HomeMy WebLinkAboutResolution 030-16RECORD OF RESOLUTIONS
30 -16
Resolution No. P"sed
A RESOLUTION ACCEPTING THE LOWEST AND BEST
BID FOR THE GLICK ROAD SHARED -USE PATH —
SECTION 1 PROJECT
]u _
WHEREAS, formal advertising and competitive bidding procedures have been
conducted, pursuant to Section 8.04 of the Revised Charter and Chapter 37 of the
Dublin Code, for the Glick Road Shared -Use Path — Section 1 Project; and
WHEREAS, Council has determined that the bid submitted by Danbert, Inc.
constitutes the lowest and best bid; and
WHEREAS, Council has determined that there may be a legitimate need to declare
the relocation of the utilities in connection with the above - referenced project as a
"single source" procurement, for reason that the company owning the utilities in
question has the exclusive rights to relocate such utilities.
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of Dublin,
of its elected members concurring, that:
Section 1. The bid submitted by Danbert, Inc. in the total amount of $822,908.50
is hereby accepted.
Section 2. The City Manager is hereby authorized to enter into contracts with
Danbert, Inc. for performance and completion of the Glick Road Shared -Use Path —
Section 1 pursuant to the Advertisement, Proposal and Contract Documents for said
project on file in the office of the City Engineer.
Section 3. This Resolution shall take effect upon passage in accordance with
Section 4.04(a) of the Revised Charter.
—2016.
ATTEST:
Clerk of Council
Office of the City Manager
5200 Emerald Parkway � Dublin, QH 43017 -1090
U �.� Phase; 614 - 410.4400 s Fax; 614 - 410 -4490
To: Members of Dublin City Council 1 01
Frain; Dana L McDaniel City Mana
Dates May 19, 2016
Initiated By: Paul A, Hammersmith, P.E., Director of Engineering/City Engineer
Kenneth B. Richardson, P.E., P,S,, Senior Civil Engineer
Rey Resolution Na, 34 -16
Glick Road Shared-Use Path -- Section I -Bid Acceptance
Summary
On May 11, 2016, five (5) bids were received, publicly opened and read for the Glick Road Shared -
Use Path -- Sectian 1 project, This project involves the WHO tructian of 3,Q00 feet of eight -fact wide
asphalt shared -use path along the south side of Glick Road between Davington Drive and Muirfield
Drive, The majority of the shared -use path replaces the existing private Muirfield Association six -foot
wide asphalt trail and will be located on Muirfield Association reserve areas and the Country Club at
Muirfield Village properties, In addition to building the shared -use path, this project also
rehabilitates two pedestrian tunnels under Glick Road that were built over 30 years ago,
The Engineer's estimate is $780,000, The budgeted funds for this construction project are in the
2016 Capital Improvement Program (CIP) and are $415,000 in ET1204 and $216,000 (tunnel
maintenance) in AT1608, Danbert, Inc, submitted the lowest and best bid of $822,908,50, Staff
has reviewed ail bids and a summary of the bids is listed below,
For Councii's reference and review, a reduced set of project construction drawings has been placed
in the Councii Planning Room,
The higher bids above our Engineer's estimate can be attributed to the cast -in -place retaining wall
and tunnel repairs exceeding our estimate by $55,OOQ. Our estimate was $310,000 and Danbert's
bid, far the cast -in -place retaining wail and tunnel repairs, was $365,000. The need to minimize the
time of tunnel closures and the aggressive construction schedule likely caused a premium to the bid,
Staff believes Danbert's bids for these items are reasonable,
Bid as Read
� Bidder
Bid as Read
Over ( +) or Under (-)
Engineer's Estimate
Corrected Bid '
� Danbert, Inc,
$822,9Q8.50
+5.5%
� Strawser Paving Company, Inc,
$834,291,36
+7.0%
Double 2 Construction
$$99,978,25
+15.4 ° /a
� a
s
Columbus Asphalt Paving, Inc,
$935,391J5
+199%
Shelly &Sands, Inc
$1,019,33380
+30,7 ° /a
For Councii's reference and review, a reduced set of project construction drawings has been placed
in the Councii Planning Room,
The higher bids above our Engineer's estimate can be attributed to the cast -in -place retaining wall
and tunnel repairs exceeding our estimate by $55,OOQ. Our estimate was $310,000 and Danbert's
bid, far the cast -in -place retaining wail and tunnel repairs, was $365,000. The need to minimize the
time of tunnel closures and the aggressive construction schedule likely caused a premium to the bid,
Staff believes Danbert's bids for these items are reasonable,
Res, 30 -16 •Glick Road Shared -User Path — Section 1 Bid Acceptance
May 19, 2016
Page 2 of 2
Staff anticipates the construction to commence in mid -June 2016. Glick Road will remain open to
trafFc far the duration of the CO The planned completion date far the project is
September 30, 2016. The existing Muirfield Association's path along the south side of Glick Road will
be closed with appropriate barricades for the duration of the construction period A temporary
crosswalk will be provided across Glick Road at each tunnel location for use when the tunnels are
closed due to construction work. Staff has coordinated with the Country Club at Muirfield Village an
time periods far tunnel closures.
Staff held a public involvement meeting with the neighborhood residents adjacent to this project on
Wednesday, May 41 2016 at Deer Run Elementary School There were 9 residents in attendance.
The overall feedback was positive and the discussion mainly revalued around why the change from
the private trail to a public path and details about the location of the shared -use path.
Recommendation
Staff has thoroughly reviewed the bid from Danbert, Inc. Previous experience with Danbert has
been favorable, including these recent projects; Waterford Village 5tormwater Improvements
Areas 4 and 5; 2015 Stormwater Maintenance Program; and ZQ1S Sanitary Sewer Maintenance
Program, Staff recommends Council approval of Resolution 3Q -16, accepting as lowest and best the
bid of Danbert, Inc. in the amount of $822,908,50 and authorizing the City Manager to enter into a
contract with Danbert, Inc. for this project.