's goals and vision for the BSD and therefore
should be advanced through City partnership. For this reason, it is appropriate to ensure early
Council understanding and general support of proposals that will involve development agreements
with the City, prior to extensive planning and design investment by prospective applicants.
Opportunities for such Council input and reaction are not currently provided within existing
development review procedures for the BSD. To facilitate an efficient and predictable review
Memo re. Bridge Street District Work Sessions
March 6, 2014
Page 2 of 2
process, staff will prepare options to better incorporate Council into the early stages of the
process, and will present these for Council's consideration at an upcoming meeting.
As noted above, because there are currently development applications moving through the
established review process, staff recommends that City Council schedule a work session in the
coming weeks, in lieu of a more formal Council review process that will be proposed.
Public Projects
At its Retreat, Council discussed the scope and timing of major public infrastructure improvements,
primarily located in the Scioto River Corridor planning area, as well as other portions of the street
network that will be constructed with individual private development projects. As part of that
discussion, Council directed staff to prepare a resolution affirming key public infrastructure
improvements and directing the Administration to proceed with final design of those projects.
Resolution 17 -14 is attached to this memo for Council consideration.
In addition, staff will provide information at future meetings on the progress of other facets of
planned public improvements planning efforts, including:
• An overview of the Bridge Street District Transportation Phasing Plan (nearing completion)
• Illustrative simulation showing how the Riverside /SR 161 roundabout will function
• Creation of streetscape character and furnishings standards for new streets in the BSD (this
is necessary to complete the final design of the new public streets)
• Additional refinement of the pedestrian bridge design and potential construction methods
• Maintenance of traffic plans related to the realignment of Riverside Drive and construction
of Riverside /SR 161 roundabout
• Remaining land acquisitions need to construct new roadways
Staff recommends presenting this information as it becomes available as an agenda item at regular
Council meetings. If Council prefers, separate work sessions can subsequently be scheduled to
focus on one or more of these items in greater depth.
Recommendation
Staff recommends adoption of Resolution 17 -14 at the March 10"' Council meeting. Staff also
recommends Council schedule its first work session within the next month to provide timely
direction of architectural and design expectations for pending development proposals. Staff will
follow up with additional information regarding the other items noted in this memo, and will
schedule additional work sessions as directed.