HomeMy WebLinkAboutResolution 033-19RECORD OF RESOLUTIONS
Dayton Legal Blank, Inc., Form No. 30045
Resolution No. 33-19 Passed , 20
A RESOLUTION ACCEPTING THE LOWEST AND BEST BID FOR THE
DUMFRIES COURT EAST HYDRAULIC DISCONNECT PROJECT
WHEREAS, formal advertising and competitive bidding procedures have been
conducted, pursuant to Section 8.04 of the Revised Charter and Chapter 37 of the
Dublin Code, for the Dumfries Court East Hydraulic Disconnect project; and
WHEREAS, Council has determined that the bid submitted by Complete General
Construction Company on May 29, 2019, constitutes the lowest and best bid.
NOW, THE EFORE, BE IT RESOLVED by the Council of the City of Dublin, State
of Ohio, of its elected members concurring that:
Section 1. The bid submitted by Complete General Construction Company in the
total amount of $468,497.50 is hereby accepted.
Section 2. The City Manager is hereby authorized to enter into contracts with
Complete General Construction Company for performance and completion of the
Dumfries Court East Hydraulic Disconnect project pursuant to the Advertisement,
Proposal and Contract Documents for said project on file in the office of the City
Engineer.
Section 3. This Council further hereby authorizes and directs the City Manager,
the Director of Law, the Director of Finance, the Clerk of Council, or other appropriate
officers of the City to prepare and sign all other agreements and instruments and to
take any other actions as may be necessary to implement this Resolution and
complete the Project.
Se 'on 4. This R olution shall take effect upon passage in accordance with
S tion 4.04(a) oft Revised Charter.
r
Pas ped his Ja 2019.
�ayor —Presiding Officer
TTEST:
Clerk of Council
Office of the City Manager
5200 Emerald Parkway * Dublin OH 43017-1090
Cityof Dublin Phone: 614.410.4400 a Fax: 614'.410.4490 VEL.Aft
i4it WRin"s
—MeRNIV
To: Members of Dublin City Council
From Dana L. McDaniel, Cty Mani qer'�io"#r&
Date: June 4, 2019
Initiated By: Paul A. Hammersmith, PE, Director of Engineering/City Engineer
Todd A. Garwick, P.E., Senior Civil Engineer
Re: Resolutloon No,. 33-19 — BI"d Acceptance for Dumfir"Ies Court East
Hydraulik Disconnect Project
Resolution No. 33-19- — Bid Acceptance for Dumfries Court East Hydraulic Disconnect Project
June 4, 2019
Page 2 of 2
there were rock excavation, bypass pumping, depth of construction and manhole construction
method concerns,
For the second bid opening (re -bid) for this project on May 29, 2019, Complete General Construction
Company submitted the lowest and best bid of 1468,497.50. Staff has reviewed the bid and a
summary of the bid received is listed below.
Staff has thoroughly reviewed the bid submitted by Complete General Construction Company on May
29, 2019. Previous experience with Complete General Construction Company has been favorable,
including these recent projects: Hyland -Croy Road/Post Road Interim Traffic Signal Upgrade, Frantz
Road/Bradenton Avenue Traffic Signal Upgrade, and North High Street Widening. Staff is confident
Complete General �-onstructlon Company will perform well on this project.
Staff recommends Council approval of Resolution No. 33-19 accepting as lowest and best the bid of
Complete General Construction Company in the amount of $468,497.50 and authorizing the City
Manager to enter into a contract with Complete General Construction Company for this project.